IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
NINALA JAYASURYA, J.
V. Prabhakar – Petitioner
Versus
The Transmission Corporation of A.P. Limited – Respondent
Writ Petition No. 8214 of 2017
Decided On : 08-05-2024
Electricity - Writ of Mandamus - Indian Telegraph Act, 1885; Electricity Act, 2003 - The court examined the legality of the respondents' actions in laying transmission lines and erecting towers on the petitioner's land, emphasizing adherence to statutory provisions and principles of natural justice.
Fact of the Case:
The petitioner, owner of horticultural land, challenged the respondents' decision to lay a high-tension line and erect a tower on his property, claiming the actions were arbitrary and violated natural justice principles due to lack of proper notification and opportunity to object.
Finding of the Court:
The court found that the respondents acted within their statutory powers under the Electricity Act and the Indian Telegraph Act, and that the petitioner was not denied natural justice as the notification process was legally sufficient.
Issues: Whether the respondents' actions in laying the line and erecting the tower were arbitrary, violated principles of natural justice, and contravened relevant regulations.
Ratio Decidendi: The court held that the statutory framework under the Electricity Act and the Indian Telegraph Act allowed the respondents to proceed without individual notifications to landowners, and that the actions taken were not arbitrary or mala fide.
Result: The writ petition is dismissed.
ORDER :
1. The writ petition is filed seeking the following relief:
2. The basic case of the petitioner as culled out from the affidavit filed in support of the writ petition may briefly be stated as follows:
The respondents have taken up the work of construction of 400 KV Electrical Sub-Station at Kamavarapu Kota Village to connect the same with 400/220 KV Sub-Station located at Vemagiri, East Godavari District and started laying of the connecting line. As per the alignment planned, the respondents have given the markings for all the towers for laying the said line. But no such markings were given in respect of the petitioner’s lands. In other words, by the said alignment, there was no proposal for laying the line to go through the petitioner’s lands and therefore, no survey was done with regard to the petitioner’s lands nor any peg marks were marked.
On 22.12.2016, the 7th respondent along with the supporting staff and others visited the petitioner’s land for the purpose of giving tentative markings for laying a Tower on the South Western side of the land and damaged the plantation in that area. The respondents have changed the alignment with a mala-fide intention, in order to protect the interest of the owners of the land adjoining or opposite to the petitioner’s land. The petitioner under those circumstances, made representations to the concerned respondent authorities to call for the Survey Reports/Sketches to comprehend the issue and take steps to rectify the same.
The 7th respondent addressed a Letter/Notice dated 15.02.2017 to the petitioner informing that the above mentioned line is passing through the petitioner’s fields/lands in Survey No. 259 and a Tower (location No. 87/1) is to be constructed in the petitioner’s land and the foundation work will be started within 15 days. The action of the respondent-authorities in changing the alignment of line is arbitrary, mala-fide one and only with a view to see that the line do not pass through the land of the other owners and to favour them. Hence, the present writ petition.
3. Heard Mr. Ravindranath Reddy, learned Senior Counsel appearing on behalf of the petitioner. Also heard Mr. O. Manohar Reddy, learned Senior Counsel along with Mr. Anoop Koushik Karavadi appearing on behalf of the respondent-authorities.
4. The learned Senior Counsel for the petitioner while referring to the chronological events and the material placed on record made his submissions. He submits that the 3rd respondent issued a Noti
Bhavngar University v. Palitana Sugar Mill (P) Limited
Gunwant Kaur v. Municipal Committee, Bhatinda
Girias Investment Private Limited v. State of Karnataka
Power Grid Corporation of India Ltd. v. Century Textiles and Industries Ltd. (2017) 5 SCC 143
Ramniklal N. Bhutta v. State of Maharashtra
State of Orissa v. Dr. Binapani Dei and Others
Union of India v. Indo-Afghan Agencies Ltd. 1987 (4) SCC 482
The court affirmed that statutory authorities can lay transmission lines without individual notifications to landowners, provided they follow the established legal framework.
The main legal point established in the judgment is that once the technical feasibility of an electricity project is approved by the appropriate Government, the landowner has no right to object to th....
It is the prerogative of the transmission company to decide the route and whereas there is clear absence of any cogent and reliable material in support of the allegation of mala-fide, therefore also ....
The authority under the Indian Telegraph Act has the right to lay transmission lines on private property, prioritizing public interest and following due process, including compensation for any damage....
Section 164 of Electricity Act, 2003, no land owner or person interested can seek for shifting or realigning of the route, on the premise that the District Collector-cum-District Magistrate, has powe....
Section 10(d) there are two mandatory requirements; (1) Telegraph Authority shall do as little damage as possible; and (2) to pay full compensation to all persons interested for the damage sustained ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.