IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
U. Durga Prasad Rao, J.
Southern Power Distribution Company of Andhra Pradesh Limited and another - Petitioners
Versus
Central Electricity Regulatory Commission, (CERC) Rep. by its Chairman and others - Respondents
W.P. No.5212 of 2020
Decided On : 06-01-2023
ELECTRICITY ACT, 2003 - JURISDICTION - CERC - APERC - DISCOMS - SAFEGUARD DUTY - GST - BACK TO BACK AGREEMENT - WRIT PETITION - WRIT JURISDICTION - ALTERNATIVE REMEDY - TERRITORIAL JURISDICTION - CAUSE OF ACTION - COMPOSITE SCHEME - CHANGE IN LAW EVENT - PRIVITY OF CONTRACT - NATURAL JUSTICE - PUBLIC HEARING - TARIFF - MITIGATIVE MEASURES - CONFIDENTIALITY - DELAY - FACTUAL AND LEGAL ERRORS - EX PARTE ORDER - REMAND.
Fact of the Case:
NTPC entered into a Power Sale Agreement (PSA) with the petitioners, Southern and Eastern Power Distribution Companies (DISCOMs) of Andhra Pradesh, for the supply of 250 MW of solar power under Bundling Scheme. NTPC selected the 3rd respondent, a Solar Power Developer (SPD), to supply solar power at a tariff of Rs.3.15 ps per unit. The 3rd respondent filed a petition before the Central Electricity Regulatory Commission (CERC) claiming entitlement of Safeguard Duty Tax (SDT) and GST on SDT for a total amount of nearly Rs.162.00 Cr. in addition to the tariff of Rs.3.15 ps per unit. The petitioners challenged the CERC's order allowing the 3rd respondent's claim, arguing that the CERC lacked jurisdiction, there was no privity of contract between them and the 3rd respondent, and the principles of natural justice were not followed.
Finding of the Court:
1. The CERC had jurisdiction to entertain the 3rd respondent's claim petition as the generation and distribution of power took place in more than one State. 2. The PSA and PPA were inter-connected and inextricable link to each other and as such there was a privity between the claim petitioners and respondents i.e., DISCOMs before it. 3. The CERC ought to have afforded further reasonable time to the petitioners to submit their counter and to address arguments. 4. The impugned order is set aside and the matter is remitted back to the CERC for fresh consideration.
Issues: 1. Whether the CERC had jurisdiction to entertain the 3rd respondent's claim petition. 2. Whether there was privity of contract between the petitioners and the 3rd respondent. 3. Whether the principles of natural justice were followed. 4. Whether the CERC erred in its findings and conclusions.
Ratio Decidendi: 1. The CERC has jurisdiction to adjudicate upon disputes involving generating companies or transmission licensees in regard to matters connected with clauses (a) to (d) of Section 79(1). Clause (b) obviously relates to the power of CERC to regulate the tariff of generating companies other than those owned by Central Government, if such generating companies enter into a composite scheme for generation and sale of electricity in more than one State. 2. The PPA and PSA are inter-connected and inextricable link to each other and as such there is a privity between the claim petitioners and respondents i.e., DISCOMs before it. 3. The CERC ought to have afforded further reasonable time to the petitioners to submit their counter and to address arguments. 4. The impugned order is set aside and the matter is remitted back to the CERC for fresh consideration.
Final Decision: The impugned order dated 05.02.2020 in petition No.176/MP/2019 passed by the 1st respondent is hereby set aside and matter is remitted back with a direction to the 1st respondent to afford sufficient opportunity to the petitioners herein to file their counters and hear all the parties and consider their submissions and pass an appropriate order afresh in accordance with governing law and rules without being influenced by its earlier findings in the impugned order.
ORDER :
The petitioners pray for a Writ of Certiorari calling for records relating to the orders in petition No.176/MP/2019 dated 05.02.2020 passed by the 1st respondent holding that the 2nd respondent / NTPC has to pay safeguard duty and GST to the 3rd respondent and that the 2nd respondent is entitled to claim the said amount from the petitioner DISCOMs on back-to-back basis and quash the said order as illegal, arbitrary, discriminative and without jurisdiction and contrary to the provisions of the Electricity Act, 2003 and agreement entered into by the parties and pass such other order.
