SUPREME COURT OF INDIA
A.N. RAY, C.J.I., M.H. BEG AND JASWANT SINGH, JJ.
Ramdas Oil Mills, Appellant
Versus
Union of India (Military Deptt.), Respondent.
Civil Appeal No. 1871 of 1968
D/- 7-12-1976.
Defence of India Act, 1939 - Section 19 – Claim of compensation - Compensation for damages to building - Appeal arises out of an award passed by District Judge as an arbitrator under Section 19 of Defense of India Act, 1939 - Property of the appellant was requisitioned - He claimed compensation - Matter was referred to arbitrator - Before arbitrator the appellant claimed compensation under several heads amounting to Rupees - Two important claims were first compensation for damages to building was assessed by appellant and second interest was claimed – Held, High Court reduced the award of arbitrator under head damages to building - High Court also reduced the claim Iron Water Pipes from allowed by arbitrator - High Court disallowed interest - Counsel for the appellant pressed really these three claims - Court are unable to accept the submission of appellant - High Court rightly disallowed the major part of claim of compensation for damages to building and also for G. I. Water Pipes - Principal reason given by the High Court is that account books were maintained in respect of construction and repairs to the building by the appellant but no such accounts were produced - It is also said by the High Court that the appellant did not produce account books which would have shown the length of pipes used for running the mills - It is well settled that if a person does not produce account books which are in his possession an adverse inference can be drawn for non-production thereof - A claim for interest is not a matter of right - It is also well settled that interest by way of damages cannot be awarded - High Court rightly disallowed interest which had been awarded by arbitrator - Appeal dismissed
Judgment
A. N. RAY, C.J.I. :- This appeal is by certificate from the judgment dated 27 November 1967 of the Patna High Court.
2. The appeal arises out of an award dated 1 March 1962 passed by the District Judge of Singhbhum at Chaibassa as an arbitrator under Section 19 of the Defence of India Act, 1939 (hereinafter referred to as the Act).
3. The property of the appellant was requisitioned. He claimed compensation. The matter was referred to the arbitrator.
4. Before the arbitrator the appellant claimed compensation under several heads amounting to Rupees 1,07,130. The two important claims were first, compensation for damages to building was assessed by the appellant at Rs. 34,000 and second, interest was claimed for Rs. 15,216.
5. The other heads under which the appellant claimed compensation were for Galvanised iron Water Pipes at Rs. 20,000 and compensation for removal of entire electric wirings and fittings at Rupees 20,000.
6.The arbitrator awarded Rs. 10,000 as compensation for damages to building. He also gave interest slightly in excess of the amount claimed. He also awarded a sum of Rs.8,000 for Galvanised Iron Water Pipes.
7. An appeal was preferred to the High Court by the Government. An appeal lies to the High Court under Section 19(1) (f) of the Act.
8. It has been held by this Court in Collector of Varanasi v. Gauri Shankar Misra, 1968-1 SCR 372 that the High Court in hearing an appeal under Section 19 of the Act acts as an appellate Court and not as a Court hearing an application for setting aside an award.
9. The High Court reduced the award of the arbitrator from Rs.10,000/- to Rs. 6,545/- under the head damages to building. The High Court also reduced the claim for Galvanised Iron Water Pipes from Rs. 8,000/- allowed by the arbitrator to Rs. 2,556.62. The High Court disallowed the interest.
10. Counsel for the appellant pressed really these three claims. We are unable to accept the submission of the appellant. The High Court rightly disallowed the major part of the claim of compensation for damages to building and also for G. I. Water Pipes. The principal reason given by the High Court is that account books were maintained in respect of construction and repairs to the building by the appellant but no such accounts were produced. It is also said by the High Court that the appellant did not produce account books which would have shown the length of the pipes used for running the mills. It is well settled that if a person does not produce account books which are in his possession an adverse inference can be drawn for non-production thereof. (See Seth Maganmal Since Deceased v. Darbarilal Chowdhry reported in 47 Cal LJ 222 at page 230 where the Judicial Committee observed to that effect.
11. A claim for interest is not a matter of right. It is also well settled that interest by way of damages cannot be awarded. The High Court rightly disallowed interest which had been awarded by the arbitrator.
12. For these reasons the appeal fails and is dismissed. There will be no order as to costs.
Appeal dismissed.
For Citation : AIR 1977 SC 638
Vikas Info Solutions Pvt. Ltd.
The main legal point established in the judgment is the binding effect of the settlement between the parties, the waiver of the right to seek re-employment by the workmen, and the entitlement of the ....
A lockout is justified if it is declared in response to an illegal strike or a strike that is in breach of a settlement or award.
The combination of eyewitness testimonies, recovery of the weapon used, and forensic examination results can establish guilt in criminal cases, even based on circumstantial evidence.
The conviction of an accused person under Section 27(3) of the Arms Act is not permissible in law if the accused is also charged with committing murder under Section 302 of the Indian Penal Code.
The court can enhance compensation based on the deceased's income and family dependency, and adjust the multiplier used by the Tribunal if found unjustified.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.