SUPREME COURT OF INDIA
INDIRA BANERJEE, KRISHNA MURARI, JJ.
Sepco Electric Power Construction Corporation – Appellant
Versus
Power Mech Projects Ltd. – Respondent
Civil Appeal No. 6789 of 2022, SLP (C) Nos. 4511, 5322 of 2021
Decided On : 19-09-2022
(A) Arbitration and Conciliation Act, 1996 – Sections 9 and 36 – Stay of operation of arbitral award – There is no hard and fast rule that application made earlier in point of time must be heard before application made later in point of time – Both applications under Section 9 filed by Respondent and application for stay under Section 36(2) filed by Appellant relate to same impugned award – Even though, applications may be independent applications, there are common factors required to be considered for both applications of Respondent under Section 9 and application of Appellant under Section 36(2) – Jurisdiction of this Court under Section 9 is wide – A party may apply to a Court for interim measures before commencement of Arbitral proceedings, during Arbitral proceedings or at any time after the making of Arbitral Award, but before it is enforced in accordance with Section 36 of Arbitration Act – For grant of interim relief under Section 9, Court would have to consider prima facie case – In this case, prima facie there is award for huge amount of Rs. 142 Crores against Appellant – Respondent has a strong case for interim relief. (Paras 21, 22, 23 and 25)
(B) Civil Procedure Code, 1908 – Order 41, Rule 5 – Arbitration and Conciliation Act, 1996 – Sections 9 and 36 – Stay of operation of arbitral award – Under Section 36, where time for making application to set aside arbitral award has expired, award might be enforced in accordance with provisions of CPC in same manner as it were a decree of Court – Section 9 of Arbitration Act confers wide power on Court to pass orders securing amount in dispute in arbitration, whether before commencement of arbitral proceedings, during arbitral proceedings or at any time after making of arbitral award, but before its enforcement in accordance with Section 36 of Arbitration Act – All that Court is required to see is, whether applicant for interim measure has a good prima facie case, whether balance of convenience is in favour of interim relief as prayed for being granted and whether applicant has approached court with reasonable expedition – Order 41 Rule 5 of CPC provides for stay of decree upon furnishing of cash security – High Court acted within scope of its powers under Section 9 in passing impugned judgment and order – Appeals dismissed. (Paras 27, 28, 34, 36 and 37)
Facts of the case:
Appellant, an entity incorporated in China was awarded contracts in relation to various coal based power projects in India and Respondent, a company incorporated in India was engaged as a sub-contractor of Appellant. Disputes and differences between Respondent and the Appellant were referred to Arbitration. Arbitration culminated in an Award dated 17th October 2017 of approximately Rs. 1,42,00,00,000/- in favour of the Respondent.
Findings of Court:
High Court requested to dispose of the pending applications of the Appellant under Section 34 for setting aside the award as expeditiously as possible, preferably within 3 months from date of communication of this judgment and order.
Result : Appeals dismissed.
JUDGMENT :
INDIRA BANERJEE, J.
1. Leave granted.
2. The Appellant, an entity incorporated in China was awarded contracts in relation to various coal based power projects in India and the Respondent, a company incorporated in India was engaged as a subcontractor of the Appellant. Disputes and differences between the Respondent and the Appellant were referred to Arbitration. Suffice it to mention that the Arbitration culminated in an Award dated 17th October 2017 of approximately Rs. 1,42,00,00,000/- (Rupees One Hundred and Forty Two Crores) in favour of the Respondent.
3. On 3rd December 2017, the Appellant filed an application under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the “Arbitration Act”) being O.M.P. (COMM) No. 432 of 2017 challenging the Arbitral Award dated 17th October 2017 in the Commercial Division of the Delhi High Court, which is pending.
4. On the same day, that is, 3rd December 2017, the Appellant filed an interim application being I.A. No. 14342 of 2017 in the said O.M.P. (COMM) No. 432 of 2017 under Section 36(2) of the Arbitration Act seeking stay of the arbitral award.
5. After about a week, on 11th December 2017, the Respondent filed an application under Section 9 of the Arbitration Act being O.M.P. (I) (COMM) No. 523 of 2017 in the High Court, inter-alia, seeking orders on the Appellant to furnish security against the amount awarded by the Arbitral Tribunal.
6. On 14th December 2017, the High Court issued notice in the application filed by the Respondent under Section 9 of the Arbitration Act and directed the Appellant to file an affidavit of assets. In compliance with the order dated 14th December 2017, the Appellant submitted its affidavit giving details of its assets.
7. On or about 10th May 2018, the Respondent filed an application being I.A. No. 6704 of 2018 praying for deposit of the entire amount due from Talwandi Sabo Power Corporation Limited (TSPL). The said application was disposed of by an order dated 15th May 2018 with the observation that the Court did not see sufficient cause to allow the prayers made by the Respondent.
8. By an order dated 24th July 2018, the High Court directed the Appellant to disclose better particulars of its assets in India. In the meanwhile, the Appellant was directed to deposit 10% of the amount in its bank accounts, which is referred to in its affidavit of assets in the High Court at intervals of every 15 days.
9. Pursuant to the aforesaid order dated 24th July 2018, the Appellant filed its supplementary affidavit of assets. Two days later, on 20th August 2018, the Respondent filed an application being I.A. No. 11128 of 2018 for directions on the Respondent to deposit the awarded amount of Rs. 142,41,14,499/- (Rupees One Hundred Forty-Two Crores, Forty One Lakhs, Fourteen Thousand, Four Hundred Ninety-Nine Only) along with interest @ 12% per annum from the date of the award till realisation of the awarded amount in the High Court.
10. Diverse interim applications were filed from time to time. On 20th March 2019, the Respondent filed another application being I.A. No. 4259 of 2019, seeking orders for deposit of the awarded amount of Rs. 142,41,14,499/- along with interest.
11. By a judgment and order dated 17th February 2020, a Single Judge of the High Court disposed of the application filed by the Respondent under Section 9 of the Arbitration Act being O.M.P. (I) (COMM) No. 523 of 2017 along with connected interim applications. The operative part of the judgment and order dated 17th February 2020 is set out herein-below:
33. Si
Ajay Singh & Ors. v. Kal Airways Private Limited and Ors.
The main legal point established in the judgment is the discretion of the court to direct the petitioner to furnish security on the full arbitral award and the impact of the Arbitration and Conciliat....
Arbitration awards, lacking jurisdiction, do not equate to money decrees; interim relief granted during appeal pending jurisdictional determinations.
The award holder can seek interim relief under Section 9 of the Arbitration and Conciliation Act, 1996 until the complete satisfaction of the award.
Point of Law : Since the award was a money decree there should be 100% deposit with respondent being entitled to withdraw amount deposited and furnish solvent security to the satisfaction of High Cou....
An unconditional stay of an arbitral award is impermissible unless specific statutory conditions under Section 36(3) of the Arbitration Act are fulfilled.
Automatic suspension of execution of the award, the moment an application challenging the said award is filed under section 34 of Act leaving no discretion in court to put parties on terms, in court ....
The court emphasized that the conditions for stay of an arbitral award should not differ based on whether a party is a statutory body, reinforcing the principle of equal treatment under the Arbitrati....
The main legal point established in the judgment is the maintainability of an appeal under section 37(1)(b) of the Arbitration & Conciliation Act, 1996, and the need for clear authority of law for th....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.