SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Kar) 1344

IN THE HIGH COURT OF KARNATAKA
ALOK ARADHE, ANANT RAMANATH HEGDE, JJ.
Mr.Sumanth Reddy and ors. - Appellants
Versus
Jaganmayi Builders And Develpers Private Ltd. and ors. - Respondents
MFA No.7929 of 2022 (AA).
Decided on : 06-07-2023

Advocates Appeared:
For the Appellant :Sri D.R.Ravishankar, Sr.Counsel For Sri Ramu S., Advocate.
For the Respondent:Sri G.L.Vishwanath Sr.Counsel For Sri Arun Pradesh E, Advocate

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 37(1)(b) - Appeal against order directing cash security of Rs.50 crores along with interest @ 18% per annum and restraining respondents from alienating properties - Appeals arose from an MOU and supplementary agreement on development of properties, with disputes regarding arbitration clause and alleged violations - Court held prima facie case for security, but also modified the restraint order. (Paras 1, 19, 28, 34)

(B) Arbitration - Jurisdiction and powers of court under Section 9 - Court can grant interim measures and security even if there are disputes over agreements; proof of intent to defeat arbitration is not imperative but balance of convenience must be assessed. (Paras 22)

Facts of the case:
The appellants and respondents entered into a MOU for property development, with security deposits totaling Rs.50 crores. The respondents alleged breaches and sought relief under Section 9 of the Arbitration Act after the appellants contested the existence of an arbitration clause. (Paras 3-6)

Findings of Court:
Court found prima facie grounds to direct the appellants to furnish cash security and found no grounds to interfere with the requirement of security for the interest on the principal amount. (Paras 28-31)

Issues: The court addressed existence of arbitration clauses, violations of agreements, and appropriateness of security measures under Section 9. (Paras 10, 12, 15)

Ratio Decidendi: The court confirmed that an enforcement of the agreement for security was justified, and clarified that interim measures do not require proof of intent to thwart arbitration, emphasizing the balance of convenience to grant relief to maintain the status quo. (Paras 22, 34)

Result: Appeal partly allowed with modification of the restraint order.

Table of Content
1. formation of the mou and security deposit acknowledged (Para 3 , 4)
2. arguments against the arbitration clause's applicability (Para 5 , 10 , 11)
3. obligations under mou and supplementary agreement clarified (Para 12 , 13 , 14 , 15)
4. assertions regarding defaults by the appellants (Para 16 , 17 , 18)
5. supreme court precedent applied to interim relief considerations (Para 19 , 20)
6. court's analysis on security deposit and interest awarded (Para 28 , 29 , 30 , 31 , 32)
7. timeline for furnishing security and conditions applied (Para 34 , 35)
8. conclusion on the appeal and order modification (Para 38)

JUDGMENT :

Mr. Anant Ramanath Hegde, J. - This appeal under Section 37 (1)(b) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the 'Act, 1996' for short) has been filed by the respondents in the proceeding under Section 9 of the Act. In terms of the order dated.29.10.2022 the application is allowed and the respondents are directed to furnish cash security of Rs.50.00 crores along with interest @ 18% per annum from the date of payment. The respondents have also been restrained from alienating or creating any third-party interest over petition properties (hereinafter referred to as 'schedule properties') till the disposal of arbitration proceedings.

2. The parties to the proceeding are referred to as appellants and respondents, as per their designation before this Court.

3. Brief facts necessary for adjudication of the case can be summarised as under:

- the appellants and respondent No.1 entered into a Memorandum of Understanding (MOU) on 06.10.2018 to develop scheduled properties. Thereafter, on 04.12.2018 a supplementary agreement was executed modifying certain terms and conditions of the MOU.

4. On 10.10.2018 the respondents paid Rs.25.00 crores to the appellants as security deposit. Later, on 3.12.2018, respondents paid Rs.25.00 crores to the appellants. In all Rs.50.00 crores is paid towards security deposit. The payment of Rs.50.00 crores is not in dispute. The appellants acknowledge the receipt of Rs.50.00 crores.

5. Alleging violation of the terms and conditions of the MOU as well as supplementary agreement, the respondents filed petition under Section 9 of the Act, 1996 praying some interim measures before the commencement of the arbitral proceedings. The appellants opposed the Section 9 petition and urged that there is no arbitration clause and prayed for dismissal of the petition on merits.

6. It is relevant to note that in a petition filed under Section 11 of the Act, 1996, this Court has kept open the question of the existence of an arbitration clause to be decided by the arbitrator.

7. After hearing the parties, the District Court allowed the application and directed the appellants to furnish cash security of Rs.50.00 crores along with interest @ 18% per annum from the date of payment.

8. Aggrieved by the said order, the appellants are in appeal.

9. Heard Sri D.R. Ravishankar, learned Senior Counsel for the appellants and Sri G. L. Vishwanath, learned Senior Counsel for the respondents.

10. Learned Senior Counsel appearing for the appellants submitted that the question relating to the maintainability of the proceeding before the arbitrator is kept open, and that being the position, the impugned order could not have been passed. It is urged that in view of the supplementary agreement dated 04.12.2018, the earlier agreement dated 06.10.2018 stands superseded in respect of the matters contained in the supplementary agreement, and the arbitration clause is not found in the supplementary agreement dated 04.12.2018, as such the dispute is not arbitrable and Court acting under Section 9 of the Act, 1996 does not have the jurisdiction to entertain the petition.

11. The claim for payment of interest @ 18% per annum is nothing but the claim for damages as such there cannot be an order to furnish the security for the amount claimed by way of damages.

12. Learned Senior Counsel appearing fo

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top