SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Jhk) 216

IN THE HIGH COURT OF JHARKHAND AT RANCHI
RAJESH SHANKAR, J.
The State of Jharkhand – Petitioner
Versus
M/s. B.M.S. Associates – Respondent
W.P. (C) No. 4132 of 2018, I.A. Nos. 7216 of 2021, 508 of 2022
Decided On : 18-04-2022

Advocates:
Advocate Appeared:
For the Petitioners: Sachin Kumar, Gaurav Raj.
For the Respondents: Ajit Kumar, Indrajit Sinha, Shresth Gautam.

The main legal point established in the judgment is the importance of written consent for arbitration, the effect of the appointment of an arbitrator, and the availability of statutory remedies under the Arbitration and Conciliation Act, 1996.

Headnote:

Arbitration Clause - Appointment of Arbitrator - Arbitration and Conciliation Act, 1996 - [ARBITRATION CLAUSE] - [APPOINTMENT OF ARBITRATOR] - [Section 12(5), Section 16, Section 34, Section 8, Section 11] - The court discussed the interpretation and application of Clause 23 of the agreement, the appointment of arbitrators, and the jurisdiction of the arbitral tribunal under the Arbitration and Conciliation Act, 1996. The court emphasized the importance of written consent for arbitration, the effect of the appointment of an arbitrator, and the availability of statutory remedies under the Act.

Fact of the Case:

The respondent filed a suit seeking a decree against the petitioners. The petitioners sought arbitration under Clause 23 of the agreement. The appointment of arbitrators and subsequent challenges were made, leading to the appointment of Vijay Kumar Srivastava as an arbitrator. The petitioners filed a writ petition to quash the appointment.

Finding of the Court:

The court found that the appointment of the arbitrator was valid and dismissed the writ petition. The court emphasized the importance of written consent for arbitration, the effect of the appointment of an arbitrator, and the availability of statutory remedies under the Act.

Issues: The issues included the interpretation of the arbitration clause, challenges to the appointment of arbitrators, and the jurisdiction of the arbitral tribunal under the Arbitration and Conciliation Act, 1996.

Ratio Decidendi: The court held that the appointment of the arbitrator was valid, and the petitioners had the statutory remedy to challenge the award under Section 34 of the Act, 1996.

Final Decision: The writ petition was dismissed, and the petitioners were given the liberty to challenge the award under Section 34 of the Act, 1996.

ORDER :

1. The present writ petition has been preferred for quashing the order dated 15.02.2019 passed by the Civil Judge (Senior Division-II), Seraikella in Money Suit No. 07 of 2010(S), whereby the learned court below has appointed Vijay Kumar Srivastava, retired In-charge Chief Engineer, Rural Works Department, Government of Jharkhand as an arbitrator by recalling the earlier order dated 20.01.2018 whereby Late Anil Kumar, retired Chief Engineer, Government of Jharkhand was appointed as sole Arbitrator.

2. The factual background of the case, as stated in the writ petition, is that the respondent filed a suit being Money Suit No. 07 of 2010 in the Court of Sub-Judge, Seraikella against the petitioners seeking a decree of Rs. 56,17,093/- as detailed in schedule A, B and C of the plaint and also for cost of the suit. The petitioners filed an application before the said Court on 12.10.2012 through Additional Government Pleader (AGP) for referring the matter to an arbitrator under Clause 23 of the conditions of contract of the agreement, whereupon the court below vide order dated 22.04.2015 appointed Superintending Engineer, Subarnrekha Canal Circle, Jamshedpur (petitioner no. 3/defendant no. 3) as an arbitrator. The respondent filed a petition on 24.11.2017 under Section 151 CPC for modification of the order dated 22.04.2015, stating that after insertion of a new provision i.e. Section 12(5) by way of amendment in the Arbitration and Conciliation Act, 1996 (hereinafter to be referred as ‘the Act 1996’) which had come into force with effect from 23.10.2015, the Superintending Engineer, Subarnrekha Project could not have acted as an arbitrator. Subsequently, the petitioners filed rejoinder to the petition filed by the respondent on 12.01.2018 through the Government Pleader (GP), praying, inter-alia, to recall the order dated 22.04.2015 and to appoint any other person as neutral arbitrator for which the petitioner had no objection. Thereafter, the petitioners and the respondent filed a joint petition before the court below providing name of an arbitrator to decide the dispute, whereupon the court below vide order dated 20.01.2018 appointed one Anil Kumar, retired Chief Engineer, Government of Jharkhand as an arbitrator. In the meantime, the petitioners filed the present writ petition on 16.08.2018 with a prayer to quash the order dated 20.01.2018 passed by the Civil Judge (Senior Division-II), Seraikella. The petitioners also filed an application under Section 16 of the Act, 1996 before the Arbitrator, raising objection to his jurisdiction, which was rejected vide order dated 10.08.2018. The said arbitrator thereafter died on 11.10.2018. The respondent then filed an application under section 42 of the Act, 1996 for appointment of a new arbitrator. The said application was allowed by the court below vide order dated 15.02.2019, appointing one Vijay Kumar Srivastav, retired In-charge Chief Engineer, Rural Works Department, Government of Jharkhand as new arbitrator. Thereafter, the petitioners filed amended writ petition praying, inter alia, to quash of the order dated 15.02.2019.

3. Mr. Sachin Kumar, learned AAG-II, appearing on behalf of the petitioners submits that on conjoint reading of Clause 20 (engineer’s decision) of the General Conditions of Contract (GCC), as mentioned in the tender document relating to residual earth work from k.m. 9.0236 to k.m. 9.144 of Subarnrekha Left Main Canal and Clause 23 of the Conditions of Contract as mentioned in Agreement no. 1 F2 of 1999-2000 relating to the aforesaid work, it would appear that the Superintending Engineer has been vested with certain powers as an ‘in-house procedure’ to resolve the dispute relating to matters of technical consideration in course of execution of the contract. Clause 20 of GCC further makes it clear that the Superintending Engineer’s final authority does not include decisions regarding sum due to or from the contractor or for extension of time. It is submitted tha

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon telegram-icon
      whatsapp-icon Back to top