SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(SC) 344

SUPREME COURT OF INDIA
Abhay S. Oka, Ujjal Bhuyan, JJ.
Sahakarmaharshi Bhausaheb Thorat Sahakari Sakhar Karkhana Ltd. – Appellant
Versus
Thyssen Krupp Industries India Pvt. Ltd. – Respondent
Civil Appeal No. 3194 of 2014
Decided On ; 14-02-2025

Advocates appeared:
For the Appellant(s) : Mr. Vijay Hansaria, Sr. Adv. Mr. M. Y. Deshmukh, AOR Mr. Pradip Rajendra Malpani, Adv. Ms. Manjeet Kirpal, Adv. Ms. Adviteeya Sharma, Adv. Ms. Kavya Jhawar, Adv.
For the Respondent(s): Mr. Chander Uday Singh, Sr. Adv. Ms. Surekha Raman, Adv. Mr. Amarjit Singh Bedi, Adv. Mr. Abhishek Anand, Adv. Mr. Varun Chandiok, Adv. Ms. Riya Seth, Adv. Ms. Unnimaya S, Adv. Mr. Shreyash Kumar, Adv. M/S. K J John And Co, AOR

IMPORTANT POINT
Claim for damages will remain confined to what is expressly provided under Agreement.

Headnote:

Arbitration Act, 1940 – Section 40 – Contract Act, 1872 – Section 74 – Challenge to arbitral award – Case made out in claim is that respondent failed to commission plant successfully so as to give guaranteed performance as per agreement – Penalties/liquidated damages were stipulated for delay in delivering machinery and plant, failure to give guaranteed performance of continuous fermentation plant, failure to provide a guaranteed performance with respect to steam, and failure to give a guaranteed performance with respect to power – There is a clause for liquidated damages under which claim was allowed by Arbitral Tribunal, which respondent accepted – Appellant got liquidated damages as provided in agreement on account of breaches committed by respondent – Claim for damages of appellant will remain confined to what is expressly provided under Agreement – Appeal dismissed. (Paras 22, 24, 27, 29 and 30)

Facts of the case:

Issues involved in this appeal are limited, but litigation has a chequered history. An agreement was executed on 17th November 1992 by and between appellant and respondent. Under said agreement, respondent agreed to design, procure, manufacture and supply to appellant machinery and equipment for a continuous fermentation process based on Encillium process, patented by National Chemical Laboratory, Pune. Agreement contained an arbitration clause.

Findings of Court:

Appellant was not entitled to the claim of Rs.68.15 lakhs as it was claimed in statement of claim as refund of amount spent by the appellant on the acquisition of plant and machinery.

Result : Appeal dismissed.

Judgement Key Points

Key Points: - The appellant was awarded liquidated damages for delay in delivery and for non-performance, and claims for refund of amounts spent were disputed; High Court and Supreme Court upheld that damages must be confined to what is expressly provided under the contract. (!) (!) - The claim for Rs. 68.15 lakhs (loss due to non-performing machinery) was rejected as not supported by the contractual framework and because the claimant did not exercise the replacement option under clause 21; the Court held damages must align with the contract terms and Section 74. (!) (!) - Clause 21 provides maintenance/rectification rights and cost recovery, including replacement at seller’s cost if defects are not remedied within reasonable time; the claimant did not rely on this clause for a replacement remedy. (!) (!) (!) - The supplementary/MOU increased liquidated damages for short production, and the overall dispute centered on whether the refund of investment could be treated as damages under the contract. (!) (!) - The final decision dismissed the appeal, confirming the High Court’s view that the Rs. 68.15 lakhs claim was not arbitrable or permissible under the contract terms as interpreted. (!)

What is the scope of damages recoverable under the contract and whether the claim for Rs. 68.15 lakhs was permissible under the terms of the agreement?

What is the effect of Section 74 of the Contract Act on claims for liquidated damages versus actual damages in this arbitration context?

