SUPREME COURT OF INDIA
(From the High Court of Jharkhand at Ranchi)
HEMANT GUPTA, V. RAMASUBRAMANIAN, JJ.
M/s. N.G. Projects Limited – Appellant
Versus
M/s. Vinod Kumar Jain and Others – Respondents
Civil Appeal No. 1846 of 2022, SLP (Civil) No. 2103 of 2022
Decided On : 21-03-2022
(A) Government Contract – Tender – Cancellation of tender and fresh NIT issued – Interference in contract awarded to appellant is wholly unwarranted and has caused loss to public interest – Construction of roads is an essential part of development of infrastructure in any State – Single Bench and Division Bench of High Court were exercising power of judicial review to find out whether decision of State was manifestly arbitrary or unjust – Courts should not use a magnifying glass while scanning tenders and make every small mistake appear like a big blunder – Courts must give fair play in joints to Government and public sector undertakings in matters of contract – Courts must also not interfere where such interference would cause unnecessary loss to public exchequer – Ground reality today is that almost no tender remains unchallenged – Unsuccessful parties or parties not even participating in tender seek to invoke jurisdiction of High Court under Article 226 of Constitution – Authority that authors tender document is the best person to understand and appreciate its requirements and its interpretation should not be second-guessed by a court in judicial review proceedings – Question as to whether a term of contract is essential or not is to be viewed from perspective of employer and by employer. (Paras 10, 13, 16 and 17)
(B) Constitution of India – Article 226 – Specific Relief Act, 1963 – Section 41 – Cancellation of tender and fresh NIT issued – Satisfaction whether a bidder satisfies tender condition is primarily upon authority inviting bids – Such authority is aware of expectations from tenderers while evaluating consequences of non-performance – Since construction of road is an infrastructure project and keeping in view intent of legislature that infrastructure projects should not be stayed, High Court would have been well advised to hold its hand to stay construction of infrastructure project – Such provision should be kept in view even by Writ Court while exercising its jurisdiction under Article 226 of Constitution of India – It is not the case of writ petitioner that action of Technical Evaluation Committee was actuated by extraneous considerations or was malafide – On same set of facts, different conclusions can be arrived at in a bona-fide manner by Technical Evaluation Committee – Since view of Technical Evaluation Committee was not to liking of writ petitioner, such decision does not warrant for interference in a grant of contract to a successful bidder – Writ Court should refrain itself from imposing its decision over decision of employer as to whether or not to accept bid of a tenderer – Court does not have expertise to examine terms and conditions of present day economic activities of State and this limitation should be kept in view – Courts should be even more reluctant in interfering with contracts involving technical issues as there is a requirement of necessary expertise to adjudicate upon such issues – If Court finds that there is total arbitrariness or that tender has been granted in a malafide manner, still Court should refrain from interfering in grant of tender but instead relegate parties to seek damages for wrongful exclusion rather than to injunct execution of contract – Injunction or interference in tender leads to additional costs on State and is also against public interest – Action of respondent in setting aside letter of acceptance granted to appellant suffers from manifest illegality and cannot be sustained – Appeal disposed of with a direction to respondent State to allow appellant to resume and complete work by excluding period spent in stay of execution of contract – Any contract of public service should not be interfered with lightly and in any case, there should not be any interim order derailing entire process of services meant for larger public good. (Paras 21, 22, 23, 25 and 26)
Facts of the case:
Challenge in the present appeal is to an order dated 6.1.2022 passed by Division Bench of the High Court of Jharkhand at Ranchi whereby appeal filed by the State against the order of Single Bench allowing the Writ Petition No. 5416 of 2019 was dismissed.
Findings of Court:
Multiple layers of exercise of jurisdiction also delay final adjudication challenging the grant of tender. Therefore, it would be open to the High Courts or Hon’ble Chief Justice to entrust these petitions to a Division Bench of the High Court, which would avoid at least hearing by one of the forums.
Result : Appeal disposed of with directions.
ORDER :
1. The challenge in the present appeal is to an order dated 6.1.2022 passed by the Division Bench of the High Court of Jharkhand at Ranchi whereby the appeal filed by the State against the order of the learned Single Bench allowing the Writ Petition No. 5416 of 2019 was dismissed.
2. The Special Leave Petition came up for hearing before this Court on 7.3.2022, when the following order was passed:
“Leave granted.
