IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
Subba Reddy Satti, J.
Narra Constructions Pvt. Ltd. - Petitioner.
Versus
State of Andhra Pradesh, Rep. by its Prl. Secretary (R&B) and three others - Respondents
Writ Petition Nos.42236 of 2017 and 39288 of 2018
Decided On : 15-11-2022
Constitution of india, 1949 – Article 14, 226 –Limitation Act, 1963 – Section 14 – Power of High Courts to issue certain writs – Equality before law – Exclusion of time in cases where leave to sue or appeal as a pauper is applied – Writ petitions were filed petitioner Private Limited Company represented by its Managing Directorn – Reliefs claimed in both writ petitions are interlinked they are dealt with jointly and disposed of by a common order – Held, Court is conscious that merely because parties to litigation raises a dispute with regard to facts of case – Court entertaining such writ petition is not always bound to relegate parties to a suit expressions of Hon’ble Apex Court writ petition is not a bar – Court is conscious that merely because one of parties to litigation raises a dispute with regard to facts of case – Court entertaining such writ petition under Article 226 of the Constitution of India is not always bound to relegate the parties to a suit. As per the expressions of Hon’ble Apex Court writ petition is not a bar – Court prerogative writ under Article 226 of Constitution of India will not be issued of petitioner not maintainable – W.P.No.39288 dismissed.
ORDER :
These writ petitions were filed by the petitioner Private Limited Company represented by its Managing Director. Since the reliefs claimed in both the writ petitions are interlinked, they are dealt with jointly and disposed of by a common order.
WRIT PETITION No.42236 of 2017
2. This writ petition is filed seeking Writ of Mandamus declaring the action of 4th respondent in terminating the contract under Clause 62.3 of GCC and not following the procedure contemplated under Clause 63 of GCC as illegal, arbitrary and against the terms of agreement and consequently direct the respondents to release the petitioner’s amount due under contract bearing CR.No.91/2013-04 dated 14.02.2014.
3. (a) In the affidavit filed in support of the writ petition, it was contended inter-alia that the Government of Andhra Pradesh called for tenders on 10.12.2013 through e-procurement for construction of multi-storied building after demolishing the sub-court building at Vijayawada; that bid was submitted on behalf of petitioner on 31.01.2014 and the petitioner’s company stood as lowest; that estimated value is Rs.43,26,72,948/- and petitioner quoted the bid amount at Rs.39,31,26,640.55/-, 9.14% less than estimated value; that 3rd respondent-Superintendent Engineer, R&B sent communication to the petitioner to sign the agreement, accordingly, agreement bearing No.CR.No.91/2013-14 was signed by 3rd respondent and authorized representative of petitioner; that site was handed over to petitioner on 14.02.2014, however designs and drawings were not made ready.
(b) Stipulated time for completion of contract is 36 months from the date of agreement; that entire site was not handed over; that designs and drawings were not supplied till 20.06.2015; that 3rd respondent concluded supplemental agreement after supply of designs and drawings and hence, the petitioner could not show work progress in initial period, in fact letters were addressed to 3rd respondent on 23.05.2015, 29.08.2016, 30.11.2016, 18.01.2017, 07.02.2017 and 27.02.2017 explaining the reasons for slow progress of work.
(c) On 10.02.2016 letter was addressed to 3rd respondent to arrange funds for making payment; that another letter dated 01.02.2017 was addressed stating that site is located adjacent to the Hon’ble Chief Minister’s Officer and hence, the police did not allow to ply vehicles; that police also did not allow to do contract work during day time in view of Pushkarams; that structural designs and drawings were handed over on 20.06.2017 and there is variation of work by more than 200%.
(d) Stipulated time for completion of contract was expired by 14.02.2017; that in letter dated 28.02.2017, a request was made to extend the time upto 31.08.2018 without liquidated damages and also submitted a revised programme; that 2nd respondent by letter dated 16.03.2017 extended the currency of contract upto 30.06.2018 by imposing liquidated damage of Rs.11 lakhs; that as per Clause 54 of GCC, the department has to impose liquidated damages only, when there is no possibility of extending currency of contract.
(e) 4th Respondent sent letter No.Court Complex @ VJA /A3/2013 dated 26.07.2017 terminating the contract as per Clause 62.3 of GCC and requested to take immediate action as per Clause 62.4 of GCC; that though the order is dated 26.07.2017, it was communicated to petitioner on 30.07.2017; that even after expiry of four months, neither 3rd respondent nor 4th respondent issued any certificate for the value of work done by petitioner as per Clause 63.1 of GCC.
(f) 3rd Respondent issued paper publication inviting tenders from the eligible contractors for the left over work, since the contract was terminated, petitioner is entitled to get the amount due to him from the department as per Clause 63.1; that nearly 4.5 crores was held up with the department, apart from bank guarantees and deposits submitted by t
A.V.Venkateswaran, Collector of Customs, Bombay Vs. Ramchand Sobhraj Wadhwani and Anr.
ABL International Ltd. and another Vs. Export Credit Guarantee Corporation of India Ltd. and others
Bhagawati Oxygen Ltd. Vs. Hindustan Copper Ltd.
K.S.Rashid and Son Vs. The Income-tax Investigation Commission
State of Bihar Vs. Jain Plastic and Chemicals Ltd.
Whirlpool Corporation v. Registrar of Trade Marks
Whirlpool Corporation, Vs. Registrar of Trade Marks, Mumbai and others
The main legal point established in the judgment is that in contractual matters, the court may not entertain a writ petition if there is a public law element, and the parties should resort to the con....
The court affirmed that principles of natural justice do not apply to non-statutory, purely contractual disputes where parties must adhere to the terms of their contract.
Writ jurisdiction can address arbitrary state actions in contractual disputes, emphasizing the importance of procedural fairness and adherence to contractual terms, especially regarding extensions an....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.