2. The factual matrix of the case in nut shell is thus:
(b) While so, the 2nd respondent following bidding process, selected the 3rd respondent who is a SPD to supply solar power at a tariff of Rs.3,15 ps per unit from their 250 MW solar power plant proposed at Kadapa Ultra Mega Solar Park for 25 years from the date of commission of their project. The respondents 2 and 3 entered into a Power Purchasing Agreement (PPA) dated 07.02.2018 in this regard but the petitioners are not privy to the said agreement. The 3rd respondent with a delay of three months commissioned part capacity of 200 MW.
(c) As per the PSA entered into by the petitioners and 2nd respondent, the disputes if any shall be referred to Appropriate Commission and further, the PSA shall come into force after the approval of Appropriate Commission. The phrase ‘Appropriate Commission’ has been defined in the PSA. As per PSA, the entire power of the SPD i.e., the 3rd respondent was agreed to be sold to the petitioners in Andhra Pradesh state. Due to all these facts, APERC alone is the appropriate Commission as per Section 86 of the Electricity Act, 2003 (for short ‘Act, 2003’). That is why, with the consent of 2nd respondent, the petitioners have submitted PSA to the APERC for approval with regard to the procurement of the power. Pending the proceedings before the APERC, the 3rd respondent commissioned the project with a part capacity of 200 MW on 03.05.2019 and with a delay of three months.
(d) The APERC vide its common order dated 05.10.2019 granted approval to the procurement of 750 MW from NTPC, 250 MW from NTPC and 750 MW from SPCL with the conditions mentioned thereon. The SPDs filed O.P. No.368/2019 before appellate Tribunal for electricity at New Delhi and an interim stay was granted.
(e) While so, the petitioner came to know that the 3rd respondent filed a petition No.176/MP/2019 dated 14.06.2019 against the 2nd respondent before the 1s
Babubhai Muljibhai Patel v. Nandlal Khodidas Barot MANU/SC/0404/1974 : (1974) 2 SCC 706
Bloom Dekor Limited v. Subhash Himmatlal Desai and others
Chattisgarh State Electricity Board v. CERC and others (2010) 5 SCC 23
Cicily Kallarackal v. Vehicle Factory
Energy watchdog and others vs. CERC
Harbanslal Sahnia v. Indian Oil Corporation Ltd.
Kanaiyalal Lalchand Sanchdev v. State of Maharashtra
Kusum Ingots and Alloys Ltd v. Union of India
Navinchandra N Majithia v. State of Maharashtra
Oil and Natural Gas Commission v. Utpal Kumar Basu
Prakash Chander Manchanda v. Janki Manchanda
Radha Krishan Industries v. State of Himachal Pradesh’s
Rajasthan High Court Advocates Association v. UoI
Rajasthan SEB v. Union of India MANU/SC/7628/2008 : (2008) 5 SCC 632
Seth Chand Ratan v. Pandit Durga Prasad MANU/SC/0256/2003 : (2003) 5 SCC 399
The Executive Engineer v. Seetaram Rice Mill
Union of India v. R. Thiyagarajan
The CERC has jurisdiction to adjudicate upon disputes involving generating companies or transmission licensees in regard to matters connected with clauses (a) to (d) of Section 79(1). Clause (b) obvi....
Writ petitions challenging regulatory fixation of normative O&M charges as tariff component not maintainable due to statutory appeal to expert Appellate Tribunal under Electricity Act, absent jurisdi....
The jurisdiction of CERC is limited to matters covered by clauses (a) to (k) of Sub-Section 1 of Section 79 of the Electricity Act, 2003.
The main legal point established in the judgment is the application of the doctrine of forum conveniens in determining the territorial jurisdiction of the High Court under Article 226 of the Constitu....
The existence of an alternative appellate remedy precludes maintaining a writ petition unless exceptional circumstances justify bypassing it; KERC did not act beyond its jurisdiction when determining....
The Central Commission has exclusive jurisdiction to adjudicate disputes concerning tariff under inter-state Power Purchase Agreements and can refer non-tariff disputes for arbitration.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.