IN THE HIGH COURT OF DELHI
Sanjeev Sachdeva, Rajnish Bhatnagar, JJ.
Ram Kripal Singh Constructions Pvt. Ltd. - Appellant
Versus
Indian Oil Corporation Ltd. - Respondent
FAO(OS) (COMM) 295 of 2022 & CM Appl. 45618 of 2022, CM Appl. 45619 of 2022, CM Appl. 45620 of 2022 & CM Appl. 49377 of 2022
Decided On : 15-12-2022
| Table of Content |
|---|
| 1. dispute regarding contract termination and performance delays. (Para 1 , 2 , 3 , 4) |
| 2. appellant argues wrongful termination; no notice for breach. (Para 5 , 8 , 11) |
| 3. court examines the appropriateness of granting injunctions. (Para 6 , 7 , 9 , 10) |
| 4. court clarifies when specific performance and injunctions can be granted. (Para 12 , 13 , 16 , 17 , 18 , 20) |
| 5. finding on appeal and review of injunction decision. (Para 19 , 22) |
| 6. court upholds single judge's dismissal of injunction application. (Para 21 , 23 , 24) |
| 7. conclusion and final order of dismissal. (Para 25 , 26) |
JUDGMENT
Sanjeev Sachdeva, J. (Oral)--Appellant impugns Order dated 13.10.2022 whereby the application of the respondent under Order 39 Rules 1 and 2 CPC has been dismissed holding that the application for injunction does not survive, and directing that it is open to the Appellant to take appropriate remedies impugning the Fax of Acceptance dated 07.10.2022 and for claiming damages and other reliefs as may be permissible in law.
2. Appellant had filed the subject suit seeking declaration that invocation by the Respondent of Clause 4.7.4.0 of General Conditions of Contract was illegal and void ab initio. Appellant had also sought a declaration that the contract does not require the Appellant to supply Hot Dipped Galvanised Iron Bolt or Steel section, and if it did require supplying the same, the supply would be at the existing market rate as extra works. A mandatory injunction is also sought against the Respondent to provide the maps/plans/drawings for the underground pipes/cables/utilities at the work site so that the Appellant can carry out the work in question at a fast pace.
3. Pursuant to Notice Inviting E-Tender for piling and civil and structural works for capacity expansion project at the Respondent's Oil Refinery at Barauni, Appellant was awarded the contract for Engineering Procurement Construction and Material-22 (`EPCM-22') which comprises of 25 segments. The dispute is with regard to one of the 25 segments.
4. It is an admitted position that for the expansion project, one of the segments i.e., EPCM-22 was awarded to the Appellant, and there are other similar segments awarded to third parties. The dispute pertains to the termination of the contract with regard to one of the 25 segments which Respondent has terminated on the ground of delay in performance by the Appellant, and awarded the same to a third party.
5. Learned counsel for the Appellant contends that termination has been done on the ground of delay in performance. He submits that there is substantial material on record to show that the Appellant was not at fault in the execution of the contract and the site on which the work was to be executed was admittedly not made available by the Respondent as the same was encroached upon by material of third party contractors of the Respondent. He submits that since the termination is wrongful, and the relevant clause contains a negative covenant, Respondent could not have terminated the contract and an injunction was liable to be granted restraining the Respondent from terminating the contract and allotting it to a third party with regard to one of the segments.
6. On a query from the learned counsel for the Appellant, the categorical answer is that 25 segments are not so integral that one of them cannot be separated from the others. The admitted position is that one of the segments could have been independently allotted to a third party for execution. The only question that arises for consideration is as to whether the termination of one of the 25 segments is rightful or wrongful.
7. We notice that in the prayer clause of the Suit, the Appellant has sought a simplicitor declaration that the termination is wrongful. There is no consequential relief prayed for injunction restraining the Respondent from allotting the terminated segment to a third party or permitting the Appellant to execute the work.
8. Learned counsel for
Injunctions cannot be granted in cases involving infrastructure project contracts under Section 20A of the Specific Relief Act; damages are the appropriate remedy for wrongful termination in terminab....
A contract that is determinable in nature cannot be specifically enforced, and no injunction against termination and enforcement of the contract can be issued.
The main legal point established in the judgment is that in the case of a determinable contract, no injunction against termination and enforcement of the contract can be issued.
The court emphasized the importance of adhering to contractual procedures and the validity of penalties for non-performance, reinforcing the authority's right to terminate contracts under specified c....
The court affirmed that the Tribunal's rejection of the appellant's request for interim measures was valid due to established insufficient funding and non-compliance, affirming limited grounds for in....
The main legal point established in the judgment is that the conclusion of a contract can occur upon the award of work, and non-compliance with tender and contract terms can justify contract terminat....
Injunctions cannot be granted to prevent breaches of determinable contracts under the Specific Relief Act, and the trial court must adhere to established principles when considering applications for ....
A contract that is inherently terminable does not prevent the enforcement of specific performance claims if the termination is contested as being unjust or improper.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.