SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2014 Supreme(SC) 106

SUPREME COURT OF INDIA
SURINDER SINGH NIJJAR, FAKKIR MOHAMED IBRAHIM KALIFULLA, JJ.
Enercon (India) Ltd. & Others – Appellants
Versus
Enercon GMBH & Another – Respondents
Civil Appeal No. 2086 of 2014 (Arising Out Of SLP (C) No. 10924 of 2013) with Civil Appeal No.2087 of 2014 (Arising out of SLP (C) No. 10906 of 2013)
Decided On : 14-02-2014

IMPORTANT POINTS
Issue of concluded contract should be left to the Arbitral tribunal.
Arbitration agreement is Independent of main contract.
Seat of arbitration and venue of arbitration are different and choice of Curial law decides the seat.
Anti-suit injunction: factors to be considered.

Headnote:(a) Indian Contracts Act, 1872 – Sections 14 to20 r/w section 44, Arbitration and Conciliation Act, 1996 – Contract can be declared nullity on grounds of coercion, fraud or misrepresentation – No pleadings to that effect – Issue of concluded contract should be left to the Arbitral tribunal. (Para 75)

       (1975) 1 SCC 199; [1953] 1 WLR 280; [1965] 1 W.L.R. 1025; [1976] 1 WLR 591; (1968) 3 SCR 387; (2006) 1 SCC 751 – Referred

       (b) Arbitration and Conciliation Act, 1996 – Section 16 – Arbitration agreement – Materials on record clearly showing parties’ intention and agreement for arbitration in case of dispute – Existence or otherwise of a concluded contract becomes irrelevant in such situation – Severability – Arbitration clause forming part of a contract is an agreement independent of the contract – Arbitration agreement will not perish on non-finalisation of IPLA – Parties must proceed with arbitration – All difficulties can be addressed by arbitrator. (Para 77 to 81)

       (2012) 2 SCC 93; 2013 (7) SCALE 327 – Relied upon

       (2013) 1 SCC 641 – Referred

       (c) Company law – A company and the person holding 100% share of that Company cannot be two independent licensors. (Para 82)

       (d) Arbitration and Conciliation Act, 1996 – Section 7 – Arbitration clause – Interpretation – seemingly unworkable clause – Duty of court – To make the same workable within permissible limits – Court ought to adopt the attitude of a reasonable business person – Arbitration clause cannot be construed with a purely legalistic mindset, as if construing a statutory provision. (Para 83)

       [1985] 1 AC 191; (2009) 2 SCC 55; (2009) 4 SCC 495 – Relied upon

       (2009) 1 SCC 267 – Referred

       (e) Arbitration and Conciliation Act, 1996 – Section 44 – Officious bystander principle – Arbitral agreement providing for each party to nominate its arbitrator – Provision for appointment of third and presiding arbitrator – omission is so obvious that Court should supply the missing line. (Para 85)

       1937 S. 1835; (2006) 2 SCC 628 – Relied upon

       (f) Arbitration and Conciliation Act, 1996 – Sections 7, 8, 10 and 11 – Machinery provision – Parties free to determine number of arbitrators, which should not be even – Intention to go to arbitration can be gathered from correspondence, e-mails, statement of claims pleadings etc. – Instantly parties can be permitted to proceed to arbitration. (Para 88)

       AIR 1997 SC 605 – Relied upon

       (2007) 5 SCC 719; (1980) 4 SCC 556 – Referred

       (g) Arbitration and Conciliation Act, 1996 – Section 7 – ‘Venue’ and ‘seat’ of arbitration – Parties agreeing that provisions of the Act contained in chapters IV to VI would apply – By choosing Part I of the Act, parties made a choice for seat of arbitration in India – Further, parties agreeing to applicability of Indian law of contract, law governing the arbitration agreement and the law of arbitration/Curial law – Venue cannot be read as seat. (Para 90, 95, 105)

       1988 (1) Lloyd’s Rep 116; (2012) 9 SCC 552; [1970] 1 Lloyd’s Rep. 269: [1970] A.C.583]; [1981] 2 Lloyd’s Rep. 446; [2008]EWHC 426 (TCC) – Relied upon

       (h) Arbitration and Conciliation Act, 1996 – Section 20(1) and 20(3) – Parties agreeing that curial law will be the Arbitration and Conciliation Act, 1996 – Provision of section 20(3) applies. (Para 96)

       (19993) 2 Lloyd’s Rep 48; Sulame Rica – Relied upon

       (2012) 9 SCC 552 – Distinguished

       [1984] AC 398 – Referred

       (i) Arbitration and Conciliation Act, 1996 – Section 7 – Seat of arbitration – Choice of Curial law decides the seat. (Para 110)

       [2007] EWCA Civ 1282 – Relied upon

       (2009) 2 LLR 376 – Referred

       (j) Arbitration and Conciliation Act, 1996 – Section 7 – Seat of arbitration – ‘Close and most intimate connection’ – Arbitrations are anchored to the seat/place/situs of arbitration – All proceedings of arbitration need not be held at the seat of arbitration – Can be held at a place convenient to the parties – Seat of arbitration remains in India although the venue may be in London. (Para 125)

       (2012) 9 SCC 552; (19993) 2 Lloyd’s Rep 48; [2008] EWHC 426 (TCC); 1988 (1) Lloyd’s Rep 116 – Relied upon

       (k) Arbitration Laws – Seat and jurisdiction – Once seat is fixed in India, it would have exclusive jurisdiction to exercise the supervisory powers over the arbitration – Courts in England cannot have concurrent jurisdiction. (Para 128, 130, 136)

       [1984] AC 398; (2012) EWHC 3711(Comm); (2012) 9 SCC 552; (2009) 2 LLR 376; [2007] 1 Lloyds Report 237 – Relied upon

