SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(SC) 385

SUPREME COURT OF INDIA
B.R. GAVAI, VIKRAM NATH, JJ.
GMR Warora Energy Limited – Appellant
VERSUS
Central Electricity Regulatory Commission (CERC) & Ors. – Respondents
Civil Appeal No.11095 OF 2018 WITH Civil Appeal Nos.11910-11911 OF 2018 Civil Appeal Nos.12055-12056 OF 2018, Civil Appeal No.3123 OF 2019, Civil Appeal No.5372 OF 2019, Civil Appeal No. 6641 OF 2019, Civil Appeal Nos. 2935-2936 OF 2020, Civil Appeal Nos. 4628-4629 OF 2021, Civil Appeal Nos. 5583-5584 OF 2021, Civil Appeal No. 39 OF 2021, Civil Appeal No. 5005 OF 2022, Civil Appeal No. 4089 OF 2022
Decided On : 20-04-2023

The term “Law” in the PPAs would include all applicable rules, regulations, orders, Notifications issued by an Indian Governmental Instrumentality and shall also include all rules, regulations, decisions and orders of the CERC and the MERC. Therefore, all additional charges payable on account of orders, directions, Notifications, Regulations, etc., issued by the instrumentalities of the State, after the cut-off date, will have to be considered to be “Change in Law” events. The Generators would be entitled to compensation on the restitutionary principle on such changes occurring after the cut-off date.

Headnote:

The judgment deals with the interpretation of the term 'Change in Law' under various Power Purchase Agreements (PPAs) and the entitlement of Generators to compensation for changes in law occurring after the cut-off date. The Court held that all additional charges payable on account of orders, directions, Notifications, Regulations, etc., issued by the instrumentalities of the State, after the cut-off date, will have to be considered to be 'Change in Law' events. The Generators would be entitled to compensation on the restitutionary principle on such changes occurring after the cut-off date.

Fact of the Case:

Numerous cross-appeals were filed challenging the common judgment and order dated 14th August 2018 passed by the learned Appellate Tribunal for Electricity, New Delhi (hereinafter referred to as “APTEL”) in Appeal No. 111 of 2017 & I.A. No.450 of 2018 and in Appeal No.290 of 2017 & I.A. No.519 of 2017. The appeals arose out of long term Power Purchase Agreements (“PPAs”) for supply of power to various Distribution Companies (“DISCOMS”). The main issue in the appeals was whether certain changes in law, such as changes in coal prices, railway freight charges, and environmental regulations, constituted “Change in Law” events under the PPAs, entitling the Generators to compensation.

Finding of the Court:

The Court held that all additional charges payable on account of orders, directions, Notifications, Regulations, etc., issued by the instrumentalities of the State, after the cut-off date, will have to be considered to be “Change in Law” events. The Generators would be entitled to compensation on the restitutionary principle on such changes occurring after the cut-off date. The Court further held that the term “Law” in the PPAs would include all applicable rules, regulations, orders, Notifications issued by an Indian Governmental Instrumentality and shall also include all rules, regulations, decisions and orders of the Central Electricity Regulatory Commission (CERC) and the MERC.

Issues: 1. Whether 'Change in Law' relief on account of New Coal Distribution Policy, 2013 ("NCDP 2013") should be on 'actuals' viz. as against 100% of normative coal requirement assured in terms of New Coal Distribution Policy, 2007 ("NCDP 2007") OR restricted to trigger levels in NCDP 2013 viz. 65%, 65%, 67% and 75% of ACQ? 2. Whether for computing 'Change in Law' relief, the operating parameters should be considered on 'actuals' OR as per technical information submitted in bid? 3. Whether 'Change in Law' relief compensation is to be granted from 1st April 2013 (start of Financial Year) or 31st July 2013 (date of NCDP 2013)? 4. Whether Busy Season Surcharge and Development Surcharge and Port Congestion Surcharge; MoEF Notification on coal quality; Shortfall in linkage coal due to Change in NCDP; Forest Tax; Add on Premium price; Evacuation Facility Charges (EFC) would amount to 'Change in Law' events? 5. Whether various taxes/charges imposed by various State Governments would also fall under 'Change in Law' events? 6. At what rate the Generators would be entitled to 'carrying cost'.

