1. Dispute over compensation for domestic coal shortfall following the introduction of the SHAKTI Policy, alleged as a Change in Law under Power Purchase Agreements. (Para 1 , 2 , 3 , 4 , 5 , 6 )
2023 Supreme(SC) 387
SUPREME COURT OF INDIA
B.R. GAVAI, VIKRAM NATH, JJ.
Maharashtra State Electricity Distribution Company Limited - Appellant
Versus
Adani Power Maharashtra Limited And Another - Respondents
Civil Appeal Nos. 677-678 of 2021
Decided On : 20-04-2023
Important Points
Subject
Civil Law - Electricity Dispute
Act Referred
Electricity Act, 2003
Headnote
Fact of the Case:
The case involved appeals challenging a judgment related to Change in Law compensation under PPAs due to the introduction of SHAKTI Policy.Finding of the Court:
The court dismissed MSEDCL's appeal and upheld APML's appeal, affirming that SHAKTI Policy constitutes a Change in Law event.Issues:
The court addressed various issues including whether SHAKTI Policy amounts to Change in Law, computation of change in law compensation, advance intimation requirement, and entitlement to carrying cost.Ratio Decidendi:
The court applied the principle that any change resulting in a cost impact on selling electricity constitutes a Change in Law event. It also emphasized restitutionary principles for compensating affected parties.Final Decision:
The court dismissed the appeals and upheld APTEL's decision.Legal Category Hierarchy
Table of Contents
2. Whether the SHAKTI Policy constitutes a Change in Law, whether mandatory notice was served, and whether carrying costs are permissible under restitutionary principles. (Para 11 , 12 , 13 , 14 )
3. The SHAKTI Policy reduces assured coal quantity, triggering Change in Law provisions and the restitutionary principle to restore the affected party's economic position. (Para 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 31 , 32 , 33 , 34 )
4. Modification of coal distribution policies reducing assured quantity constitutes a Change in Law, entitling the generator to restitutionary compensation and carrying costs. (Para 22 , 25 , 32 )
5. Appeals dismissed; the judgment and order of the Appellate Tribunal for Electricity are upheld. (Para 35 )
6. Does the SHAKTI Policy amount to a Change in Law under Power Purchase Agreements?
Yes. Because the SHAKTI Policy reduces the Assured Coal Quantity (ACQ) compared to the 2007 NCDP, it constitutes a Change in Law, entitling the generating company to compensation. (Para 22 , 23 , 26 , 27 )
7. What is the legal principle for calculating compensation for a Change in Law event?
The restitutionary principle applies, which creates a legal fiction to restore the affected party to the same economic position as if the Change in Law had not occurred. (Para 24 , 25 )
8. Is a generator entitled to carrying costs for the period between the Change in Law event and the Commission's approval?
Yes. Carrying costs are allowable based on the principle of restitution to restore the party to its rightful economic status from the effective date of the event until approval. (Para 31 , 32 )
9. To what extent can courts interfere with the decisions of expert bodies like APTEL or CERC?
Courts should be slow to interfere unless the expert body failed to consider mandatory statutory provisions, relied on extraneous considerations, or the decision is ex-facie arbitrary and illegal. (Para 33 , 34 )
JUDGMENT :
(B.R. Gavai, J.)
1. The present appeals challenge the judgment and order dated 28th September 2020 passed by the Appellate Tribunal for Electricity (hereinafter referred to as ‘APTEL’), in cross appeals being Appeal No. 116 of 2019, filed by Maharashtra State Electricity Distribution Company Limited (hereinafter referred to as ‘MSEDCL’), the appellant herein, and Appeal No. 155 of 2019, filed by ADANI Power Maharashtra Limited (hereinafter referred to as ‘APML’), respondent No. 1 herein, thereby challenging the order dated 7th February 2019, passed by Maharashtra Electricity Regulatory Commission (hereinafter referred to as ‘MERC’).
2. The facts, in brief, giving rise to the present appeals are as under:
APML and MSEDCL had entered into four long term Power Project Agreements (hereinafter referred to as ‘PPA’) dated (a) 8th September, 2008 for 1320 MW (hereinafter referred to as ‘1320 MW PPA’); (b) 31st March, 2010 for 1200 MW (hereinafter referred to as ‘1200 MW PPA’); (c) 9th August, 2010 for 120 MW (hereinafter referred to as ‘120 MW PPA’) and (d)16th February, 2013 for 440 MW (hereinafter referred to as ‘440 MW PPA’), pursuant to the competitive bidding process conducted by MSEDCL.
3. APML, being aggrieved by the Change in Law on account of the Ministry of Coal bringing into force the New Coal Distribution Policy, 2013 (hereinafter referred to as ‘NCDP, 2013’), which revised the arrangements prescribed under New Coal Distribution Policy, 2007 (hereinafter referred to as ‘NCDP, 2007’) for supply of coal, had filed a petition being Case No. 189 of 2013, seeking compensation in Tariff on account of Change in Law under the PPAs before MERC. Finally, in the light of the judgment of this Court in the case of Energy Watchdog v. Central Electricity Regulatory Commission and Others , (2017) 14 SCC 80, the said petition, after being remanded by the APTEL, was heard afresh by the MERC.
4. Vide order dated 7th March, 2018, the MERC allowed the claims of APML on account of Change in Law due to changes brought about by NCDP, 2013. APML, thereafter, preferred a review petition, being Review Petition No. 167 of 2018 seeking extension of Change in Law relief for domestic coal shortfall beyond March, 2017 on account of changes introduced by the Scheme for Harnessing and Allocating Koyala (Coal) Transparently in India (hereinafter referred to as ‘SHAKTI Policy’) which had been released by the Ministry of Power on 22nd May, 2017. As per Clause 6.1 of the SHAKTI Policy, the Appropriate Commission was required to consider the cost of imported/market based e-auction coal procured for making up the shortfall in the domestic coal for pass-through.
5. The MERC dismissed the said review petition. However, liberty was granted to APML to file a fresh petition to seek extension of Change in Law relief for domestic coal shortfall beyond March, 2017 in view of the introduction of the SHAKTI Policy. Subsequently, APML filed a fresh petition, being Case No. 290 of 2018, before the MERC seeking relief in support of Change of Law under the respective PPAs for non-availability/short supply of domestic coal under SHAKTI Policy after March, 2017.
6. The MERC, vide its order dated 7th February 2019, allowed the petition and granted relief for Change in Law due to the promulgation of SHAKTI Policy. However, the relief was directed to be computed on the same methodology and parameters as approved by the MERC vide its order dated 7th March, 2018. Cross appeals were filed before the APTEL by APML and MSEDCL against the aforesaid order.
7. The learned APTEL framed the following five issues for adjudication :
| “Issue No.1:- | Whether introduction SHAKTI Policy does not amount to Change in Law under the PPAs entered into between APML and MSEDCL and whether APML has not provided notice of such Change in Law to the Respondent MSEDCL. |
| Issue No.2:- | Whether the MERC is correct in holding that for the purpose of Change in Law compensation, sho |