SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Sanjeev Sachdeva, Rajnish Bhatnagar, JJ.
Ram Kripal Singh Constructions Pvt. Ltd. - Appellant
Versus
Indian Oil Corporation Ltd. - Respondent
FAO(OS) (COMM) 295 of 2022 & CM Appl. 45618 of 2022, CM Appl. 45619 of 2022, CM Appl. 45620 of 2022 & CM Appl. 49377 of 2022
Decided On : 15-12-2022




Injunctions cannot be granted in cases involving infrastructure project contracts under Section 20A of the Specific Relief Act; damages are the appropriate remedy for wrongful termination in terminable contracts.

Headnote:(A) Specific Relief Act, 1963 - Sections 20 and 20A - Appellant sought injunction against termination of contract and declaration of wrongful termination - Court dismissed the application for injunction; held that the contract is terminable and substantive relief lies in damages for wrongful termination - The refinery project qualifies as an infrastructure project under Section 20A, prohibiting injunctions if it impedes progress. (Paras 9, 15, 19)

(B) Contract Law - For contracts deemed terminable, specific performance and injunctions are typically not granted; damages constitute the appropriate remedy for wrongful termination. (Paras 15, 19)

Facts of the case:
The appellant, contracted for a segment of an infrastructure project with the respondent, appealed the dismissal of an application for injunction against termination of the contract, claiming delays were not attributable to their performance.

Findings of Court:
The Appellant's claim does not demonstrate grounds for injunctive relief as the segment had already been awarded to a third party, satisfying the specific provisions under the Act.

Issues: Whether the termination of the contract segment was lawful, and whether the appellant was entitled to an injunction against further actions by the respondent.

Ratio Decidendi: The court determined that the infrastructure project classification restricts injunctive relief under Section 20A; remedy for wrongful termination lies in compensation rather than specific performance.

Result: Appeal dismissed.

Table of Content
1. dispute regarding contract termination and performance delays. (Para 1 , 2 , 3 , 4)
2. appellant argues wrongful termination; no notice for breach. (Para 5 , 8 , 11)
3. court examines the appropriateness of granting injunctions. (Para 6 , 7 , 9 , 10)
4. court clarifies when specific performance and injunctions can be granted. (Para 12 , 13 , 16 , 17 , 18 , 20)
5. finding on appeal and review of injunction decision. (Para 19 , 22)
6. court upholds single judge's dismissal of injunction application. (Para 21 , 23 , 24)
7. conclusion and final order of dismissal. (Para 25 , 26)

JUDGMENT

Sanjeev Sachdeva, J. (Oral)--Appellant impugns Order dated 13.10.2022 whereby the application of the respondent under Order 39 Rules 1 and 2 CPC has been dismissed holding that the application for injunction does not survive, and directing that it is open to the Appellant to take appropriate remedies impugning the Fax of Acceptance dated 07.10.2022 and for claiming damages and other reliefs as may be permissible in law.

2. Appellant had filed the subject suit seeking declaration that invocation by the Respondent of Clause 4.7.4.0 of General Conditions of Contract was illegal and void ab initio. Appellant had also sought a declaration that the contract does not require the Appellant to supply Hot Dipped Galvanised Iron Bolt or Steel section, and if it did require supplying the same, the supply would be at the existing market rate as extra works. A mandatory injunction is also sought against the Respondent to provide the maps/plans/drawings for the underground pipes/cables/utilities at the work site so that the Appellant can carry out the work in question at a fast pace.

3. Pursuant to Notice Inviting E-Tender for piling and civil and structural works for capacity expansion project at the Respondent's Oil Refinery at Barauni, Appellant was awarded the contract for Engineering Procurement Construction and Material-22 (`EPCM-22') which comprises of 25 segments. The dispute is with regard to one of the 25 segments.

4. It is an admitted position that for the expansion project, one of the segments i.e., EPCM-22 was awarded to the Appellant, and there are other similar segments awarded to third parties. The dispute pertains to the termination of the contract with regard to one of the 25 segments which Respondent has terminated on the ground of delay in performance by the Appellant, and awarded the same to a third party.

5. Learned counsel for the Appellant contends that termination has been done on the ground of delay in performance. He submits that there is substantial material on record to show that the Appellant was not at fault in the execution of the contract and the site on which the work was to be executed was admittedly not made available by the Respondent as the same was encroached upon by material of third party contractors of the Respondent. He submits that since the termination is wrongful, and the relevant clause contains a negative covenant, Respondent could not have terminated the contract and an injunction was liable to be granted restraining the Respondent from terminating the contract and allotting it to a third party with regard to one of the segments.

6. On a query from the learned counsel for the Appellant, the categorical answer is that 25 segments are not so integral that one of them cannot be separated from the others. The admitted position is that one of the segments could have been independently allotted to a third party for execution. The only question that arises for consideration is as to whether the termination of one of the 25 segments is rightful or wrongful.

7. We notice that in the prayer clause of the Suit, the Appellant has sought a simplicitor declaration that the termination is wrongful. There is no consequential relief prayed for injunction restraining the Respondent from allotting the terminated segment to a third party or permitting the Appellant to execute the work.

8. Learned counsel for

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top