What are the rights and remedies under clause 21 for replacement or rectification of defective machinery and how did they impact the appellant’s claim?


Table of Content
1. agreement for machinery supply (Para 1)
2. delay in delivery and performance (Para 2)
3. memorandum of understanding executed (Para 3)
4. claims made before the arbitral tribunal (Para 4 , 5)
5. high court's judgment on claims (Para 6 , 7 , 8 , 9 , 10)
6. appellant's arguments on damages (Para 11)
7. respondent's counterarguments (Para 12 , 13 , 14 , 15)
8. court's reasoning on claims (Para 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27)
9. appeal dismissed (Para 28 , 29 , 30)

JUDGMENT

ABHAY S. OKA, J.

FACTUAL ASPECTS

1. The issues involved in this appeal are limited, but the litigation has a chequered history. An agreement was executed on 17th November 1992 by and between the appellant and the respondent. Under the said agreement, the respondent agreed to design, procure, manufacture and supply to the appellant machinery and equipment for a continuous fermentation process based on the Encillium process, patented by the National Chemical Laboratory, Pune (for short, ‘the NCL’). The agreement contained an arbitration clause. The total consideration was of Rs. 93,20,000/-. One of the clauses in the agreement was that the fermentation plant that was to be supplied by the respondent must have a guaranteed minimum yield of 280 litres of alcohol per metric tonne of Molasses. According to the appellant's case, when the agreement was entered into, the existing yield in their factory was 245 litres per metric tonne of Molasses. Under the agreement, the plant and machinery were to be supplied within a period of five and half months from the effective date of the agreement, i.e., by 15th May 1993, for a total consideration of Rs.93.20 lakhs.

2. According to the appellant, there was a delay of about 24 weeks in the delivery of the machinery. The appellant's case was that four trial runs were conducted on the machinery supplied by the respondent. The yield was much less than the guaranteed yield of 280 litres per metric tonne of Molasses. The maximum yield in trial runs was 237.68 litres per metric tonne of Molasses. Therefore, on 19th October 1994, the appellant issued a legal notice to the respondent claiming a sum of Rs. 237.83 lakhs as damages. As expected, the respondent disputed the said claim. That is how the appellant invoked the arbitration clause by appointing its nominee arbitrator.

3. According to the appellant's case, a memorandum of understanding dated 24th July 1995 (for short, ‘the MOU’) was executed by and between the parties without prejudice to their rights and contentions. It provided for conducting one more trial run for 15 days after necessary modifications were made in the machine as suggested by the NCL. The modifications were to be made by the respondent at its own cost. By the MOU, the quantum of liquidated damages under clause 15 of the agreement was increased to 20% of the contract value, i.e. Rs. 18.64 lakhs, which would be payable if the machine failed to give guaranteed performance. According to the appellant's case, the fifth trial run conducted in August 1995 generated a yield of 224.54 litres per metric tonne of Molasses.

4. The appellant filed a statement of claim before the Arbitral Tribunal, claiming damages of Rs.233.75 lakhs. Broadly, the following claims were made:-

    a) For a delay of 24 weeks in the supply of plant and machinery - Rs.4.66 lakhs, which is 5% of the contract price

    b) Liquidated damages equivalent to 20% of the contract value – Rs.18.64 lakhs;

    c) On account of the failure of guaranteed performance of steam and power consumption - Rs. 9.30 lakhs at 10% of the contract value;

    d) Loss caused due to short production – Rs. 48.45 lakhs;

    e) The amount spent by the appellant on payment of the price to the respondent, civil work, and supervision – Rs. 107.54 lakhs; and,

    (f) Interest at the rate of 18% on the claim amount of Rs. 107.54 lakhs from May 1993 till 31st August 1995 – Rs.45.16 lakhs –

    Total 233.75 lakhs.

5. The Arbitral Tribunal, by an award dated 20th June 1999, granted the f

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon telegram-icon
      whatsapp-icon Back to top