IN THE HIGH COURT OF KARNATAKA AT BENGALURU
ARAVIND KUMAR, J.
ITC Infotech India Limited – Petitioner
Vs.
Venkataramana Uppada – Respondent
Writ Petition No. 27510 of 2015
Decided On : 03-03-2016
LIFE INSURANCE CORPORATION ACT, 1956 - Section 14 & Industrial Disputes Act (14 of 1947), Section 2A (3): [Aravind Kumar, J] Condonation of delay - Claim petition filed after period of 5 years from date of dispute - Plea of workman to exclude period spent before wrong forum for calculating limitation - Provisions of Section 2A(3) of Industrial Disputes Act made it mandatory to file claim petition within three years from date of dispute, failing which proceedings would lapse - Held, Provisions of Limitation Act not applicable as mandatory limitation of three years prescribed by provisions of Section 2A(3) of Industrial Disputes Act. Period spent in wrong forum cannot be excluded.
1. In this Writ Petition, order dated 17.03.2015 passed in I.D. No. 6/2014 by the Principal Labour Court, Bengaluru, Annexure-A is impugned.
2. A claim petition filed under Section 2A(2) of the Industrial Disputes Act, 1947 (for short I.D. Act) came to be filed on 13.02.2014 by the respondent herein, questioning termination letter dated 11.02.2009 – Annexure-O. An interlocutory application under Section 11-A of the I.D. Act read with Section 5 of the Limitation Act, 1963 and Section 151 CPC – Annexure-P came to be filed seeking for condonation of the delay of 730 days in filing the claim petition. Said application having been allowed by the impugned order has been called in question by the employer-Management in this writ petition.
3. Heard Sri. K. Kasturi, learned Senior Counsel appearing on behalf of petitioner and Sri. Venkataramana Uppada, respondent appearing in person.
4. It is the contention of Sri. K. Kasturi, learned Senior counsel appearing for writ petitioner that Labour Court is not vested with the power to condone the delay under Section 2A(2) or under Section 10(4A) of the I.D. Act when claim petition is filed beyond three years from date of dismissal or discharge and as such application for condonation of delay filed by employee ought to have been dismissed by the Labour Court. He would elaborate his submission by contending sub-section (3) of Section 2A of I.D. Act mandates that an workman can make an application before expiry of three years from the date of discharge, dismissal, retrenchment or otherwise as provided under sub-section (1) and there being a delay of 5 years 2 days in filing the claim petition from the date of termination, Labour Court ought not to have condoned the delay. He would also submit that registry of the Labour Court itself had raised office objection with regard to maintainability of claim petition as noted in the order sheet Annexure-R and as such Labour Court ought to have sustained said office objection and it ought not to have condoned the delay in filing the claim petition by allowing the application filed by the respondent for condonation of delay. Hence, he prays for allowing the writ petition and rejecting the application for condonation of delay and consequently dismissing the claim petition.
In support of his submissions, he has relied upon following Judgments:-
(1) Sri. Amar Chand Inani vs. Union of India, (1973) 1 SCC 115
(2) Nedungadi Bank Ltd. vs. K.P. Madhavankutty and Others, (2000) 2 SCC 455
(3) Rajasthan State Road Transport Corporation and Others vs. Zakir Hussain, (2005) 7 SCC 447
(4) Damodaran Pillai and Others vs. South Indian Bank Limited, (2005) 7 SCC 300
(5) Kendriya Vidyalaya Sangathan vs. Arun Kumar Madhavrao Sinddhaye and Another, (2007) 1 SCC 283
(6) Foreshore Coop. Housing Society Ltd. vs. Praveen D. Desai, (2015) 6 SCC 412
(7) Pandurang Dhondi Chougule and Others vs. Maruti Hari Jadhav and Others, AIR 1966 SC 153
(8) Pyare Lal Sharma vs. Managing Director, Jammu and Kashmir Industries Ltd. and Others, AIR 1989 SC 1854
(9) KSRTC vs. Abdul Azeez, (2004) 107 FJR 155 (KAR)
(10) Executive Engineer and Others vs. Lokesh Reddy and Others, 2003 (3) LLJ 118
(11) Commissioner of Sales Tax, UP vs. Parson Tools and Plants, Kanpur, 1975 (2) Laws (SC) 4
(12) Executive Engineer BRLBC Division, Shivamogga vs. Lokesh Reddy, 2003 (4) Laws (KAR) 5
(13) Haryana State Co-operative Land Development Bank vs. Neelam, 2005 (2) Laws (SC) 87
(14) Rukmini Bai and Others vs. Divisional Controller NEKRTC, Bidar, ILR 2013 (KAR) 1024
(15) Nityanand M. Joshi and Others vs. Life Insurance Corporation of India and Others, (1969) 2 LLJ 711
(16) State of Karnataka vs. Sri. K. Veergowda, W.P. No. 18723 of 2015, dated 01.06.2015
(17) P.K. Ramachandran vs. State of Kerala and Another, (1997) 7 SCC 556
5. Per contra, Sri. Venkataramana Uppada, respondent – party-in-person would support the impugned order
Sri. Amar Chand Inani vs. Union of India
Nedungadi Bank Ltd. vs. K.P. Madhavankutty and Others
Rajasthan State Road Transport Corporation and Others vs. Zakir Hussain
Damodaran Pillai and Others vs. South Indian Bank Limited
Foreshore Coop. Housing Society Ltd. vs. Praveen D. Desai
Pandurang Dhondi Chougule and Others vs. Maruti Hari Jadhav and Others
P.K. Ramachandran vs. State of Kerala and another
Director, Food and Supplies, Punjab and Another vs. Gurmit Singh
Executive Engineer and Others vs. Lokesh Reddy and Others
Kendriya Vidyalaya Sangathan vs. Arun Kumar Madhavrao Sinddhaye and Another
Pyare Lal Sharma vs. Managing Director, Jammu and Kashmir Industries Ltd. and Others
Nityanand M. Joshi and Others vs. Life Insurance Corporation of India and Others
Collector, Land Acquisition, Anantnag and Another vs. Master Katiji and Others
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.