In many parts of India, high tension (HT) lines passing over residential or agricultural properties raise serious safety concerns for homeowners and farmers. A common question arises: High Tension Line Hataane Ki Power Permanent Lok Adalat Ka Pass Hai Ya Nahi? (Does the Permanent Lok Adalat have the power to remove high tension lines or not?). This issue often stems from disputes with electricity providers over safety violations, negligence, or property rights.

This blog post breaks down the legal position based on key judgments and statutes. We'll explore the Permanent Lok Adalat's (PLA) jurisdiction, its limitations, and why statutory authorities typically hold the real power for such orders. Note: This is general information and not specific legal advice. Consult a qualified lawyer for your case.

Understanding Permanent Lok Adalat (PLA) and Its Role

The Permanent Lok Adalat, established under the Legal Services Authorities Act, 1987 (as amended), primarily handles disputes related to public utility services, including electricity supply. Its main goal is to promote speedy resolution through conciliation (settlement talks). If parties agree, the PLA passes an award based on that compromise.

However, if conciliation fails, the PLA can decide the dispute on merits—but only under strict conditions. According to key legal findings, 2019 0 Supreme(Raj) 3065, The Permanent Lok Adalat, while conducting conciliation proceedings or deciding a dispute on merit under this Act, be guided by the principles of natural justice, objectivity, fair play, equity and other principles of justice and shall not be bound by the Code of Civil Procedure, 1908 and the Indian Evidence Act, 1872.

Importantly, the PLA's powers are limited. It cannot handle disputes involving criminal offences or non-compoundable offences, such as negligence under the Electricity Act, 2003. 2019 0 Supreme(Raj) 3065

Does PLA Have Jurisdiction Over HT Line Removal?

Generally, no. The PLA does not have the authority to directly order the removal of high tension lines as an adjudicatory measure, especially in cases involving safety hazards, negligence, or violations of the Electricity Act.

Key Limitations on PLA's Power

  • Conciliation-First Approach: PLA first attempts settlement. Only if it fails can it adjudicate, but not for offences. 2019 0 Supreme(Raj) 3065
  • No Override of Statutes: PLA cannot issue orders contrary to laws like the Electricity Act or safety regulations. For instance,

    The Principal, vs Sathiya Moorthy - Madras

    states, The Permanent Lok-Adalat has no power to pass orders which are contrary to the University Statute. This principle extends to infrastructure like HT lines, where removal must comply with regulatory norms.
  • Civil Disputes Only: Purely civil matters within monetary limits may be decided, but safety/negligence claims often involve criminal elements, pushing them outside PLA's scope. 2022 0 Supreme(SC) 480

In 2022 0 Supreme(SC) 480, courts clarified that PLA's powers are confined, and it cannot issue orders that amount to criminal or safety enforcement actions. Instead, statutory bodies like the Electrical Inspectorate or State Electricity Regulatory Commission (SERC) enforce HT line safety standards.

Why Statutory Authorities Hold the Power

Under the Electricity Act, 2003, and related rules (e.g., Indian Electricity Rules, 1956), HT lines must follow safety clearances. Removal or re-routing requires:1. Safety inspections by licensed authorities.2. Compliance with minimum clearances (e.g., 3.7m for 11kV lines over buildings).3. Approval from distribution licensees or regulators.

The PLA's role is dispute resolution, not regulatory enforcement. 2022 0 Supreme(SC) 480 2019 0 Supreme(Raj) 3065 emphasize that orders for HT line alterations rest with these bodies after due process.

Supporting this, other cases reinforce PLA's boundaries:- 2025 Supreme(Online)(Chh) 10652: Argues that powers like declarations under specific acts are exclusive to civil courts, not PLA, as the said power has exclusively been vested on the Civil Court.-

The South Bihar Power Distribution Company Limited Vs Sunderi Devi - Patna

: The Lok Adalat/Permanent Lok Adalat can pass orders only on the basis of compromise entered between the parties.

Thus, without a mutual settlement, PLA cannot mandate removal.

Exceptions: When PLA Might Intervene

Rarely, if parties settle via conciliation—including agreement on line removal—and it doesn't violate statutes, PLA can pass an award. But even then:- It must align with public policy and Electricity Act.

The Principal, vs Sathiya Moorthy - Madras

- Disputes barred by limitation or involving unwilling parties limit options. 2024 Supreme(Online)(Mad) 86330: When one of the parties to the dispute is not willing, automatically the Permanent Lok Adalat will pass appropriate Orders in the light of the National Legal Services Authority Act.

For monetary claims (e.g., compensation for safety fears), PLA may award if civil and within limits (up to ₹1 crore). But structural removal? No.2017 5 Supreme 150

Insights from Additional Case Law

Further precedents highlight PLA's facilitative, not authoritative, role:- 2022 Supreme(Online)(Bom) 4923: PLA passes awards in terms thereof only post-agreement.-

HDFC ERGO GENERAL INSURANCE COMPANY LTD. Vs SUJATA CHHABRA AND ANOTHER - Punjab and Haryana

: High Courts won't interfere if PLA's view is reasonable, but won't expand its powers.-

AVVNL AJMER AND ORS vs SHANKAR LAL AND ANR - Rajasthan

: PLA decisions must scan evidence but stay within jurisdiction.

These align with the core finding: PLA facilitates, doesn't enforce infrastructure changes like HT line removal.

Practical Recommendations for Affected Parties

If HT lines endanger your property:- Step 1: File complaints with the electricity discom and Electrical Inspector for safety audit.- Step 2: Approach SERC or Consumer Grievance Redressal Forum (CGRF).- Step 3: Try PLA for conciliation on compensation/power supply issues, but expect referral elsewhere for removal.- Step 4: Escalate to civil courts or High Court writs for safety violations.

Key Takeaway: Attempt PLA for amicable settlement, but for binding removal orders, statutory routes are essential. 2019 0 Supreme(Raj) 3065 2022 0 Supreme(SC) 480

Conclusion: PLA's Role is Limited

In summary, the Permanent Lok Adalat generally lacks the power to order high tension line removal. Its jurisdiction focuses on settling public utility disputes via conciliation, not adjudicating safety enforcement or overriding Electricity Act mandates. Statutory authorities and courts are the proper forums for such actions.

Final Note: Always verify with local regulations, as outcomes depend on facts. For personalized guidance, contact a legal expert.

Key Takeaways

  • PLA excels in settlements, not standalone removal orders.
  • Electricity Act bodies handle HT line safety and relocation.
  • Criminal/negligence elements bar PLA adjudication. 2019 0 Supreme(Raj) 3065
  • Mutual compromise is the only PLA pathway for related awards.

References

  1. 2022 0 Supreme(SC) 480: Limits PLA to non-enforcement roles.
  2. 2019 0 Supreme(Raj) 3065: Defines PLA scope excluding offences.
  3. 2017 5 Supreme 150: Public utility jurisdiction without enforcement.
  4. The Principal, vs Sathiya Moorthy - Madras

    , 2025 Supreme(Online)(Chh) 10652, etc.: Reinforce statutory limits.
#PermanentLokAdalat #HTLinesRemoval #ElectricityLaw
Chat Download
Chat Print
Chat R ALL
Landmark
Strategy
Argument
Risk
Chat Voice Bottom Icon
Chat Sent Bottom Icon
SupremeToday Portrait Ad
whatsapp-icon Back to top