SUPREME COURT OF INDIA
Abhay S. Oka, Ujjal Bhuyan, JJ.
Sahakarmaharshi Bhausaheb Thorat Sahakari Sakhar Karkhana Ltd. – Appellant
Versus
Thyssen Krupp Industries India Pvt. Ltd. – Respondent
Civil Appeal No. 3194 of 2014
Decided On ; 14-02-2025
Arbitration Act, 1940 – Section 40 – Contract Act, 1872 – Section 74 – Challenge to arbitral award – Case made out in claim is that respondent failed to commission plant successfully so as to give guaranteed performance as per agreement – Penalties/liquidated damages were stipulated for delay in delivering machinery and plant, failure to give guaranteed performance of continuous fermentation plant, failure to provide a guaranteed performance with respect to steam, and failure to give a guaranteed performance with respect to power – There is a clause for liquidated damages under which claim was allowed by Arbitral Tribunal, which respondent accepted – Appellant got liquidated damages as provided in agreement on account of breaches committed by respondent – Claim for damages of appellant will remain confined to what is expressly provided under Agreement – Appeal dismissed. (Paras 22, 24, 27, 29 and 30)
Facts of the case:
Issues involved in this appeal are limited, but litigation has a chequered history. An agreement was executed on 17th November 1992 by and between appellant and respondent. Under said agreement, respondent agreed to design, procure, manufacture and supply to appellant machinery and equipment for a continuous fermentation process based on Encillium process, patented by National Chemical Laboratory, Pune. Agreement contained an arbitration clause.
Findings of Court:
Appellant was not entitled to the claim of Rs.68.15 lakhs as it was claimed in statement of claim as refund of amount spent by the appellant on the acquisition of plant and machinery.
Result : Appeal dismissed.
Key Points: - The appellant was awarded liquidated damages for delay in delivery and for non-performance, and claims for refund of amounts spent were disputed; High Court and Supreme Court upheld that damages must be confined to what is expressly provided under the contract. (!) (!) - The claim for Rs. 68.15 lakhs (loss due to non-performing machinery) was rejected as not supported by the contractual framework and because the claimant did not exercise the replacement option under clause 21; the Court held damages must align with the contract terms and Section 74. (!) (!) - Clause 21 provides maintenance/rectification rights and cost recovery, including replacement at seller’s cost if defects are not remedied within reasonable time; the claimant did not rely on this clause for a replacement remedy. (!) (!) (!) - The supplementary/MOU increased liquidated damages for short production, and the overall dispute centered on whether the refund of investment could be treated as damages under the contract. (!) (!) - The final decision dismissed the appeal, confirming the High Court’s view that the Rs. 68.15 lakhs claim was not arbitrable or permissible under the contract terms as interpreted. (!)
| Table of Content |
|---|
| 1. agreement for machinery supply (Para 1) |
| 2. delay in delivery and performance (Para 2) |
| 3. memorandum of understanding executed (Para 3) |
| 4. claims made before the arbitral tribunal (Para 4 , 5) |
| 5. high court's judgment on claims (Para 6 , 7 , 8 , 9 , 10) |
| 6. appellant's arguments on damages (Para 11) |
| 7. respondent's counterarguments (Para 12 , 13 , 14 , 15) |
| 8. court's reasoning on claims (Para 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27) |
| 9. appeal dismissed (Para 28 , 29 , 30) |
JUDGMENT
ABHAY S. OKA, J.
FACTUAL ASPECTS
1. The issues involved in this appeal are limited, but the litigation has a chequered history. An agreement was executed on 17th November 1992 by and between the appellant and the respondent. Under the said agreement, the respondent agreed to design, procure, manufacture and supply to the appellant machinery and equipment for a continuous fermentation process based on the Encillium process, patented by the National Chemical Laboratory, Pune (for short, ‘the NCL’). The agreement contained an arbitration clause. The total consideration was of Rs. 93,20,000/-. One of the clauses in the agreement was that the fermentation plant that was to be supplied by the respondent must have a guaranteed minimum yield of 280 litres of alcohol per metric tonne of Molasses. According to the appellant's case, when the agreement was entered into, the existing yield in their factory was 245 litres per metric tonne of Molasses. Under the agreement, the plant and machinery were to be supplied within a period of five and half months from the effective date of the agreement, i.e., by 15th May 1993, for a total consideration of Rs.93.20 lakhs.
2. According to the appellant, there was a delay of about 24 weeks in the delivery of the machinery. The appellant's case was that four trial runs were conducted on the machinery supplied by the respondent. The yield was much less than the guaranteed yield of 280 litres per metric tonne of Molasses. The maximum yield in trial runs was 237.68 litres per metric tonne of Molasses. Therefore, on 19th October 1994, the appellant issued a legal notice to the respondent claiming a sum of Rs. 237.83 lakhs as damages. As expected, the respondent disputed the said claim. That is how the appellant invoked the arbitration clause by appointing its nominee arbitrator.
3. According to the appellant's case, a memorandum of understanding dated 24th July 1995 (for short, ‘the MOU’) was executed by and between the parties without prejudice to their rights and contentions. It provided for conducting one more trial run for 15 days after necessary modifications were made in the machine as suggested by the NCL. The modifications were to be made by the respondent at its own cost. By the MOU, the quantum of liquidated damages under clause 15 of the agreement was increased to 20% of the contract value, i.e. Rs. 18.64 lakhs, which would be payable if the machine failed to give guaranteed performance. According to the appellant's case, the fifth trial run conducted in August 1995 generated a yield of 224.54 litres per metric tonne of Molasses.
4. The appellant filed a statement of claim before the Arbitral Tribunal, claiming damages of Rs.233.75 lakhs. Broadly, the following claims were made:-
b) Liquidated damages equivalent to 20% of the contract value – Rs.18.64 lakhs;
c) On account of the failure of guaranteed performance of steam and power consumption - Rs. 9.30 lakhs at 10% of the contract value;
d) Loss caused due to short production – Rs. 48.45 lakhs;
e) The amount spent by the appellant on payment of the price to the respondent, civil work, and supervision – Rs. 107.54 lakhs; and,
(f) Interest at the rate of 18% on the claim amount of Rs. 107.54 lakhs from May 1993 till 31st August 1995 – Rs.45.16 lakhs –
Total 233.75 lakhs.
5. The Arbitral Tribunal, by an award dated 20th June 1999, granted the f
Madnani Construction Corporation (P) Ltd. v. Union of India & Ors. (2010) 1 SCC 549 [Para 11]
Claim for damages will remain confined to what is expressly provided under Agreement.
Arbitration Award - An Award however can be interfered with if it is found to be vulnerable under any of the grounds in Section 34 including being in contravention with the fundamental policy of Indi....
The court reaffirmed that a party's failure to raise specific contractual defenses during arbitration precludes them from asserting those defenses in subsequent petitions, maintaining the integrity o....
Liquidated damages must be genuinely reflective of actual loss; their retention without proof of damage is unjustified under relevant contract provisions.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.