Ratio Decidendi: The Court held that the term “Law” in the PPAs would include all applicable rules, regulations, orders, Notifications issued by an Indian Governmental Instrumentality and shall also include all rules, regulations, decisions and orders of the CERC and the MERC. Therefore, all additional charges payable on account of orders, directions, Notifications, Regulations, etc., issued by the instrumentalities of the State, after the cut-off date, will have to be considered to be “Change in Law” events. The Generators would be entitled to compensation on the restitutionary principle on such changes occurring after the cut-off date.

Final Decision: The appeals were dismissed.

JUDGMENT :

B.R. GAVAI, J.

Index

I.

INTRODUCTION

II.

BRIEF FACTS AND SUBMISSIONS

III.

ADDITIONAL ISSUES

IV.

CONSIDERATION

V.

CONCLUSION

VI.

EPILOGUE

List of abbreviations:

1. APTEL - Appellate Tribunal for Electricity

2. CEA - Central Electricity Authority

3. CERC - Central Electricity Regulatory Commission

4. CIL - Coal India Limited

5. COD - Commercial Operation Date

6. CSA - Coal Supply Agreement

7. DISCOMS - Distribution Companies

8. ECL - Eastern Coalfield Limited

9. EFC - Evacuation Facility Charges

10. FSA - Fuel Supply Agreement

11. GCV - Gross Calorific Value

12. LoA - Letter of Assurance

13. LPS - Late Payment Surcharge

14. MAT - Minimum Alternate Tax

15. MCL - Mahanadi Coalfield Limited

16. MERC - Maharashtra Electricity Regulatory Commission

17. MoC - Ministry of Coal

18. MoP - Ministry of Power

19. MSEDCL - Maharashtra State Electricity Distribution Company Limited

20. NCDP - New Coal Distribution Policy

21. PPAs - Power Purchase Agreements

22. RFP - Request for Proposal

23. SBAR - State Bank Advance Rate

24. SECL - South Eastern Coal Limited

25. SHAKTI - Scheme for Harnessing and Allocating Koyala (Coal) Transparently in India

26. SHR - Station Heat Rate

27. TANGEDCO- Tamil Nadu Generation and Distribution Corporation

28. UHV - Useful Heat Value

I. INTRODUCTION

1. When we heard this batch of Electricity appeals, it was agreed between all the parties that this Court should first decide Civil Appeal No. 684 of 2021 (Maharashtra State Electricity Distribution Company Limited v. Adani Power Maharashtra Limited & Ors., 2023 SCC OnLine 233) [“MSEDCL v. APML & Ors.” for short] and Civil Appeal No. 6927 of 2021 (Maharashtra State Electricity Distribution Company Limited v. GMR Warora Energy Ltd. & ors.), inasmuch as three of the issues involved in all the appeals in the batch were common. It was submitted that those two appeals could be decided by deciding the three common issues. However, insofar as the other appeals are concerned, it was submitted that, in addition to the three common issues, certain additional issues were also involved and it was agreed that after those two appeals are decided, the other appeals should be heard for considering these additional issues.

2. The said three common issues are thus:

    (i) Whether ‘Change in Law’ relief on account of New Coal Distribution Policy, 2013 (“NCDP 2013” for short) should be on ‘actuals’ viz. as against 100% of normative coal requirement assured in terms of New Coal Distribution Policy, 2007 (“NCDP 2007” for short) OR restricted to trigger levels in NCDP 2013 viz. 65%, 65%, 67% and 75% of ACQ?

    (ii) Whether for computing ‘Change in Law’ relief, the operating parameters should be considered on ‘actuals’ OR as per technical information submitted in bid?

    (iii) Whether ‘Change in Law’ relief compensation is to be granted from 1st April 2013 (start of Financial Year) or 31st July 2013 (date of NCDP 2013)?

3. After extensively hearing all the learned counsel for the parties, vide the judgment and order dated 3rd March 2023 in the case of MSEDCL v. APML & Ors. (supra), this Court decided those two appeals after considering the aforesaid three issues.

4. The first issue was answered by this Court, holding that the ‘Change in Law’ relief for domestic coal shortfall should be on ‘actuals’, i.e. as against 100% of normative coal requirement assured in terms of the NCDP, 2007. Insofar as the second issue is concerned, it was held that the Station Heat Rate (“SHR” for short) and Auxiliary consumption should be considered as per the Regulations or actuals, whichever is lower. The t


Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top