SUPREME COURT OF INDIA
B.R. GAVAI, VIKRAM NATH, JJ.
GMR Warora Energy Limited – Appellant
VERSUS
Central Electricity Regulatory Commission (CERC) & Ors. – Respondents
Civil Appeal No.11095 OF 2018 WITH Civil Appeal Nos.11910-11911 OF 2018 Civil Appeal Nos.12055-12056 OF 2018, Civil Appeal No.3123 OF 2019, Civil Appeal No.5372 OF 2019, Civil Appeal No. 6641 OF 2019, Civil Appeal Nos. 2935-2936 OF 2020, Civil Appeal Nos. 4628-4629 OF 2021, Civil Appeal Nos. 5583-5584 OF 2021, Civil Appeal No. 39 OF 2021, Civil Appeal No. 5005 OF 2022, Civil Appeal No. 4089 OF 2022
Decided On : 20-04-2023
The judgment deals with the interpretation of the term 'Change in Law' under various Power Purchase Agreements (PPAs) and the entitlement of Generators to compensation for changes in law occurring after the cut-off date. The Court held that all additional charges payable on account of orders, directions, Notifications, Regulations, etc., issued by the instrumentalities of the State, after the cut-off date, will have to be considered to be 'Change in Law' events. The Generators would be entitled to compensation on the restitutionary principle on such changes occurring after the cut-off date.
Fact of the Case:
Numerous cross-appeals were filed challenging the common judgment and order dated 14th August 2018 passed by the learned Appellate Tribunal for Electricity, New Delhi (hereinafter referred to as “APTEL”) in Appeal No. 111 of 2017 & I.A. No.450 of 2018 and in Appeal No.290 of 2017 & I.A. No.519 of 2017. The appeals arose out of long term Power Purchase Agreements (“PPAs”) for supply of power to various Distribution Companies (“DISCOMS”). The main issue in the appeals was whether certain changes in law, such as changes in coal prices, railway freight charges, and environmental regulations, constituted “Change in Law” events under the PPAs, entitling the Generators to compensation.
Finding of the Court:
The Court held that all additional charges payable on account of orders, directions, Notifications, Regulations, etc., issued by the instrumentalities of the State, after the cut-off date, will have to be considered to be “Change in Law” events. The Generators would be entitled to compensation on the restitutionary principle on such changes occurring after the cut-off date. The Court further held that the term “Law” in the PPAs would include all applicable rules, regulations, orders, Notifications issued by an Indian Governmental Instrumentality and shall also include all rules, regulations, decisions and orders of the Central Electricity Regulatory Commission (CERC) and the MERC.
Issues: 1. Whether 'Change in Law' relief on account of New Coal Distribution Policy, 2013 ("NCDP 2013") should be on 'actuals' viz. as against 100% of normative coal requirement assured in terms of New Coal Distribution Policy, 2007 ("NCDP 2007") OR restricted to trigger levels in NCDP 2013 viz. 65%, 65%, 67% and 75% of ACQ? 2. Whether for computing 'Change in Law' relief, the operating parameters should be considered on 'actuals' OR as per technical information submitted in bid? 3. Whether 'Change in Law' relief compensation is to be granted from 1st April 2013 (start of Financial Year) or 31st July 2013 (date of NCDP 2013)? 4. Whether Busy Season Surcharge and Development Surcharge and Port Congestion Surcharge; MoEF Notification on coal quality; Shortfall in linkage coal due to Change in NCDP; Forest Tax; Add on Premium price; Evacuation Facility Charges (EFC) would amount to 'Change in Law' events? 5. Whether various taxes/charges imposed by various State Governments would also fall under 'Change in Law' events? 6. At what rate the Generators would be entitled to 'carrying cost'.
Ratio Decidendi: The Court held that the term “Law” in the PPAs would include all applicable rules, regulations, orders, Notifications issued by an Indian Governmental Instrumentality and shall also include all rules, regulations, decisions and orders of the CERC and the MERC. Therefore, all additional charges payable on account of orders, directions, Notifications, Regulations, etc., issued by the instrumentalities of the State, after the cut-off date, will have to be considered to be “Change in Law” events. The Generators would be entitled to compensation on the restitutionary principle on such changes occurring after the cut-off date.
Final Decision: The appeals were dismissed.
