SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Mad) 179

IN THE HIGH COURT OF JUDICATURE AT MADRAS
N. Anand Venkatesh, J.
The Chairman, Chennai Port Trust - Petitioner
Versus
Mr. A. Manicavassalou - Respondent
Arbitration O.P. (Com.Div.) No.119 of 2023
Decided On : 09-02-2026

Advocates Appeared:
For the Petitioner: Mr. Haja Mohideen Gisthi, Standing Counsel
For the Respondent: Mr. D.Vivekanandan

Liquidated damages must be genuinely reflective of actual loss; their retention without proof of damage is unjustified under relevant contract provisions.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34(2)(b) - Challenge to arbitration award on grounds of patent illegality and perversity - The Arbitrator found that the petitioner unlawfully retained liquidated damages amounting to Rs.49,19,960/- despite the work being completed satisfactorily. The petitioner’s claim for liquidated damages was deemed unreasonable as it exceeded the contract value and failed to align with Clause 49 of the contract. (Paras 3, 8, 10-20)

(B) Principles of Liquidated Damages - The actual loss must be demonstrated to validate claims for liquidated damages. The levy of liquidated damages must reflect genuine pre-estimates of potential loss. (Para 15)

Facts of the case:
The petitioner engaged the respondent for restoration work with a scheduled completion of 10 months. The project was delayed, and the petitioner withheld substantial liquidated damages. The Arbitrator found the retention unjustified, contrary to evidence showing no actual loss. (Paras 1-4)

Findings of Court:
The Arbitrator's award to refund the liquidated damages was justified. No evidence of loss supported the retention of the amount. The claims beyond liquidated damages were awarded with sufficient rationale. (Paras 10, 20)

Issues: Whether the Arbitrator's award was tainted by patent illegality, especially concerning liquidated damages? (Paras 8, 10)

Ratio Decidendi: Retaining liquidated damages without proving actual loss violates contractual terms and established legal principles regarding genuine pre-estimates. (Paras 10-18)

Result: Petition dismissed.

Table of Content
1. factual background of the case. (Para 1 , 2)
2. arguments related to liquidated damages. (Para 4 , 5 , 6)
3. court's observations on the arbitration process. (Para 7 , 8 , 9)
4. key findings regarding liquidated damages. (Para 10 , 11 , 12 , 13)
5. legal rationale for the arbitrator's findings. (Para 14 , 15 , 16 , 17 , 18)
6. final conclusion and order. (Para 19 , 20 , 21)

ORDER :

N. Anand Venkatesh, J.

This petition has been filed by the petitioner under Section 34 of the Arbitration and Conciliation Act, 1996 (for short, the Act) against the award dated 06.4.2022 passed by the learned Arbitrator to the extent the claims made by the respondent/claimant were allowed.

2. Heard both.

3. The facts leading to filing of this petition are as follows:

(i) The petitioner issued a tender dated 24.2.2013 for restoration of the damaged revetment structure at east of east quay due to cyclones ‘Thane’ and ‘Nilam’. The respondent submitted his tender and was declared as a successful bidder, pursuant to which, the parties entered into an agreement on 03.10.2013. The work involved as many as 11 kinds of work and the respondent took over the site and commenced the work on 18.10.2013. As per the agreement, the time for completion of work was 10 months from the date of taking over the site and it was expected to be completed on 17.8.2014. However, the work was completed only on 24.9.2016 after extension of time was granted by the petitioner. Thus, there was a delay of 768 days in completing the work.

(ii) The petitioner sought to recover the liquidated damages from the respondent and withheld a sum of Rs.49,19,960/- towards the same. Apart from that, the respondent also had other claims against the petitioner. The trigger notice was issued and a petition was filed before this Court in O.P.No.763 of 2018 by the respondent. Pursuant to the order dated 06.12.2018 passed in the said original petition, the learned Arbitrator was appointed by this Court.

(iii) In the claim statement filed before the learned Arbitrator, the respondent/claimant made the following claims against the petitioner:

“A. To repay/return the liquidated damages to an extent of Rs.49,19,960/- (Rupees Forty Nine Lakhs Nineteen Thousand Nine Hundred and Sixty Only) wrongfully deducted from the claimant together with 18% interest per annum as mentioned in Annexure – A;

B. To return the Service Tax of a sum of Rs.7,23,754/- (Rupees Seven Lakhs Twenty Three Thousand Seven Hundred and Fifty Four Only) deducted contrary to the agreement from the claimant together with 18% interest per annum as mentioned in Annexure – B;

C. To return a sum of Rs.2,18,836/-(Rupees Two Lakhs Eighteen Thousand Eight Hundred and Thirty Six Only) wrongly deducted towards the room rent charges from the claimant together with 18% interest per annum as mentioned in Annexure – C;

D. To pay a sum of Rs.1,06,60,000/-(Rupees One Crore Six Lakhs and Sixty Thousand Only) towards the rental charges of the machinery viz., Excavator Ex 220 and a container for the extended period as mentioned in Annexure – D;

E. To pay a sum of Rs.29,38,000/-(Rupees Twenty Nine Lakhs and Thirty Eight Thousand Only) towards the salaries paid to the employees for the extended period as mentioned in Annexure – E;

F. To pay a sum of Rs.36,48,147.40/-(Rupees Thirty Six Lakhs Forty Eight Thousand Hundred and Forty Seven and Forty Paise Only) towards the escalation of materials procurement cost incurred during the extended period to the claimant as mentioned in Annexure – F;

G. To pay a sum of Rs.2,54,002/- (Rupees Two Lakhs Fifty Four Thousand and Two Only) towards the renewal of insurance charges which was time and again renewed by the claimant as mentioned in Annexure G;

H. To pay a sum of Rs.1,03,423.30/-(Rupees One Lakh Three Thousand Four Hundred and Twenty Three and Thirty Paise Only) towards the renewal of bank guarantee charges which was time and again renewed by the claimant as mentioned in Annexure – H';

I. To pay a sum of Rs.1,20,000/-

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top