SUPREME COURT OF INDIA
K.M. Joseph, Krishna Murari, B.V. Nagarathna, JJ.
Union of India & Ors. - Appellants
Versus
M/s. Bharat Enterprise - Respondent
Civil Appeal Nos. 3441-3442 of 2015
Decided On : 23-03-2023
Fact of the Case:
A contract dispute arose between parties regarding additional claims made after submission of the final bill for repair works. The respondent sought arbitration under Section 11(6) of the Arbitration and Conciliation Act, which led to an award in their favor. However, the appellant's petition under Section 34 was allowed by the District Judge but overturned on appeal under Section 37.Finding of the Court:
The court found that clauses 65 and 65A of the contract were binding on both parties and emphasized that an arbitrator must not exceed the contractual provisions. It noted that there was no finding that the final bill or 'no claims due certificate' were vitiated by duress or coercion.Issues:
The main issue was whether the impugned order was sustainable in light of clauses 65 and 65A of the Contract.Ratio Decidendi:
The court held that an arbitrator is bound by the terms of the contract and cannot exceed its boundaries. It emphasized that a final bill or 'no claims due certificate' can only be overridden if it was proven to be a result of vitiating factors under law.Final Decision:
While setting aside the impugned order, the court directed a lump sum payment to settle all claims as per equitable considerations.JUDGMENT :
K. M. JOSEPH, J.
1. A contract was entered into between the parties for the repair of bathrooms and other allied works on 02.07.2001. It would appear that time was extended up to 19.01.2002. The respondent-Contractor submitted final bill on 13.02.2002. It contained a No Claims Certificate. The said amount claimed by the respondent apparently was not paid immediately. The respondent it would appear made several reminders regarding the non-payment of the final bill for a period of one year. Following many reminders by the respondent regarding the non payment of the final bill, according to the respondent, it sent a list of additional claims on 25.02.2003 and in the said letter, claimed that the letter and the Final bill should be considered as under protest. The respondent signed affidavit dated 24.05.2003 which according to the respondent was prepared by the appellant and which provided for the withdrawal of the letter dated 25.02.2003. An undertaking was also got signed from the respondent on 12.09.2003. Thereafter, respondent on 14.11.2003 revoked the affidavit and undertaking on account of non payment of the bill and purported to give the final notice invoking the arbitration clause contained in the contract for the non payment of claims due. It is, thereafter, on 25.11.2003, that the appellant made payment of Rs.100358/-. This was followed by letter dated 08.09.2004 by which the respondent sought to invoke the arbitration clause and appointment of arbitrator. Later, on 12.11.2007, a petition was moved under Section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘Act’ for brevity) for appointment of an arbitrator. The same was allowed. A fresh agreement for arbitration was entered into on 22.11.2007 providing for appointment of a new Arbitrator. Suffice it to notice that a former District and Sessions Judge came to be appointed as sole arbitrator. The appellant filed an application under Section 16 for dismissal of the claims. The appellant invoked clauses 65 and 65A of the contract. This application, no doubt, was rejected on 04.03.2009 by the Arbitrator. Thereafter, the Arbitrator entered upon the merits of the matter and passed Award dated 16.07.2009. There were a total of 10 claims. The Arbitrator disallowed seven out of the ten claims while it allowed three claims. The claims were allowed with rate of interest which we need not notice at this stage. The petition filed by the appellant under Section 34 of the Act came to be allowed by the District Judge. It is this order passed by the District Judge under Section 34 which stands overturned by the impugned order in an appeal under Section 37 of the Act.
2. We have heard Col. R. Balasubramanium, learned senior counsel for the appellants, and Ms. Praveena Gautam, learned counsel for the respondent.
3. The only controversy which we are called upon to resolve is whether the impugned order is sustainable having regard to clauses 65 and 65A of the Contract.
4. The contention of the learned senior counsel for the appellants is that the impugned order is in the teeth of law laid down by this Court in Bharat Coking Coal Ltd. vs. Annapurna Construction (2003) 8 SCC 154. He also points out that the said view has been followed in PSA SI CAL Terminate (P) Ltd. v. Board of Trustees of V.O. Chidambranar Port Trust Tuticorin 2021 SCC Online SC 508. In a nutshell, the argument is as follows:
5. He contends that the Arbitrator cannot travel outside the boundaries of the contact. In fact, he is fully bound by the terms of the contract. In the terms of the contract which are apposite in the context of the dispute before us, there is a prohibition against the Contractor supplementing the claims in the final bill by including claims which are not found in the final bill. In the facts of this case, he would submit that this is precisely what has happened by pointing out the final bill which was submitted on 13.02.2002 and the claims allowed are later raised
Bharat Coking Coal Ltd. v. Annapurna Construction (2003) 8 SCC 154 [Para 4
Boghara Polyfab (P) Ltd. [(2009) 1 SCC 267 : (2009) 1 SCC (Civ) 177] [Para 12]
Damodar Valley Corpn. v. K.K. Kar [(1974) 1 SCC 141] [Para 13]
Naihati Jute Mills Ltd. v. Khyaliram Jagannath [AIR 1968 SC 522] [Para 13]
National Insurance Company Limited v. Boghara Polyfab Private Limited (2009) 1 SCC 267 [Para 12
SBP & Co. v. Patel Engineering Ltd. and Another (2005) 8 SCC 618 [Para 14]
Tahera Khatoon (D)By LRs. v. Salambin Mohammad (1999) 2 SCC 635 [Para 28]
Union of India and Others v. Master Construction Company (2011) 12 SCC 349 [Para 6
Union of India v. Parmar Construction Company (2019) 15 SCC 682 [Para 6]
An arbitrator is bound by the terms of a contract and cannot exceed its boundaries; a final bill or 'no claims due certificate' can only be overridden if it was proven to be a result of vitiating fac....
The main legal point established is that the submission of a 'no claim certificate' does not necessarily foreclose the right to raise further claims, and disputes involving such certificates are arbi....
(1) Arbitration – Parties to arbitration agreement have autonomy to decide not only on procedural law to be followed but also substantive law – A party cannot claim anything more than what is covered....
The main legal point established in the judgment is the application of limitation laws and the categorization of cases as dead wood in determining the eligibility for appointment of an arbitrator.
A certificate from an Engineer is not a condition precedent to a counterclaim if the arbitration clause in the contract is widely worded and gives the Arbitrator the power to open up, review, and rev....
Point of Law : when the applicant has asserted their claim and the respondent failed to respond to such claim, the failure of the respondent is liable to be treated as a denial of the claim of the ap....
The interpretation of the contract is within the exclusive domain of the learned Arbitrator, and the court would not interfere with such interpretation.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.