SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(SC) 443

SUPREME COURT OF INDIA
ABHAY S. OKA, RAJESH BINDAL, JJ.
M/s. Asian Avenues Pvt Ltd. - Appellant
Versus
Sri Syed Shoukat Hussain - Respondent
Civil Appeal No.2927 Of 2023
Decided On : 28-04-2023

IMPORTANT POINTS
(1) Cancellation of an instrument - Action instituted under Section 31 of Specific Relief for cancellation of an instrument is not an action in rem.
(2) Rejection of plaint - Suit will not lie when there is arbitration clause in Development Agreement.

Headnote:

(A) Specific Relief Act, 1963 - Section 31 - Cancellation of instrument - Action instituted under Section 31 of Specific Relief for cancellation of an instrument is not an action in rem - In present case, dispute, whether Development Agreement stands cancelled or whether agreement can be lawfully cancelled, is a dispute arising out of or in connection with Development Agreement - As per arbitration clause, if issue concerning cancellation is not mutually resolved, same must be referred to arbitration - In view of applicability of arbitration clause to dispute subject matter of suit filed by respondent, Trial Judge was justified in passing an order under Section 8 of Arbitration Act by directing that dispute be referred to arbitration. (Paras 7 and 8)

(B) Civil Procedure Code, 1908 - Order VII Rule 11 - Arbitration and Conciliation Act, 1996 - Section 8 - Rejection of plaint - There is arbitration clause in Development Agreement - In view of applicability of arbitration clause to dispute subject matter of suit filed by respondent, Trial Judge was justified in passing order under Section 8 of Arbitration Act by directing that dispute be referred to arbitration - Impugned judgment and order of High Court set aside and judgment and order of Trial Court restored. (Paras 6, 8 and 9)

Facts of the case:

Present appeal is by defendant in a suit filed by respondent. Respondent-plaintiff claims to be the owner of suit property, more particularly described in plaint. There was a Development Agreement-cum-General Power of Attorney executed on 23rd October 2008 by and between the appellant and the respondent. By Development Agreement, appellant was granted permissive possession for the purposes of carrying out development work on the property subject matter of Development Agreement. There was a dispute between parties, which led to the respondent cancelling Development Agreement.

Findings of Court:

It is impossible to hold that an action instituted under Section 31 of the Specific Relief for cancellation of an instrument is an action in rem.

Result : Appeal allowed.

JUDGMENT :

(Abhay S. Oka, J.)

FACTS

1. The present appeal is by the defendant in a suit filed by the respondent. The respondent-plaintiff claims to be the owner of the suit property, more particularly described in the plaint. There was a Development Agreement-cum-General Power of Attorney (for short, ‘the Development Agreement’) executed on 23rd October 2008 by and between the appellant and the respondent. By the Development Agreement, the appellant was granted permissive possession for the purposes of carrying out development work on the property subject matter of the Development Agreement. There was a dispute between the parties, which led to the respondent cancelling the Development Agreement. The respondent issued a legal notice to the appellant calling upon him to execute a deed of cancellation of the Development Agreement. The prayer in the suit is for a decree directing the appellant to execute a deed of cancellation in respect of the Development Agreement. There is also a prayer for the delivery of possession of the suit property.

2. After the suit summons was served, the appellant filed an application under Rule 11 of Order VII of the Code of Civil Procedure, 1908 (for short, ‘CPC’). The application was filed on the ground that in view of the arbitration clause in the Development Agreement, the dispute ought to be referred to arbitration. There was a prayer made for referring the dispute to arbitration. The Trial Court rejected the plaint. The Trial Court also exercised power under Section 8 of the Arbitration and Conciliation Act, 1996 (for short ‘the Arbitration Act’). The Trial Court directed the parties to refer their dispute to arbitration. In a revision application preferred by the respondent, the High Court has interfered and has set aside the order of the Trial Court.

SUBMISSIONS

3. The learned counsel appearing for the appellant pointed out that the High Court relied upon a decision of the Division Bench of the same Court, which holds that the adjudication on the issue whether there is a cancellation of the Development Agreement will operate in rem and therefore, the arbitration clause cannot be invoked.

4. The learned counsel appearing for the appellant relied upon a decision of the Bench of three Hon’ble Judges of this Court in the case of Deccan Paper Mills Company Limited v. Regency Mahavir Properties and Ors., (2021) 4 SCC 786. He submitted that this Court has held that action instituted under Section 31 of the Specific Relief Act, 1963 (for short ‘the Specific Relief Act’) is not an action in rem. He would, therefore, submit that the order of the High Court is erroneous and, therefore, the order of the Trial Court be restored.

5. The learned counsel appearing for the respondent submitted that the arbitration clause will not apply as the prayer in the suit is for cancellation of the agreement in accordance with Section 31 of the Specific Relief Act. Her submission is that the issues arising under Section 31 of the Specific Relief Act can be adjudicated only by a competent Civil Court.

OUR VIEW

6. We have considered the submissions. Admittedly, there is an arbitration clause in the Development Agreement, which reads thus:

    "All the disputes arising out of or in connection with this agreement shall be initially resolved by mutual discussions among the developer and landowner or the nominated representatives of both the parties. In case of disputes not resolved by mutual discussions, the same shall be referred to the arbitration in accordance with the provisions of the Arbitration and Conciliation Act 1996. The disputes shall be referred to the mutually agreed arbitrator within from the cause of action. The award of the arbitrator shall be binding and final on both the parties." (emphasis added)

7. The dispute, whether the Development Agreement stands cancelled or whether the agreement can be lawfully cancelled, is a dispute arising out of or in connection with the Development Agreement. There

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top