IN THE HIGH COURT OF JUDICATURE AT BOMBAY, BENCH AT AURANGABAD
Sandeep V. Marne, J.
M/s. Mehra & Company, Through its Partner, Mr. Shailendra Mahendraprasad Mehra - Applicant
Versus
The State of Maharashtra - Respondents
Arbitration Application No. 4 Of 2016
Decided On : 02-12-2022
Arbitration - Appointment of Arbitrator - Arbitration and Conciliation Act, 1996, Section 11 - 30(1), 30(2), 30(3)
Fact of the Case:
The application was filed for the appointment of an arbitrator under section 11 of the Arbitration and Conciliation Act, 1996. The court considered the interpretation of clauses 30.1, 30.2, and 30.3 and held that there was no valid arbitration agreement between the parties, dismissing the application.
Finding of the Court:
The court found that the clauses in question did not constitute a valid arbitration agreement and therefore the application under section 11(6) of the Act of 1996 was dismissed.
Issues: The main issue was whether the clauses 30.1, 30.2, and 30.3 constituted a valid arbitration agreement between the parties.
Ratio Decidendi: The court held that the clauses in question did not contain the words 'arbitration' or 'arbitrator' and merely provided for departmental remedies, indicating the absence of a valid arbitration agreement.
Final Decision: The application filed under section 11(6) of the Act of 1996 was dismissed, and it was concluded that there was no arbitration agreement between the parties.
JUDGMENT :
1. This application is filed for appointment of arbitrator under sub section 6 of section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as "the Act of 1996" for the sake of brevity).
2. The relevant clauses of the agreement between the parties under which appointment of arbitrator is sought are as under :-
30 (2) : The contractor may within 30 days of receipt by him of any order passed by the Superintending Engineer of the circle as aforesaid appeal against it to the Chief Engineer concerned with the contract, work or project provided that.
a) The accepted value of the contract exceed Rs. 100 lakhs (Rupees hundred lakhs only.)
b) Amount of claim is not less than Rs. 1.00 Lakh (Rupees one lakh only.)
30 (3) : If the contractor is not satisfied with the order passed by the Chief Engineer as aforesaid, the contractor may within 30 deays of receipt by him of any such order, appeal against it to the Executive Director, Godawari Marathwada Irrigation Development Corporation Aurangabad, who, if convinced that Prima-facie the contractor's claim rejected by S.E/C.E. is not frivolous and that there is some substance in the claim of the contractor as would merit a detailed examination and decision by the Executive Committee/Standing committee at Corporation level for suitable decision.
3. Mr Surwase, the learned counsel appearing for respondent Nos. (B) and (D) has relied upon judgment of this Court in B.T. Patil Construction Vs. Maharashtra Krishna Valley Development Corporation, Arbitration Application No. 117/2013 decided on 11.07.2014 in support of his contention that similar clause has been interpreted by this Court to mean that there exists no arbitration agreement between the parties. Mr Surwase has therefore prayed for rejection of the application.
4. In B.T. Patil Construction (supra), clauses 30.1, 30.2 and 30.3 of the agreement therein were as under :-
Clause – 30.2 : The contractor may within 30 days of receipt by him of any order passed by the Superintending Engineer of the Circle as aforesaid appeal against it to the Chief Engineer concerned with the contract, work or project provided that -
(a) The accepted value of the contract exceeds Rs. 10 lakhs (Rs. Ten lakhs)
(b) Amount
The main legal point established in the judgment is that the absence of specific terms like 'arbitration' or 'arbitrator' in the clauses and the provision of departmental remedies indicated the absen....
The main legal point established in the judgment is that clauses empowering an engineer to take decisions and providing for an appeal do not necessarily constitute a valid arbitration agreement.
The main legal point established in the judgment is the importance of party autonomy in arbitration, the enforceability of the entire arbitration clause, and the conditional acceptance of arbitration....
The main legal point established in the judgment is the importance of written consent for arbitration, the effect of the appointment of an arbitrator, and the availability of statutory remedies under....
Appointment of arbitrator by designation is permissible. Arbitration clauses in government contracts providing that an employee of the department will be the sole arbitrator are neither void nor unen....
The judgment establishes the requirement of a written agreement for arbitration, the interpretation of settlement of disputes clauses, and the significance of party conduct in determining the existen....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.