SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(Bom) 198

IN THE HIGH COURT OF JUDICATURE AT BOMBAY BENCH AT AURANGABAD
VIBHA KANKANWADI, S.G. CHAPALGAONKAR, JJ.
M/s. Ambarwadikar and Company Through its Partner Mr. Suryakant V. Ambarwadikar – Appellant
Versus
The State of Maharashtra Through Secretary – Respondent
Commercial Appeal No.1 of 2023, Civil Application No.13953 of 2023, Civil Application No.13954 of 2023, Civil Application No.13955 of 2023, Civil Application No.14280 of 2023, Civil Application No.14803 of 2023, Civil Application No.677 of 2024
Decided on : 08-02-2024

Advocates:
Advocate Appeared:
For the Appellant :Mr. R.F. Totala, Advocate h/f Mr. Ganesh Yadav and Swapnil Lohiya, Mr. K.T. Taur and Mr. V.A. Bagal Patil, Mr. S.S. Nade, Advocate
For the Respondent:Mr. Mr. N.S. Tekale, Mr. S.V. Adwant, Advocate h/f Mr. A.A. Yadkikar and Mr. Akshay Kulkarni, Mr. S.V. Natu, Advocate

The plaintiff must establish a prima facie case and show irreparable loss to obtain an injunction. The court will consider the balance of convenience and the nature of the suit in reaching its decision.

Headnote:

Prima Facie Case - Infrastructure Project - Section 41 of the Specific Relief Act, 1908 - Summary

Fact of the Case:

The plaintiff, a registered Partnership Firm engaged in infrastructure business, filed a suit against the defendants, alleging that they had not provided all the land required for a construction project, leading to a slow progress. The defendants imposed penalties and eventually terminated the contract, leading to the plaintiff seeking various reliefs through applications for injunction and stay.

Finding of the Court:

The court found that the plaintiff failed to prove a prima facie case, would not suffer irreparable loss, and that the balance of convenience lay in favor of the defendants. The court rejected all the applications for injunction and stay, and dismissed the appeal.

Issues: Prima facie case, irreparable loss, balance of convenience, breach of contract, termination of contract, and sub-letting of the project work.

Ratio Decidendi: The plaintiff's failure to prove a prima facie case, the termination of the contract, and the sub-letting of the project work were key factors in the court's decision. The court also considered the balance of convenience and the commercial nature of the suit.

Final Decision: The Commercial Appeal was dismissed, and all civil applications for injunction/stay were also dismissed. The applications for intervention were rejected.

JUDGMENT :

VIBHA KANAKANWADI, J.

1. Present appeal has been filed by original plaintiff to challenge common order below Exhs.5, 6 and 7 dated 01.11.2023 by Commercial Court/District Judge-2, Aurangabad in Commercial Suit No.1/2023, thereby rejecting all the applications. (Hereinafter parties are referred as they were before the trial Court, for the sake of convenience.)

2. The original plaintiff is a registered Partnership Firm engaged in business of infrastructure. The plaintiff has executed various Government projects. Defendant No.2 had floated a tender in 2010 for the work i.e. construction of Earthwork Lining and Structures of Canal No.1 and Distribution System of Brahmagavan Lift Irrigation Scheme Part-II, Tq. Paithan, Dist. Aurangabad for estimated costs of Rs.4,494.86 lakhs. Plaintiff participated in the tender process and its bid was accepted. The plaintiff had deposited an amount of Rs.30,00,000/- and also given bank guarantee of Rs.82,40,000/- of Janata Sahakari Bank Limited in pursuant to the tender contract. It is the contention of the plaintiff that it was the duty of the defendants to see that all the land is made available to the plaintiff for carrying out the work. Upon the measurement of the work done and its verification the defendant authorities released part payment of Rs.18.32 Crores to the plaintiff. Defendant No.2 had issued letter dated 31.10.2017 stating that the progress of the work is slow and levied fine/penalty on the plaintiff @ Rs.25,000/- per day till further orders. There was reference of the said penalty in letter 15.02.2020 issued by defendant No.2 and allegation that the plaintiff had sub-let the project work and informed that a meeting is scheduled on 18.02.2020 and asked it to remain present. The plaintiff had written a letter on 18.06.2019 that about 11 farmers are obstructing the progress of the work on the ground that their lands have not been acquired. According to the plaintiff, the possession of part of the land is not given by defendant No.2 to it and, therefore, the progress could not be made. Time and again, there was communication in respect of removal of the obstruction, however, there was no positive response. Approximately, 90% work is complete. Allegations have been levelled against the Engineers to misguide the higher authorities. Then it is stated that the plaintiff was shocked to see letter dated 15.05.2020 issued by defendant No.6 to defendant No.3 that the remaining work has been got completed through another contractor Mr. A.M. Ambhore from Jalna. Amount of Rs.3,25,14,000/- was demanded for making necessary payments. Plaintiff raised protest by letter dated 18.05.2020 stating that no such work has been done by the said contractor and, therefore, no bill is required to be raised. Legal notice was also issued by the plaintiff on 23.05.2020 and reminder on 12.06.2020. Plaintiff had then requested to extend the time for completion up to 31.07.2022. The Superintendent Engineer and Executive Engineer by giving reference to the plaintiff’s letter opined that it is appropriate to get the work done from the plaintiff. Action of imposing penalty should be reviewed, was the stand taken by them. By letter dated 14.08.2020 the Chief Engineer accepted that proposal in the name of other contractor has not been sanctioned. It is then stated that there were various communications between the plaintiff and the defendants and the defendant (Superintending Engineer) by letter dated 03.12.2020 asked the plaintiff to submit documents and papers in relation to sub-letting contract. In the meantime, letter for extension was submitted. Plaintiff undertook that he would complete the work within two years. Plaintiff had then issued letter to defendant No.5 on 22.04.2021 and submitted copy of registered deed of cancellation executed between him and Sahas Engineers and Contractors Private Limited. Plaintiff says that the defendants are unnecessarily harassing with mala fide intention. He had also app

              Click Here to Read the rest of this document
              1
              2
              3
              4
              5
              6
              7
              8
              9
              10
              11
              Judicial Analysis

              AI

              SupremeToday Portrait Ad
              supreme today icon
              logo-black

              An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

              Please visit our Training & Support
              Center or Contact Us for assistance

              qr

              Scan Me!

              India’s Legal research and Law Firm App, Download now!

              For Daily Legal Updates, Join us on :

              whatsapp-icon Back to top