SUPREME COURT OF INDIA
VIKRAM NATH, PRASANNA B. VARALE, JJ.
Ramayana Ispat Pvt. Ltd. and Another – Appellants
Versus
State of Rajasthan and Others – Respondents
Civil Appeal No. 7964 of 2019, Civil Appeal No. 7965 of 2019, Civil Appeal No. 7966 of 2019
Decided On : 01-04-2025
Key Points: - The Rajasthan Electricity Regulatory Commission (RERC) regulations on open access are valid and do not violate statutory rights under the Electricity Act, 2003 [judgement_subject]. - The RERC has the authority to regulate intra-state open access, even for power sourced from outside the state, as it impacts the Rajasthan grid (!) (!) . - Penalties for drawal variations are justified as necessary for grid stability and are not an unreasonable restriction on open access rights (!) (!) . - The 24-hour advance notice requirement for inter-state open access (Regulation 26(7)) is not ultra vires and serves a legitimate regulatory purpose for grid stability (!) (!) . - Regulation 21 is not arbitrary or discriminatory against captive power generators; differential treatment is based on structural differences in roles and obligations (!) (!) . - The Regulations of 2016 do not foreclose the right to open access but rather prescribe conditions for its fair and efficient implementation (!) (!) . - The High Court orders upholding the validity of the RERC's Regulations of 2016 are affirmed (!) (!) (!) . - The appeals challenging the RERC's Regulations of 2016 are dismissed (!) . - The regulations ensure grid stability and fair competition [judgement_subject]. - The RERC's power to regulate open access is derived from Sections 42 and 181 of the Electricity Act, 2003 (!) (!) .
JUDGMENT :
VIKRAM NATH, J.
1. The present appeals challenge two separate orders passed by the High Court of Rajasthan-one by the Jodhpur Bench dated 29.08.2016 and the other by the Jaipur Bench dated 06.09.2016. The appeals arise from challenges to the validity of the Rajasthan Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 20161 [Regulations of 2016] framed by the Rajasthan Electricity Regulatory Commission2 [RERC] in the exercise of its powers under Section 42 read with Section 181 of the Electricity Act, 2003.3 [Act of 2003] The primary grievance of the writ petitioners, appellants herein, before the High Court, and now the appellants before this Court, relates to the restrictions and conditions imposed by the Regulations of 2016 on the exercise of open access for captive power plants4 [CPPs.] and other large consumers of electricity.
2. The brief background of the facts giving rise to the challenge before us are that the writ petitioners before the High Court are engaged in industrial production and have substantial power consumption requirements. The facts, as taken by the High Court from one of the writ petitions filed by Hindustan Zinc Limited, respondent No. 6 in Civil Appeal No. 7966 of 2019, for convenience, are that Hindustan Zinc Limited is a public limited company incorporated under the Companies Act, 1956, and is engaged in the business of mining, smelting, and production of non-ferrous metals, including lead and zinc. The company operates multiple units at Chanderia, Dariba, and Zawar, which are supported by CPPs. In addition to captive power generation, the company also has agreements with Ajmer Vidhyut Vitran Nigam Limited (respondent No. 3 in Civil Appeal No. 7964 of 2019, respondent No. 2 in Civil Appeal No. 7965 of 2019, and respondent No. 3 in Civil Appeal No. 7966 of 2019) for the supply of power to meet its contractual demand. Under these agreements, Hindustan Zinc Limited is entitled to draw electricity up to 70 MW from the distribution licensee at its Dariba Zinc Smelter Unit at any time, as per its operational requirements.
3. Prior to the introduction of the Regulations of 2016, the appellants were availing open access under the Rajasthan Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 20045 [Regulations of 2004] which permitted them to draw power from both, their captive generation and open access sources, without any reduction in the contracted demand from the distribution licensee. The open access facility under the Regulations of 2004 allowed the appellants to schedule their power requirements on a day-ahead basis for each 15-minute block, with the flexibility to meet shortfalls through their contracted demand from the distribution licensee.
4. RERC issued a draft of the proposed Regulations of 2016 through a public notice dated 06.07.2015 and invited comments and suggestions. Hindustan Zinc Limited, along with other stakeholders, submitted detailed objections, highlighting that certain provisions of the draft regulations were inconsistent with the objectives of the Act of 2003 and the principle of promoting open access. The Commission notified the Regulations of 2016 on 27.01.2016.
5. The key change introduced by the Regulations of 2016 was the imposition of limitations on the simultaneous drawal of power through open access and contracted demand from the distribution licensee. Under the new regime, if a consumer opted to procure power through open access, the contracted demand from the distribution licensee would be reduced by the quantum of power scheduled through open access. Additionally, the Regulations of 2016 imposed penalties for over-drawal and under-drawal from the contracted demand.
6. The appellants before the Jodhpur Bench of the High Court challenged several specific provisions of the Regulations of 2016 on the ground that they were arbitrary, unreasonable, and contrary to the statutory scheme of the Act of 2003.
Energy Watchdog vs. Central Electricity Regulatory Commission
The Rajasthan Electricity Regulatory Commission's regulations on open access are valid, ensuring grid stability and fair competition, and do not violate statutory rights under the Electricity Act, 20....
Writ petitions under Article 226 against electricity regulatory commission orders fixing O&M charges not maintainable due to efficacious statutory appeal remedy under Section 111 of Electricity Act, ....
Regulations mandating captive power plants to purchase renewable energy are lawful under the Electricity Act, promoting environmental sustainability without violating constitutional rights.
The High Court declined to exercise jurisdiction over a writ petition due to the availability of an alternate statutory remedy under the Electricity Act, affirming that tariff regulation issues fall ....
Writ petitions challenging regulatory fixation of normative O&M charges as tariff component not maintainable due to statutory appeal to expert Appellate Tribunal under Electricity Act, absent jurisdi....
The Central Government lacks the legislative competence to frame rules regarding open access in electricity, which is exclusively regulated by the State Commission under the Electricity Act.
Writ under Article 226 not maintainable against regulatory order where statutory appeal available, issues involve disputed facts/law, and no jurisdictional error or natural justice violation; exhaust....
Provisions for duty of distribution licensee and open access has to be read conjointly.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.