       (2010) 1 SCC 83; (1995) 6 SCC 571; (2011) 6 SCC 179; (2011) 6 SCC 161; (2011) 9 SCC 735 – Referred

       (l) Anti suit Injunction – Appellant’s prayer for anti-suit injunction granted by Daman Trial court – Seat of arbitration is in India – Parties are Indian and German – They have agreed on applicability of India Laws – Parties have participated in proceedings in India – Assets are in India – Injunction rightly granted against suit in English courts. (Para 143)

       1987 SCR (1) 10241987 SCR (1) 1024; (2003) 4 SCC 341; (2006) 9 SCC 41; (2005) 7 SCC 791 – Relied upon

       Facts of the case:

       Appellants No.2 and 3 and the Respondent No.1 entered into a joint venture business by setting up the Appellant No. 1-Company –Enercon (India) Ltd. (“EIL”), in 1994 having its registered office at Daman, to manufacture and sell Wind Turbine Generators (“WTGs”) in India. In furtherance of their business venture, the parties entered into various agreements.

       The Appellants claim that Respondent No.1, in February, 2007, unilaterally decided to stop all shipments of supplies to India in order to pressurize them to sell the share holding as desired by Dr. Wobben. However in March, 2007, after discussions between the parties, Respondent No.1 resumed supplies. Thereafter, the supplies were stopped once again in July, 2007 resulting in litigation.

       Respondent company invoked arbitration clause contained in IPLA agreement and appointed an arbitrator. The appellants denied the agreement and the arbitration clause. The Appellant also filed a suit in Daman court for declaration that there is no valid arbitration clause between the parties. However Appellant no. 1 appointed an arbitrator but both the arbitrators failed to agree on the third and presiding arbitrator.

       The litigation ended with the appellants filing writ petitions which the High Court dismissed.

       Finding of the Court:

       Seat of arbitration is India.

       

JUDGMENT :

Surinder Singh Nijjar, J.

1. Leave granted.

2. These civil appeals have been filed against the order and judgment dated 5th October, 2012, passed by the Bombay High Court in CWP Nos.7804 of 2009 and 7636 of 2009. The Bombay High Court by the impugned order dismissed both the aforesaid Civil Writ Petitions.

3. Appellants No.2 and 3 (members of the Mehra family) and the Respondent No.1 (a company incorporated under the laws of Germany, having its registered office at Aurich, Germany) entered into a joint venture business by setting up the Appellant No. 1-Company –Enercon (India) Ltd. (hereinafter referred to as “EIL”), in 1994. EIL, having its registered office at Daman, was to manufacture and sell Wind Turbine Generators (“WTGs”) in India. One Dr. Alloys Wobben is the Chairman of the Respondent No.1. Respondent No.2, a company incorporated under the laws of Germany, has the patent of technology in connection with the aforesaid WTGs. In furtherance of their business venture, the parties entered into various agreements, which can be briefly noticed:

Share Holding Agreement:

4. On 12th January, 1994, the Appellant Nos. 2 and 3 entered into a Share Holding Agreement (“SHA”) with the Respondent No.1. In terms of the SHA, the Respondent No. 1 was to hold 51% shares of the Appellant No. 1-Company, and the Appellant Nos. 2 and 3, collectively, were to hold 49% shares.

Technical Know How Agreement:

5. On the same day, i.e. 12th January, 1994, the Appellant No. 1 and the Respondent No. 1 entered into a Technical Know-How Agreement (“TKHA”) by which the Respondent No. 1 agreed to transfer to the Appellant No. 1 the right and the technical know-how for the manufacture of WTGs specified therein and their components. Under the terms of the TKHA, the Respondent No. 1 has to supply special components to the Appellant No. 1. Under the TKHA, the Respondent No. 1 is the licensor and the Appellants are the licensees.

Supplementary Shareholding Agreements:

6. The SHA was subsequently amended by two Supplementary Share Holding Agreements (“SSHAs”) dated 19th May, 1998 and 19th May, 2000. Pursuant to the said SSHAs, the shareholding of Respondent No. 1 in the Appellant No. 1-Company increased to 56% whilst the shareholding of the Appellant Nos. 2 and 3 was reduced to 44%.

Supplementary Technical Know-How Agreement:

7. A Supplementary Technical Know-How Agreement (“STKHA”) amending the TKHA was executed on 19th May, 2000, by which a further license to manufacture the E-30 and E-40 WTGs was granted by the Respondent No. 1 to the Appellants.

Heads of Agreement:

8. In April 2004, the period of the TKHA expired; however, the Respondent No. 1 continued to supply the WTGs and components to the Appellant No.1. At this stage, there were discussions between the parties about the possibility of a further agreement which would cover future technologies developed by Respondents. On 23rd May, 2006, these negotiations were recorded in a document titled “Heads of Agreement”.

Agreed Principles:

9. On 29th September, 2006, the Appellants and the Respondent No. 1 entered into what is known as the "Agreed Principles" for the use and supply of the windmill technology. The second page of the Agreed Principles, inter alia, provides as follows:

“The Agreed Principles as mentioned above, in their form and substance, would be the basis of all the final agreements which shall be finally executed.

The agreed principles shall be finally incorporated into the

A. IPLA “Draft enclosed”

B. Successive Technology Transfer Agreement

C. Name Use Licence Agreement

D. Amendment to Existing Share Holding Agreement.

The above agreements will be made to the satisfaction of all parties. And then shall be legally executed.” IPLA (dated 29th September, 2006):

10. On the same day, i.e. 29th September, 2006, Intellectual Property License Agreement (“IPLA”) was executed between the parties. It appears that Appellant No.2 has signed the IPLA on behalf of the Appellants No. 2 and 3. However, the Appellants have























































































































































































































































































































































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top