SUPREME COURT OF INDIA
PAMIDIGHANTAM SRI NARASIMHA, JOYMALYA BAGCHI, JJ.
The State Of Himachal Pradesh & Anr. – Appellants
Versus
JSW Hydro Energy Limited & Ors. – Respondents
Civil Appeal No. 12883 of 2024
Decided on : 16-07-2025
JUDGMENT :
PAMIDIGHANTAM SRI NARASIMHA, J.
| Table of Contents |
| I. Introduction |
| II. Facts |
| III. Impugned Order |
| IV. Submissions |
| V. Issue |
| VI. Analysis |
| VII. Regulation of Electricity Generation Under the ELECTRICITY ACT |
| VIII. Legal Effect of Note 3 of Regulation 55 |
| i) Interpretation of the CERC Regulations, 2019 |
| ii) CERC’s Order dated 17.03.2022 |
| IX. Maintainability of the Writ Petition: |
| i) CERC as an Expert and Specialised Regulator, and Extent of Judicial Interference |
| ii) Grant of Relief by the High Court |
| X. Conclusion |
I. Introduction:
1. Respondent no. 1, a generating company, installed and commissioned a 1045MW hydroelectric power project pursuant to a grant followed by an Implementation Agreement with the appellant-State of Himachal Pradesh. Under this Agreement, respondent no. 1 undertook to supply as consideration 18% of net generation free of cost1[The obligation to supply free power is 12% of net generation from 12.09.2011 to 12.09.2023, and 18% thereafter till 12.09.2051.] to the appellant-State. At the commencement of the obligation to supply 18% free power, respondent no. 1 approached the High Court by way of a writ petition to align the Implementation Agreement with the CERC (Terms and Conditions of Tariff) Regulations, 20192[Hereinafter “CERC Regulations, 2019”.], which provide for a maximum of 13% free power to the State Government, on the ground that contractual agreements, to the extent that they are inconsistent with the applicable regulations, shall stand overridden by their operation. Accepting the argument, the High Court entertained the writ petition and directed that the Implementation Agreement stood modified.
2. We have allowed the appeal by the State of Himachal Pradesh by interpreting the provisions of the ELECTRICITY ACT , 20033[Hereinafter “ ELECTRICITY ACT ”.] and the CERC Regulations, 2019 in the context of the subsisting and continuing contractual relationship between the parties. We have held that the Central Electricity Regulatory Commission4[Hereinafter “CERC”.] shall give effect to the Regulations and provide a pass-through to the extent of 13% free power but the remaining part of the obligation is contractual in nature and will be governed by the provisions of the Implementation Agreement. On interpreting the cap under Note 3 of Regulation 55 of the CERC Regulations, 2019, we have held that it does not restrain or prohibit respondent no. 1 from supplying free power beyond 13% but it is only meant for the calculation and fixation of tariff. Further, considering the expertise and specialisation of the CERC as a statutory regulator and the wide- ranging jurisdiction it exercises under the ELECTRICITY ACT , as well as respondent no. 1’s conduct in not seeking relief against the appellant before the CERC, we have held that the present writ petition was not maintainable before the High Court as the interpretation of the Regulations falls within the exclusive domain of the regulator.
II. Facts:
3. The facts, to the extent necessary are as follows. By a Memorandum of Understanding5[Hereinafter “MoU”.] dated 28.08.1993, the appellant- State allotted the Karcham Wangtoo Hydroelectric Project for an installed capacity of 900 MW to one Jaiprakash Industries Limited6[Hereinafter “JIL”.], which is a power generating company and the predecessor of respondent no. 1. Under Clause 6 of the MoU, JIL agreed to supply 12% of the power generated to the appellant-State free of cost.
3.1 Pursuant to the MoU, the appellant entered into an Implementation Agreement with JIL for an enhanced capacity of 1000 MW. The relevant clauses of the Implementation Agreement are as follows:
i. Article 1.2 is the definitions clause that defines “Law” as any Act, rule, regulation, notification, order, or instruction having the force of Law enacted or issued by any competent legislature, government, or statutory authority in In
PTC India Ltd. v. Central Electricity Regulatory Commission
Transmission Corporation of A.P. Ltd. v. Rain Calcining Ltd.
Ganga Retreat and Towers Ltd. v. State of Rajasthan
W.B. Electricity Regulatory Commission v. CESC Ltd.
Sesa Sterlite Ltd. v. Orissa Electricity Regulatory Commission
Chameli Singh v. State of U.P.
Tata Power Co. Ltd. v. Reliance Energy Ltd.
Transmission Corporation of Andhra Pradesh Ltd. v. Sai Renewable Power (P) Ltd.
Gujarat Urja Vikas Nigam Ltd. v. Renew Wind Energy (Rajkot) (P) Ltd.
Haryana Power Purchase Centre v. Sasan Power Ltd.
Indsil Hydro Power & Manganese Ltd. v. State of Kerala
Reliance Infrastructure Ltd. v. State of Maharashtra
Cellular Operators Assn. of India v. Union of India
U.P. Power Corpn. Ltd. v. NTPC Ltd.
BSES Ltd. v. Tata Power Co. Ltd.
Transmission Corpn. of A.P. Ltd. v. Rain Calcining Ltd.
Maharashtra State Electricity Distribution Co. Ltd. v. Adani Power Maharashtra Ltd.
Writ petitions challenging regulatory fixation of normative O&M charges as tariff component not maintainable due to statutory appeal to expert Appellate Tribunal under Electricity Act, absent jurisdi....
Writ petitions under Article 226 against electricity regulatory commission orders fixing O&M charges not maintainable due to efficacious statutory appeal remedy under Section 111 of Electricity Act, ....
Tariff determination for hydro projects with enhanced capacity, binding nature of prior PPAs on successors, and writ jurisdiction limited; exclusive domain of regulatory commission, not courts, to fi....
The High Court declined to exercise jurisdiction over a writ petition due to the availability of an alternate statutory remedy under the Electricity Act, affirming that tariff regulation issues fall ....
The main legal point established in the judgment is that the interpretation and enforcement of Regulation 17 of the CERC Tariff Regulations fall within the adjudicatory powers of the Central Electric....
The interpretation of tariff regulations concerning power supply and agreements lies exclusively with the regulatory commission, and disputes must be adjudicated by it rather than the High Court.
The CERC possesses both regulatory and adjudicatory powers under the Electricity Act, allowing it to impose compensation for delays while retaining the framework under which such determinations are m....
Regulations mandating captive power plants to purchase renewable energy are lawful under the Electricity Act, promoting environmental sustainability without violating constitutional rights.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.