IN THE HIGH COURT FOR THE STATE OF TELANGANA AT HYDERABAD
UJJAL BHUYAN, J.
M/s BPR Infrastructure Limited - Appellant
Versus
M/s. RITES Ltd - Respondent
Arbitration Application No.22 of 2019
Decided on : 08-06-2022
Arbitration - Appointment of Arbitrator - Arbitration and Conciliation Act, 1996 - Section 11 (6) - Clause 25 of the general conditions of contract
Fact of the Case:
The applicant, a civil and structural engineering services company, entered into an agreement with the first respondent, a Government of India enterprise, for construction work. Disputes arose regarding additional payment and submission of a 'no claim certificate' as a condition for final payment.
Finding of the Court:
The Court found that the submission of the 'no claim certificate' by the applicant did not foreclose the possibility of raising further claims, and the dispute required arbitration. The Court appointed a sole arbitrator to adjudicate the matter.
Issues: The issues involved the validity and effect of the 'no claim certificate' submitted by the applicant, the dominance of the first respondent, and the applicability of the arbitration clause in the agreement.
Ratio Decidendi: The Court held that the dispute required arbitration, and the validity of the 'no claim certificate' and its effect on the contract could be examined by the arbitrator. The Court emphasized the need to minimize judicial intervention at the pre-reference stage, in line with the doctrine of kompetenz-kompetenz.
Final Decision: The Court appointed a sole arbitrator to arbitrate on the dispute raised by the applicant, directing both parties to appear before the arbitrator on a specified date.
ORDER :
Heard Mr.Kilashnath PSS, learned counsel for the applicant and Mr.C.V.Rajeeva Reddy, learned counsel for respondent No.1. Also heard Mr.Gadi Praveen Kumar, learned counsel for respondent No.2.
2. This application has been filed under Section 11 (6) of the Arbitration and Conciliation Act, 1996 (briefly, ‘the 1996 Act’, hereinafter) for appointment of arbitrator.
3. Applicant is a company engaged in the business of civil and structural, infrastructural and electrical engineering services.
4. First respondent which is a Government of India enterprise, issued tender notice inviting tenders for the work “construction of laboratory, buildings, animal house, security block including internal roads, compound wall, underground sump, water supply, sanitary, internal electrification and other ancillary works at site ‘A’ and construction of hostel building, residential blocks, Director’s bungalow, internal roads, underground sump, water supply, sanitary, internal electrification and other ancillary works at site ‘B’ for the Centre for DNA Fingerprinting and Diagnostics at Uppal X Roads, Hyderabad”. Tender submitted by the applicant was accepted by the first respondent on 25.03.2013 for a total contract price of Rs.50,03,16,920-04, with completion period being 24 months.
5. Pursuant thereto, both the parties i.e. applicant and respondent No.1 entered into an agreement on 17.05.2013 at Hyderabad.
6. Though the stipulated date of completion was 24 months, with expiry date being 21.04.2015, there were extensions from time to time for reasons completely beyond applicant’s control. According to the applicant, the execution of the work was extended beyond the contract period for a further period of 691 days.
7. Because of such extension and associated escalation of price, applicant issued notice to the first respondent on 23.04.2015 for additional payment. This was followed by letters dated 05.07.2015 and 01.07.2016. However, respondents did not agree with such claim of the applicant.
8. Be that as it may, applicant completed the execution of the work on 31.12.2016 to the full satisfaction of respondent No.1. Last bill was submitted by the applicant on 24.08.2017.
9. When applicant enquired about payment to be made to it, it was informed that unless applicant furnished a ‘no claim certificate’ in the prescribed format to the first respondent, it would not receive the remaining payment. However, according to the applicant, submission of no claim certificate along with the final bill was not envisaged in the agreement. But, because of the dominant position of the first respondent and also on account of the fact that applicant was in dire need of money, it had submitted a no claim certificate on 07.03.2018, which it is stated was under coercion and duress. Two days after the no claim certificate was submitted, payment was made to the applicant on 09.03.2018.
10. Applicant thereafter issued letter to the first respondent regarding additional payment which was, however, rejected by respondent No.1 on the ground that applicant had submitted no claim certificate. Applicant has stated that all disputes arising out of the contract are governed by Clause 25 of the general conditions of contract. Accordingly, applicant had submitted its claim to the first respondent, vide letter dated 30.07.2018. The details of claim are mentioned in paragraph No.10 of the affidavit and in annexure IX.
11. Respondent No.1 denied all the claims of the applicant through its letter dated 21.08.2018 since applicant had signed and filed a no claim certificate. Being aggrieved by the rejection letter of respondent No.1 dated 21.08.2018, applicant wrote back to the first respondent on 30.08.2018 stating that though the final bill was submitted on 24.08.2017, it was informed that unless a no claim certificate was furnished in a prescribed proforma, the final bill would not be paid. Applicant was directed to submit a no claim certificate in a proforma handed over, though submission o
Bishundeo Narain Vs. Seogeni Rai
National Insurance Co. Ltd. v. Boghara Polyfab (P) Ltd.
Union of India Vs. Master Construction Company
United India Insurance Company Limited Vs. Antique Art Exports Private Limited
The main legal point established is that the submission of a 'no claim certificate' does not necessarily foreclose the right to raise further claims, and disputes involving such certificates are arbi....
The issue of arbitrability or non-arbitrability should be left to be decided by the Arbitral Tribunal.
Point of law: Signing of “No Claim” Certificate: The contractor shall not be entitled to make any claim whatsoever against the Railway under or by virtue of or arising out of this contract, nor shall....
A certificate from an Engineer is not a condition precedent to a counterclaim if the arbitration clause in the contract is widely worded and gives the Arbitrator the power to open up, review, and rev....
The arbitration agreement is separate and severable from the underlying contract, and the Arbitral Tribunal has the competence to rule on its own jurisdiction, including the existence or validity of ....
An arbitrator is bound by the terms of a contract and cannot exceed its boundaries; a final bill or 'no claims due certificate' can only be overridden if it was proven to be a result of vitiating fac....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.