The appeal is allowed.
The appellant shall be permitted to complete the project but will not claim escalation for the period the matter was pending before the Court.
The writ petition before the High Court is dismissed.
Detailed Judgment/Order to follow.”
3. The Road Construction Department of Jharkhand invited tenders on 7.6.2019 for reconstruction of Nagaruntari-Dhurki-Ambakhoriya Road. Respondent No. 1 participated in the tender process and also submitted Bank Guarantee as bid security but such tender was cancelled on 20.8.2019 and fresh Notice Inviting Tender1 [for short the ‘NIT’] was invited for reconstruction of the said Nagaruntari-Dhurki-Ambakhoriya road.
4. The Tender Evaluation Committee held a meeting for technical evaluation of bids and 13 out of 15 bids were held to be non-responsive in terms of Standard Bidding Document 2 [for short the ‘SBD’] including that of respondent No. 1. The reason for arriving at such conclusion was that respondent No. 1 submitted a letter along with the amended Bank Guarantee to the effect that such letter forms an integral part of Bank Guarantee. Such Bank Guarantee was not in the format as prescribed in the SBD. It was also found that the Bank Guarantee was valid from 8.7.2019 to 7.3.2020, which was prior to the date on which NIT was issued on 20.8.2019, apart from the fact that the amount mentioned in numerical and in words were different. Still further, the bid capacity of respondent No. 1 amounting to Rs. 60.66 crores was less than the estimated cost of work of Rs. 1,05,71,13,019/-. Additionally, the affidavit and undertaking supporting the bid were not properly notarized.
5. The technical bid of the appellant was declared to be substantially responsive and after due evaluation of its financial bid, work contract was issued to the appellant on 3.10.2019. The appellant started the work on the stipulated date of commencement on 22.10.2019 and completed earth work for 21.9 kms out of the 24 kms proposed road. As per the appellant, it had completed work of approximately Rs. 8.5 crores and had mobilized the plants and machinery to Garwa.
6. Respondent No. 1 filed a Writ Petition on 11.10.2019 for quashing of the decision of the Technical Evaluation Committee holding its bid to be non-responsive.
7. The State in its counter affidavit has taken the following objections:
(i) State could not have accepted the amended bank guarantee as it had conditions beyond what was stipulated in the format.
(ii) An amendment changes the prescribed format.
(iii) By abundant caution, the Bank was asked to verify the said Bank Guarantee but there has been no reply as on date.
(iv) NIT is of 20.8.2019 but the Bank Guarantee is from 9.7.2019 to 8.3.2020.
(v) The undertaking and affidavit has not been duly notarized.
(vi) Bid Capacity is also negative.
(vii) The other tender referred to in the writ has since been cancelled.
(viii) Financial details of bid cannot be known till opening of the bid.
8. After the pleadings were completed, the learned Single Bench of the High Court passed a common order in respect of two other works and the work in question on 14.1.2020, setting aside award of contract granted to the appellant. The learned Single Bench of the High Court passed the following directions:
“48. Under the aforesaid facts and circumstances, all the writ petitions are disposed of by passing following orders:
(i) xxx xxx xxx
(ii) The decision of the Tender Committee dated 3rd October, 2019, for the work, namely, “Reconstruction of Nagaruntari-Dhurki-Ambakhoriya Road (MDR-139)” in relation to W.P. (C) No. 541
Tata Cellular v. Union of India
Central Coalfields Limited & Anr. v. SLL-SML (Joint Venture Consortium) & Ors.
Afcons Infrastructure Limited v. Nagpur Metro Rail Corporation Limited & Anr.
Silppi Constructions Contractors v. Union of India and Ors.
National High Speed Rail Corpn. Ltd. v. Montecarlo Ltd.
(1) Tender – Courts must give fair play in joints to Government and public sector undertakings in matters of contract – Courts must also not interfere where such interference would cause unnecessary ....
The interpretation of eligibility criteria in public tenders is best determined by the tendering authority, and judicial review is limited to preventing arbitrariness or mala fides.
The court emphasized the need for judicial restraint in interfering with tender processes, especially in matters involving technical issues, and highlighted the limitations of the court's expertise i....
Point of law: Supreme Court held that any contract of public service should not be interfered with lightly and in any case, there should not be any interim order derailing entire process of services ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.