IN THE HIGH COURT OF KERALA AT ERNAKULAM
T.R. Ravi, J.
M/S Nath Infrastructures – Petitioner
Versus
Union Of India, Represented By Its Secretary, Ministry Of Home Affairs, Government Of India, North Block, Central Secretariat, New Delhi And Ors. – Respondents
WP(C) NO. 8260 of 2023, WP(C) No. 11720 of 2023
Decided On : 08-07-2025
| Table of Content |
|---|
| 1. factual background of the case. (Para 1 , 2 , 3) |
| 2. arguments regarding the extension of time. (Para 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12) |
| 3. court's observation on contractual obligations. (Para 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32) |
| 4. court's decision on the legality of terminations. (Para 33) |
JUDGMENT :
T.R. Ravi, J.
The petitioner in both these writ petitions is a partnership firm engaged in road construction. The firm undertakes projects for the Kerala Infrastructure Investment Fund Board (KIIFB), the National Highway Authority, and the Public Works Department. The Petitioner has satisfactorily completed several work contracts, including the Kuttipuram-Puthuponnani National Highway and National Highway 15/000 to 57/000 in Wayanad. The prayers in these writ petitions are intrinsically connected, and the writ petitions are being heard and disposed of together. The references to the exhibits and the status of the parties are -6- as per W.P.(C)No.11720 of 2023, which is treated as the main case.
2. The 5th respondent, who had been entrusted with the development, maintenance, and management of National Highway 766 including the section from km 25/1000 to km 45/1000, by the 1st respondent, invited proposals from eligible bidders for "strengthening and geometric improvements from km 25/1000 to km 45/1000 of NH 766 (old NH 212) in Kozhikode District in the State of Kerala on Engineering, Procurement, Construction ("EPC") mode." The petitioner was the successful bidder. An Engineering, Procurement, and Construction Agreement was executed on 07.08.2020. The site was handed over on 18.09.2020, on which day the work was to commence. The time for completion of the work was twelve months from the date of commencing the work and was to end on 17.9.2021. The petitioner had also executed a Bank guarantee as per the terms of the contract.
3. According to the petitioner, at the time of handing over the site, there were thirty trees, eighty electric posts, ten telephone poles, and one bus shelter at the site. The heavy rains during the years 2020 and 2021, and the statewide lockdown from 08.05.2021 to 30.06.2021 due to the outbreak of the COVID-19 pandemic, affected the procurement of materials and skilled labourers. The site was also earmarked as a Containment Zone on various occasions, and several labourers had also tested positive for the COVID-19 virus during that period. Even after the lockdown period, the work was carried out strictly adhering to the COVID-19 protocols, and all the above factors, according to the petitioner, resulted in slow progress of the project. The petitioner also submits that the structural works in different stretches were delayed due to the non-shifting of utilities and the failure to remove trees from the site. On 24.08.2021, the petitioner applied for an extension of time to complete the work. The request was forwarded by the 5th respondent to the Ministry of Road Transport & Highways (MoRTH), recommending the grant of time extension, by imposing a penalty on the petitioner. On 25.10.2021, the Executive Engineer wrote to the petitioner, directing them to submit a proposal for extension of time. This was followed by a letter from the Superintending Engineer asking them to submit a proposal for extension of time, without delay. The petitioner applied on 24.12.2021, seeking extension of time till 30.06.2022. On 4.2.2022, the Executive Engineer wrote to the Superintending Engineer, requesting that the time for completion of the work by the petitioner be extended up to 30.6.2022.
4. The Ministry of Road Transport & Highways (MoRTH) issued a Circular dated 11.04.2022, considering the COVID-19 pandemic, extending relief to contractors/developers of the road sector, for the period from 03.06.2022 to 31.10.2022. Taking note of the above circular, the 2nd respondent returned the proposal for extension of time to the 5th respondent, directing him to
Empire Jute Company Ltd. & Ors. v. Jute Corporation of India Ltd. & Anr.
Rukmanibai Gupta v. Collector, Jabalpur & Ors.
ABL International Ltd. V. Export Credit Guarantee Corporation of India Ltd.
Writ jurisdiction can address arbitrary state actions in contractual disputes, emphasizing the importance of procedural fairness and adherence to contractual terms, especially regarding extensions an....
The court emphasized that public authority's arbitrary termination of a contract without following due procedures violates principles of fairness and justness, meriting judicial intervention.
The court reinforced that the existence of an arbitration clause limits the scope for judicial intervention in contractual disputes involving the state.
Contract and Specific Relief – Jurisdiction - There is no cause of action and matter may be appropriately referred to appropriate forum as there is arbitral agreement between parties to address all i....
Writ under Article 226 not maintainable for contractual termination disputes involving factual questions when arbitration clause exists, natural justice not violated, and no public law issue raised.
Termination of Agreement - Disputed questions of fact which this Court cannot adjudicate in writ jurisdiction - Degree of compliance of the principles of natural justice applicable to administrative ....
The court affirmed that principles of natural justice do not apply to non-statutory, purely contractual disputes where parties must adhere to the terms of their contract.
The main legal point established in the judgment is the importance of abiding by the dispute resolution mechanism provided in the Agreement for resolving disputes arising from the contract. The Court....
The judgment emphasizes the limited scope of judicial review in contractual matters involving public authorities and the importance of resolving disputed questions of fact through alternate remedies,....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.