SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(AP) 1309

IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
R RAGHUNANDAN RAO, T.C.D. SEKHAR, JJ.
M/s. Sunrise & Engineering Industries - Appellant
Versus 
Hindustan Shipyard Limited – Respondent 
C.M.A.NOS.234, 242, 243, 244, 245, 246, 247, 248, 249, 253, 257, 258, 259 of 2025, Civil Miscellaneous Appeal No: 234 of 2025
Decided On : 31-12-2025

Advocates Appeared:
For the petitioner: Sri K. Srinivasa Rao
For the Respondent: Sri G. Ramesh Babu

JUDGMENT :

R. Raghunandan Rao, J.

As all these appeals raise the same issues and arise out of awards passed by the same Arbitrator, they are being disposed of, by way of this common judgment.

2. Respondent No.1 in all these cases is a Public Sector Undertaking, involved in the construction, fabrication and repairs of various kinds of vessels and other works. The 1st respondent had awarded sub-contracts to various sub-contractors for the aforesaid works. These contracts were awarded under separate work orders. All these work orders contained timelines within which the work was to be completed. In the event of failure to adhere to the timeline, all the contracts provided for liquidated damages to be levied @ 2% per week of delay up to a maximum of 20% of the contract value. The 1st respondent, on the ground that there was delay in all the aforesaid contracts, awarded to the appellants herein, had levied liquidated damages of 20% of the contract value and deducted the same in the bills of the appellants. Aggrieved by the said deduction of liquidated damages, the appellants sought reference to arbitration. A common arbitrator was appointed in all these cases.

3. The details of the claims made by the appellants and the awards passed by the learned Arbitrator are contained in the table set out below:

S.NoName of the PetitionerArbitration case number and Date of Arbitral AwardArbitration OP NO and date of orderCMA NO
1Sun rise and engineering industries001 of 2013
05/11/2016
ARB OP 257 of 2017
03/01/2025
234 of 2025
2Swapna fabrics and constructions003 of 2013
05/11/2016
ARB OP 2261 of 2017
03/01/2025
242 of 2025
3Sri Srinivasa engineering Works013 of 2013
05/11/2016
ARB OP 266 of 2017
03/01/2025
243 of 2025
4Nest builders and engineers012 of 2013
05/11/2016
ARB OP 259 of 2017
03/01/2025
244 of 2025
5Nest builders and engineers007 of 2013
05/11/2016
ARB OP 264 of 2017
03/01/2025
245 of 2025
6Bharat steel fabrication works015 of 2013
05/11/2016
ARB OP 256 of 2017
03/01/2025
246 of 2025
7Sri Srinivasa engineering Works014 of 2013
05/11/2016
ARB OP 255 of 2017
03/01/2025
247 of 2025
8Swapna fabrics and constructions010 of 2013
05/11/2016
ARB OP 262 of 2017
03/01/2025
248 of 2025
9Bharat steel fabrication works008 of 2013
05/11/2016
ARB OP 254 of 2017
03/01/2025
249 of 2025
10Perfect People009 of 2013
05/11/2016
ARB OP 263 of 2017
03/01/2025
253 of 2025
11KIM Fabs004 of 2013
05/11/2016
ARB OP 265 of 2017
03/01/2025
257 of 2025
12Patel Engineering Works006 of 2013
05/11/2016
ARB OP 258 of 2017
03/01/2025
258 of 2025
13Sunrise Engineering Industries005 of 2013
05/11/2016
ARB OP 260 of 2017
03/01/2025

259 of 2025

4. In all these claims, the case of the claimants can be placed under three heads.

i) The delay in the execution of the works entrusted to the appellants, were on account of the inaction as well as actions of the respondent herein including delay in providing clear facilities at ground level for works to be carried on, unrealistic work schedules, insufficient work area, not providing crane facility in needed times, delay in supply of consumables and processed elements, delay in clearing inter dependencies, delayed payments for completed works etc. The claimants contended that all these issues were brought to the notice of the respondents on a number of occasions and in relation to each of the works in particular. Thus, the delay in adherence to time schedule was not on account of claimants but only on account of the respondent.

ii) Similarly constituted contractors who had been awarded similar works had not been levied with liquidated damages and in some cases, revised schedules were also given with liquidated damage being reduced to 0.5% per week of delay subject to a maximum of 5% of the tender value.

iii) The quantum of liquidated damages @ 2% per week of delay subject to a maximum of 20% of the work is exorbitant, unconscionable, arbitrary, unjust, oppressive, illegal and unenforceable. This arbitrary conduct is further made out as similar works awarded by the respondent contained clause stipulating

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top