IN THE HIGH COURT OF JUDICATURE AT BOMBAY
DEVENDRA KUMAR UPADHYAYA, C.J., AMIT BORKAR, J.
M/s. Rajaram Construction – Petitioner
Versus
State of Maharashtra – Respondent
Writ Petition No. 10529 of 2024
Decided On : 19-09-2024
Tender - Disqualification - Clause 12, Clause 15-A, Clause 15-B - The court emphasized the importance of compliance with tender conditions, particularly regarding bid capacity and technical manpower certificates, and upheld the decision of the Technical Evaluation Committee as reasonable and not arbitrary.
Fact of the Case:
The petitioner challenged the rejection of their bid for a construction tender, claiming compliance with the requirements despite the rejection based on late submission of necessary documents.
Finding of the Court:
The court found that the petitioner failed to meet the mandatory tender requirements and that the Technical Evaluation Committee's decision was not arbitrary or irrational.
Issues: Whether the petitioner was wrongfully disqualified from the tender process due to non-compliance with submission deadlines for required documents.
Ratio Decidendi: The court held that the determination of compliance with tender conditions lies with the authority inviting bids, and judicial review is limited to cases of malice or irrationality.
Result: The writ petition stands dismissed.
JUDGMENT :
AMIT BORKAR, J.
1. The present petition challenges the legality and propriety of the communication dated 14th March 2024, regarding the technical bid summary, which demanded details of bid capacity and technical manpower, as well as the communication dated 18th June 2024, rejecting the petitioner’s bid and declaring the petitioner disqualified.
2. The petitioner, a proprietorship firm engaged in civil construction works for the past 15 years, has brought this petition. Respondents Nos. 2 and 3 issued e-Tender Notice No. 40 of 2001 (2023-2024), inviting bids for two works, which were published online from 15th February 2024 to 29th February 2024. The details of Notice No. 40 of 2001 (2023- 2024) were made available on the respondents' website for the construction of a cement concrete road from Lekha Nagar to Chhatrapati Shivaji Chowk in P. No. 24, New Nashik Division.
3. The estimated cost of the work was Rs. 5,47,68,859/- with a completion period of 18 calendar months, including monsoons. As per the tender conditions, the date for opening the tender was fixed for 1st March 2024 at 3:00 p.m. Clause 12 of the tender outlined the necessary work experience qualifications as follows:
12.1. The tenderer must have eligibility in term of work experience as follows:
(A) Experience of having successfully completed similar works during last five years ending last day of month previous to the one in which applications are invited should be either of the following:
1. Three similar completed works costing not less than the amount equal to 40% of estimated cost each
2. Two similar completed works costing not less than the amount equal to 50% of estimated cost each
3. One similar completed works costing not less than the amount equal to 80% of estimated cost each
4. “Similar works means construction of concrete road and & allied work.”
4. Clause 15-A required the average turnover of the parent company over the last three years to be 30% of the estimated cost, as certified by a Chartered Accountant. Clause 15-B provided a formula for calculating bid capacity as follows:
(B) Bid Capacity:
Bidder who meet the minimum qualification criteria will be qualified only if their available bid capacity is more than the total bid value. The available bid capacity will be calculated as under.
Assessed available bid capacity = (A x N x 1.5) - B
Where:
A = Maximum Value of Annual Turnover executed in any one year during the last Five Years (updated to 2022-23 price level)
N + Number of Years prescribed for completion of the work for which bids are invited for 12(Twelve) Months for calculation of Bid Capacity) i.e. For 12 months N+1, for 6 months N + 0.5
B = Value of existing commitments and on-going works to be completed during the next 12 (Twelve) months, In support of this information should be submitted in Format No. III
Note: Since all the data is pertaining to the contractors own performance, the contractors are requested to provide its bidding capacity for this work by furnishing the calculations and supporting documents duly certified by Chartered Accountant to prove its contents along with the application for issue of tender form.”
5. The petitioner contends that the Government Resolution dated 7th December 2023 applies to the tender in question. On 14th March 2024, respondent No. 3 informed the petitioner of failure to submit bid capacity and manpower details by 29th February 2024 and granted five days for compliance. The petitioner asserts that the bid capacity certificate, certified by a Chartered Accountant, and the technical manpower certificate had already been uploaded prior to 29th December 2024. The petitioner argues that these certificates can only be issued prospectively, and it is impossible to obtain them with backdated signatures. Therefore
M/s Michigan Rubber India Limited vs. State of Karnataka & Ors. (2012) 8 SCC 216
N.G. Projects Ltd. v. Vinod Kumar Jain
Judicial review in tender matters is limited; courts should not interfere unless there is clear evidence of arbitrariness or mala fide conduct.
The authority to cancel a tender prevails under administrative discretion, based on the rationale of maintaining integrity, fairness, and transparency in public procurement processes.
Judicial review of tender processes is limited; courts should respect the authority's discretion unless there is clear evidence of arbitrariness or irrationality.
The court upheld the authority's discretion in setting eligibility criteria for tenders, emphasizing that judicial review is limited to cases of arbitrariness or unreasonableness.
Public authorities must ensure fairness and non-arbitrariness in tender processes, adhering to established eligibility criteria.
The court emphasized the need for restraint and deference to the tendering authority's interpretation of tender documents, especially in technical matters, and highlighted the importance of public in....
The court upheld the authority's discretion in evaluating tender bids, emphasizing the need for compliance with mandatory conditions and the absence of arbitrariness in disqualification decisions.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.