SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(AP) 1289

2025 APHC 37032
IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
HARINATH N., J.
Jampana Ravi Kishore S/o Jampana Ramakrishna Raju – Appellant
Versus
The State of Andhra Pradesh – Respondent
Writ Petition No. 27480 of 2024, Contempt Case No. 1309 of 2025
Decided On : 10-09-2025
Advocates Appeared : 
For the Appellant : V. Vinod K. Reddy
For the Respondents : A.S.C. Bose, K.V.S.D. Ravi Teja

Advocates:
For the Appellants/Petitioners: Sri K.S. Murthy
For the Respondents:Learned standing counsel for the respondent Nos.2 to 4, and learned counsel appearing for the 6th respondent

Judicial review cannot adjudicate property title claims while assessing administrative actions; these should be properly contested in court.

Headnote:(A) Article 226 of the Constitution of India - Writ jurisdiction - The petitioners challenged the legality of the building permission granted to the sixth respondent, claiming violation of earlier orders by this Court - The issue of title was not adjudicated, therefore, claims over property rights remain unresolved. (Paras 8-30)

(B) Contempt of Court - Allegations were made regarding non-compliance with interim orders - The Court reinforced that only relevant jurisdiction issues were to be considered and determined - No grounds established to interfere. (Paras 10-30)

Facts of the case:
Petitioners alleged that building permission granted to respondent No.6 was without any title on the property they owned; petitioners presented several legal documents that underpinned their ownership claims.

Findings of Court:
The findings stated were largely circumstantial, involving review of documents without adjudicating definitive property title rights before a proper court.

Issues: The court considered whether the actions of respondent No.2 were beyond jurisdiction, especially regarding interpreting title claims during the proceedings.

Ratio Decidendi: The Court outlined that property title issues could not be determined through interim orders, especially when the underlying facts are still under litigation; hence, orders made by respondent No.2 cannot be seen as beyond jurisdiction.

Result: Writ petition dismissed without costs.

Table of Content
1. petitioners challenge administrative orders. (Para 1 , 2)
2. property ownership and historical claims analyzed. (Para 3 , 4 , 5)
3. counterclaims regarding construction permissions. (Para 6 , 7)
4. judicial authority asserted in property disputes. (Para 8 , 9 , 10)
5. scrutiny of jurisdiction in the facts presented. (Para 11 , 12)
6. prior rulings referenced for current permissions. (Para 13 , 14 , 15)
7. final decision against interference. (Para 29 , 30)

ORDER :

1. The petitioners are aggrieved by the order passed by the respondent No.2 vide RC No. E Office 364478/2024/ACP-IV/G1, dated 29.05.2024. It is alleged that the respondent No. 2 has not considered the orders passed by this Court in WP.No.25966 of 1998 and WA.No.1359 of 2004 and passed the impugned proceedings, which deserve to be set aside.

2. The contempt case is filed alleging violation of the interim orders passed by this Court on 26.11.2024 in IA.No.1 of 2024, whereby this Court directed the respondents not to interfere with the possession of the petitioners' property for an extent of 1743 Square Yards in TS.No.1031, Visakhapatnam Municipal Corporation Limits.

3. The grievance of the petitioners is that the respondent No.6 had obtained permission for construction without having any right, title or interest over the property which belongs to the petitioners. It is submitted that the petitioners purchased the property vide a registered sale deed on 31.07.2015 from their vendor, Sri K.S.N. Raju. It is also submitted that the vendors of the petitioners purchased the land by virtue of the registered sale deed on 05.06.1970 from one V.Manikyeswara Rao. It is also submitted that ever since the petitioners purchased the said property, they have been in continuous possession and enjoyment of the property and have also constructed an asbestos sheet shed. It is also submitted that the competent municipal authorities have assessed the property for taxes and have also issued a house number for the property of the petitioners.

4. Learned Senior Counsel Sri K.S.Murthy, appearing for the petitioners, submits that the petitioners purchased the property vide a registered sale deed on 31.07.2015. However, the Sub-Registrar did not release the registered document; the document was issued a pending No.P 383 of 2015. It is also submitted that the 2ndpetitioner filed an appeal before the District Registrar and Appellate Authority vide Appeal No.3 of 2023, aggrieved by the denial of registration and release of the registered document. The District Collector, Visakhapatnam, had allowed the appeal and directed the concerned Sub Registrar to release the registered document.

5. Accordingly, the Sub-Registrar released the registered document to the petitioners on 27.04.2023. The petitioners are the absolute owners and possessors of land admeasuring 1743 square yards in TS.No.1031. It is submitted that on receipt of a complaint from a third party, the Electricity Department had disconnected the power connection to the petitioners' property. The petitioners filed a WP.No.32405 of 2022 challenging the action of removal of the electricity meter. This Court allowed the Writ Petition vide order dated 18.11.2022. The respondents therein were directed to restore the electricity connection.

6. The learned Senior Counsel further submits that, as things stood thus, the 6th respondent obtained building permission on 14.07.2020 over an extent of 608.88 square meters out of the total extent of land of 1743 square yards. It is submitted that the 6th respondent had played fraud and obtained the building permission. It is the case of the respondent no. 6 that a Development Agreement cum GPA was executed between the respondent Nos. 5 and 6 on 09.08.2012. On the strength of the said document, the 2ndrespondent had granted permission for construction. It is submitted that the 5th respondent claims to have acquired title over the property by virtue of an unregistered agreement of sale dated 14.08.1974. It

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top