JUDGMENT :
B.R. GAVAI, J.
| Index | |
| I. | INTRODUCTION |
| II. | BRIEF FACTS AND SUBMISSIONS |
| III. | ADDITIONAL ISSUES |
| IV. | CONSIDERATION |
| V. | CONCLUSION |
| VI. | EPILOGUE |
| List of abbreviations: |
| 1. APTEL - Appellate Tribunal for Electricity |
| 2. CEA - Central Electricity Authority |
| 3. CERC - Central Electricity Regulatory Commission |
| 4. CIL - Coal India Limited |
| 5. COD - Commercial Operation Date |
| 6. CSA - Coal Supply Agreement |
| 7. DISCOMS - Distribution Companies |
| 8. ECL - Eastern Coalfield Limited |
| 9. EFC - Evacuation Facility Charges |
| 10. FSA - Fuel Supply Agreement |
| 11. GCV - Gross Calorific Value |
| 12. LoA - Letter of Assurance |
| 13. LPS - Late Payment Surcharge |
| 14. MAT - Minimum Alternate Tax |
| 15. MCL - Mahanadi Coalfield Limited |
| 16. MERC - Maharashtra Electricity Regulatory Commission |
| 17. MoC - Ministry of Coal |
| 18. MoP - Ministry of Power |
| 19. MSEDCL - Maharashtra State Electricity Distribution Company Limited |
| 20. NCDP - New Coal Distribution Policy |
| 21. PPAs - Power Purchase Agreements |
| 22. RFP - Request for Proposal |
| 23. SBAR - State Bank Advance Rate |
| 24. SECL - South Eastern Coal Limited |
| 25. SHAKTI - Scheme for Harnessing and Allocating Koyala (Coal) Transparently in India |
| 26. SHR - Station Heat Rate |
| 27. TANGEDCO- Tamil Nadu Generation and Distribution Corporation |
| 28. UHV - Useful Heat Value |
I. INTRODUCTION
1. When we heard this batch of Electricity appeals, it was agreed between all the parties that this Court should first decide Civil Appeal No. 684 of 2021 (Maharashtra State Electricity Distribution Company Limited v. Adani Power Maharashtra Limited & Ors., 2023 SCC OnLine 233) [“MSEDCL v. APML & Ors.” for short] and Civil Appeal No. 6927 of 2021 (Maharashtra State Electricity Distribution Company Limited v. GMR Warora Energy Ltd. & ors.), inasmuch as three of the issues involved in all the appeals in the batch were common. It was submitted that those two appeals could be decided by deciding the three common issues. However, insofar as the other appeals are concerned, it was submitted that, in addition to the three common issues, certain additional issues were also involved and it was agreed that after those two appeals are decided, the other appeals should be heard for considering these additional issues.
2. The said three common issues are thus:
(i) Whether ‘Change in Law’ relief on account of New Coal Distribution Policy, 2013 (“NCDP 2013” for short) should be on ‘actuals’ viz. as against 100% of normative coal requirement assured in terms of New Coal Distribution Policy, 2007 (“NCDP 2007” for short) OR restricted to trigger levels in NCDP 2013 viz. 65%, 65%, 67% and 75% of ACQ?
(ii) Whether for computing ‘Change in Law’ relief, the operating parameters should be considered on ‘actuals’ OR as per technical information submitted in bid?
(iii) Whether ‘Change in Law’ relief compensation is to be granted from 1st April 2013 (start of Financial Year) or 31st July 2013 (date of NCDP 2013)?
3. After extensively hearing all the learned counsel for the parties, vide the judgment and order dated 3rd March 2023 in the case of MSEDCL v. APML & Ors. (supra), this Court decided those two appeals after considering the aforesaid three issues.
4. The first issue was answered by this Court, holding that the ‘Change in Law’ relief for domestic coal shortfall should be on ‘actuals’, i.e. as against 100% of normative coal requirement assured in terms of the NCDP, 2007. Insofar as the second issue is concerned, it was held that the Station Heat Rate (“SHR” for short) and Auxiliary consumption should be considered as per the Regulations or actuals, whichever is lower. The t
The term “Law” in the PPAs would include all applicable rules, regulations, orders, Notifications issued by an Indian Governmental Instrumentality and shall also include all rules, regulations, decis....
The Notification imposing Evacuation Facility Charges constitutes a change in law, entitling the affected party to compensation from that date.
Any change resulting in a cost impact on selling electricity constitutes a Change in Law event, entitling affected parties to compensation under PPAs.
Definition of “Law” is wide enough to include all rules, regulations, orders, notifications by Governmental instrumentalities.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.