SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(SC) 449

SUPREME COURT OF INDIA
L. NAGESWARA RAO, B.R. GAVAI, JJ.
Chhattisgarh State Power Distribution Company Ltd. – Appellant
Versus
Chhattisgarh State Electricity Regulatory Commission and Another – Respondents
Civil Appeal Nos. 2578-2579, 2868, 2941-2942 of 2008
Decided On : 12-05-2022

Advocates:
Advocate Appeared:
For the Appellants : Nikhil Nayyar, Apoorv Kurup.
For the Respondents: Naveen R. Nath, Manish Paliwal, Vikas Kumar, Nikhil Shama, Anirudha Bhat, Swapna Seshadari, Pramod Dayal.

The main legal point established in the judgment is the fulfillment of the conditions for a power plant to qualify as a 'Captive Generating Plant' as per the provisions of the Electricity Act, 2003 and Rule 3 of the Electricity Rules, 2005, and the statutory support for the establishment of captive power plants provided by the National Electricity Policy, 2005.

Headnote:

APPEALS - Electricity - Electricity Act, 2003, Rule 3 of Electricity Rules, 2005 - The court discussed the provisions of the Electricity Act, 2003 and Rule 3 of the Electricity Rules, 2005, which define the conditions for a power plant to qualify as a 'Captive Generating Plant'. The court also referred to the National Electricity Policy, 2005, which provides for the establishment of captive power plants to secure reliable, quality, and cost-effective power and to facilitate the creation of employment opportunities through the efficient growth of industry.

Fact of the Case:

M/s Shri Bajrang Power and Ispat Ltd. established a Captive Generation Plant and sought permission to wheel power to its sister concern, M/s Shri Bajrang Metallics and Power Ltd. The Chhattisgarh State Electricity Regulatory Commission rejected the appellant's contention, leading to appeals before the Appellate Tribunal for Electricity.

Finding of the Court:

The court found that the conditions for a power plant to qualify as a 'Captive Generating Plant' were fulfilled by the appellant, as per the provisions of the Electricity Act, 2003 and Rule 3 of the Electricity Rules, 2005. The court also noted that the National Electricity Policy, 2005, supports the establishment of captive power plants to secure reliable, quality, and cost-effective power and to facilitate the creation of employment opportunities through the efficient growth of industry.

Issues: The issues revolved around the entitlement of M/s Shri Bajrang Power and Ispat Ltd. to supply electricity to its sister concern and the interpretation of the provisions of the Electricity Act, 2003 and Rule 3 of the Electricity Rules, 2005.

Ratio Decidendi: The court held that the conditions for a power plant to qualify as a 'Captive Generating Plant' were fulfilled by the appellant, as per the provisions of the Electricity Act, 2003 and Rule 3 of the Electricity Rules, 2005. The court also emphasized the statutory flavor of the National Electricity Policy, 2005, which supports the establishment of captive power plants.

Final Decision: The court dismissed the appeals, finding them without merit.

JUDGMENT :

B.R. GAVAI, J.

1. These appeals challenge the judgment dated 6th December 2007 passed by the Appellate Tribunal for Electricity (hereinafter referred to as the “APTEL”) thereby dismissing the appeals filed by the present appellant.

2. The facts in brief giving rise to the present appeals are as under:

    M/s Shri Bajrang Power and Ispat Ltd. (hereinafter referred to as “SBPIL”) has established a Captive Generation Plant. M/s Shri Bajrang Metallics and Power Ltd. (hereinafter referred to as “SBMPL”) is a sister concern of SBPIL. SBPIL submitted a petition to the Chhattisgarh State Electricity Regulatory Commission (hereinafter referred to as “the Commission”) for providing open access and wheeling of power through the transmission system of the appellant for captive use by SBMPL. The petition of the SBPIL was for permission to wheel 19 lakh units, corresponding to 13 MW, to SBMPL. It was stated in the said petition that SBMPL holds 27.6% of the equity shares of SBPIL and that more than 51% of the electricity generated by the captive power plant would be consumed by them. It was submitted that the generating capacity of the captive generation plant set up by SBPIL would be 103.68 MU per annum. It was further submitted that out of the said 103.68 MU per annum power generated, 13.22 MU per annum would be utilized in its sponge iron plant. It was further submitted that 54 MU per annum would be supplied to SBMPL through the appellant grid and the balance would be sold to the appellant.

3. The said petition came to be resisted by the appellant. It was contended by the appellant that SBPIL holds more than 72% of the shares of the company. However, its consumption would be limited only to 14.16% (13.22 MU), whereas the consumption of SBMPL holding 26.67% shares, would be 57.87% (54 MU). It was submitted that this was not proportionate to the ownership of the power plant.

4. The Commission, vide its order dated 14th October 2005, rejected the contention of the appellant and held that SBPIL was entitled to supply electricity to its sister concern SBMPL and the same would qualify to be treated as ‘own consumption’ within the ambit of Section 9 read with Section 2(8) of the Electricity Act, 2003 (hereinafter referred to as “the said Act”) and Rule 3 of the Electricity Rules, 2005 (hereinafter referred to as “the said Rules”). While allowing the said petition, the Commission imposed the following conditions:

    “(i) The consumption of electricity by the captive users shall not be less than 51% over a financial year, and in case it is not so it would be treated as ‘supply of electricity by a generating company’ in terms of provision of Rule 3(2) of the Rules.

    (ii) The CSEB is entitled to charge for wheeling of electricity and levy other charges as per their present rates which shall be subject to revision as per the provisions in regulations on the charges for open access to be notified by the Commission shortly.

    (iii) The company may enter into necessary agreement with the CSEB for the sale of balance power under the present terms and conditions of the CSEB, is subject to revision as per the directions of the Commission from time to time.”

5. Being aggrieved thereby, the appellant preferred appeals before the APTEL. The said appeals came to be dismissed by the APTEL vide impugned judgment dated 6th December 2007. Being aggrieved thereby, the present appeals.

6. We have heard Shri Nikhil Nayyar, learned Senior Counsel appearing on behalf of the appellant and Shri Naveen R. Nath, learned Senior Counsel and Smt. Swapna Seshadari, learned counsel appearing on behalf of the respondents.

7. Shri Nayyar submitted that the order passed by the Commission and the impugned judgment passed by the APTEL are contrary to the plain language used in Rule 3 of the said Rules. He submitted that SBMPL is a sister concern of SBPIL which has established the captive power plant. It is submitted that unless SBPIL consumes 51% of the aggregate electricity generated by


Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top