SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1989 Supreme(SC) 199

SUPREME COURT OF INDIA
R.S. PATHAK CJI., SABYASACHI MUKHARJI AND SHARMA, JJ.
J. and K. State Forest Corporation, Appellant
Versus
Abdul Karim Wani and others Respondent
Civil Appeal No. 2121 OF 1989 arising out of Spl Leave Petn (Civil) No. 7804 of 1987)
Decided on 31-3-1989

Advocates:
Altaf Ahmed, E.C.AGARWAL, PLIRNIMA BHAT, S.K.BHATTACHARJEE, S.N.KACKAR

Headnote:

Arbitration Act – Section 20 and 2(a) - Claim compensation – Forest activities - This appeal by special leave is directed against judgment and order of the High Court - Respondent filed an application for referring certain matters alleged to be in dispute to an independent arbitrator; and that for last 15 years respondent had been working as a contractor for appellant Corporation and was carrying on various activities in different forest areas in Jammu Province, including felling, machine sawing, pathroo, paccinali, rope span, mahan and transportation - It is stated that said Corporation issued tenders for felling, handsawing, pathroo, paccinali and mahan work of timber to be extracted from compartment - In response thereto the petitioner to original application being respondent, submitted his quotation and offered the lowest rate and thereby secured the contract - A formal agreement was also executed between the parties - After about 7 months from issuance of first work order the appellant Corporation through its General Manager (Extraction) issued a sanction for further quantity sawn volume in compartment on the same rate, terms and conditions as contained in the original contract - Whether there was any subsisting arbitration agreement in respect of matters sought to be referred – Held, By interim order High Court permitted plaintiff to execute additional work claimed by him without waiting for award - On the quashing of the main order of reference, interim order automatically disappears, but court would, like to briefly indicate the scope of Courts power to issue interim orders at time of reference of a dispute to arbitration, and point out how in present case High Court was in grave error in granting the interim relief - It has been averred before us on behalf of the plaintiff - Respondent that all the trees in question were cut down, and so the plaintiff must be permitted to complete the remaining work including their transportation to the destination - Learned counsel for the Corporation placed reliance on the statements in several affidavits and contended that if entire circumstances including period which could have been available to respondent for the purpose of felling the trees, are examined, there is no escape from the conclusion that the respondent had felled the trees or majority of them after service of the stay order passed by this Court - Court do not think it necessary to examine and decide this controversy as in court view the respondent, in facts and circumstances of this case, cannot take any advantage from or claim compensation for the hurried steps he alleges to have taken under the strength of the illegal order interim in nature, which court are setting aside - In the result, the appeal is allowed - Impugned judgment of the High Court is set aside and the respondents application filed before High Court for reference is dismissed - Respondent shall pay the costs of this Court and of the High Court to the appellant-Corporation - Order accordingly.

JUDGMENT

SABYASACHI MUKHARJI, J.— (Minority view):- I have read the judgment proposed to be delivered by L. M. Sharma, J. with which the learned Chief Justice has agreed. With great respect, I am unable to agree with them on the view that there was no arbitration agreement subsisting covering the dispute in question between the parties. It is, therefore, necessary to refer to certain facts, as I view these.

2. This appeal by special leave is directed against the judgment and order of the High Court of Jammu & Kashmir, dated 4th June, 1987. The Jammu & Kashmir Forest Corporation is the appellant. The undisputed facts leading to this appeal are that one Abdul Karim Wani, the respondent No. 1, filed an application for referring certain matters alleged to be in dispute to an independent arbitrator; and that for the last 15 years the respondent had been working as a contractor for the appellant Corporation, namely, Jammu & Kashmir Forest Corpn. and was carrying on various activities in different forest areas in Jammu Province, including felling, machine sawing, pathroo, paccinali, rope span, mahan and transportation.

3. It is stated that in February, 1986 the said Corporation issued tenders for felling, handsawing, pathroo, paccinali and mahan work of timber to be extracted from compartment No. 59 Marwah. In response thereto the petitioner to the original application being the respondent herein, submitted his quotation and offered the lowest rate of 11.74 per cft. and thereby secured the contract. A formal agreement was also executed between the parties. In October, 1987 after about 7 months from the issuance of first work order the appellant Corporation through its General Manager (Extraction) issued a sanction for further quantity of 2 lac cft. sawn volume in compartment No. 59 Marwah, on the same rate, terms and conditions as contained in the original contract. The sanction appears at pages 26 & 28 of the present appeal papers before us.

4. It appears that the total marking carried out in compartment No. 59 was 10,08,000 cft. standing out of which only 6 lac cft. was sanctioned in favour of the respondent. The compartment in question is at a distance of over 70 kms. from the nearest road point and the timber extracted from the compartment had to travel by pathroo, paccinali and mahan through Chenab river for a total distance of 80 kms before it is collected at loading point of Dedpeth.

5. It is further the case of the respondent that "as per the procedure, practice, custom and assurances extended to the respondent by the appellant Corporation through its functionaries, from time to time," the entire marking conducted in a particular compartment for extraction was required (emphasis supplied) to be handed over to the respondent in compartment No. 59. As regards sale, it is suggested that as the compartment is situated in one of the remotest area of Jammu province where making arrangements for extraction of timber including cartage/carriage of foodgrains, saws, tools and implements is very difficult, it was never intended that the balance work remaining in the compartment for extraction would be given to any other contractor.

6. The case of the respondent is that acting upon the assurances and representations of the appellant Corporation that the entire work in the aforesaid compartment would be handed over to him, the respondent had made adequate arrangements after investing Rs. 5 lacs by way of provision for rations, saws, tools and implements etc. All these arrangements at that scale were necessary and were made just to extract entire marked timber from the compartment in question and not just initially tendered quantity. That would have been wholly uneconomical.

7. It was further asserted that there was also the practice in the Corporation that once a compartment was handed over to the contractor for work, it was taken back from him only after the entire available work in the said compartment stood concluded. The contractor further














































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top