IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
V. SUJATHA, J.
GORLA YERIKALAIAH KADAPA DIST 85 OTHERS - Appellant
Versus
PRL SECY ICAD DEPT. HYD 2 OT - Respondent
Writ Petition No.12993 of 2017
Decided on : 21-11-2022
Constitution of India, 1950 - Article 226 - Land Acquisition Act, 1894 - Section 18 - Payment of compensation - Power of high court to issue certain writs - Wheather petitioners are entitled for compensation as per Standard Schedule Rate (SSR) prevailing as or as issuance of 4(1) notification - Held, Court is considered opinion that determination of market value of structures of petitioners as per SSR prevailing, though notification was issued under Section 4(1) of l Act, cannot be sustained and same is contrary to settled principles - Accordingly, petitioners are entitled for compensation for structures as per Standard Schedule Rate (SSR) prevailing as issuance of 4(1) notification - Endorsement issued by 3rd respondent are liable to be set aside - Writ petition allowed.
ORDER :
1. The writ petition is filed under Article 226 of the Constitution of India seeking the following relief:
2. The case of the petitioners, in brief, is that petitioners 1 to 40 and 42 to 86 are the residents of Kaluvoivandlapalli village, Hamlet of Varikunta village and post. The 2nd respondent-the Special Collector (Land Acquisition), had issued 4(1) Notification vide proceedings GNSS/D/335/05, dated 29.09.2005, which was published in District Gazette No.39, dated 01.10.2005, for acquisition of the petitioners structures (residential Houses, Cattle sheds and agriculture godowns) for the purpose of construction of Somasila project. The petitioners earlier filed W.P.No.24288 of 2005 challenging 4(1) notification dated 01.10.2005, on the ground that the respondents 2 and 3 have failed to notify their structures in 4 (1) notification. The said writ petition was disposed of by directing the respondents to note down the physical features of the permanent structures. Pursuant to the order passed by this court, the District Empowered Committee has been constituted by the 1st respondent headed by the District Collector to examine the matter and thereafter, the District Empowered Committee had instructed the respondents 2 and 3 to obtain fresh requisition from Engineering Department and decided to complete the inspection by the special teams and also directed the 3rd respondent to prepare draft notification and draft declaration proposals were approved and published. The District Empowered Committee had enumerated all the existing structures and submitted enumeration list to the District Empowered Committee. Pursuant to the enumerated list, the structures of the petitioners were categorised under five Heads.
3. Pursuant to the said categorization, the Engineering Department had sent estimation report to the respondents 2 and 3 by estimating the structure value prevailing in the year 2002-2003. The 3rd respondent had addressed a letter through his proceedings Ref.No.C/241/2005, dated 07.06.2006 to the Executive Engineer Somasila Project Division IV informing that several defects were found in the estimation report and requested him to verify the estimation report and re-submit the same for taking further action by showing the defects in the estimation report in respect of adopting the value of their structures as the structure values were shown in the estimation report on the Standard Schedule Rates prevailing in the year 2002-2003 instead of estimating the structure values at the Standard Schedule Rates prevailed as on the date of issuance of 4 (1) Notification i.e. 01.10.2005. The 3rd respondent, having addressed a letter dated 07.06.2006 and without obtaining a fresh estimation report from the Engineering Department, had erroneously passed consent award vide Award No.3/2006-2007, dated 31.07.2007 by determining the compensation with the Standard Schedule Rates prevailed in the year 2002-2003 though the petitioners are entitled compensation at the Standard Schedule Rates prevailing as on the date of issuance of 4(1) Notification dated 01.10.2005.
4. Further, the petitioners made a representation on 16.11.2006 to the 3rd responden
State of Karnataka and another v. Singappa Dyavappa Biradar and others
K. Peda Venkataiah and others v. Government of A.P. and others
Petitioners are not entitled to claim compensation for structures on enhanced rate, on the basis of Standard Schedule Rates of 2005-06.
In land acquisition for public infrastructure, market value should be based on credible guideline values as of the crucial date rather than stray sale deeds, and developmental charges are generally i....
Point of Law : Date of determination of market value should be recorded as 1.1.2014 in view of the Central Government orders under Section 113 of the Act.
The court affirmed that compensation for land acquisition must be based on legally established values, ensuring equity, and mandated interest payment from the date of possession, adhering to statutor....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.