M. S. SONAK, VALMIKI SA MENEZES
Reliance Jio Infratel Pvt. Ltd. – Appellant
Versus
State of Goa – Respondent
ORDER :
Heard Mr. Sardessai, learned Senior Advocate for the Applicant;
Mr. D. Pangam, learned Advocate General for the first and second Respondents; Mr. Faldessai, learned Deputy Solicitor General for the fourth Respondent; and Mr. Nigel Da Costa Frias, learned Counsel for the Respondent nos. 5 to 24.
2. This application seeks vacation/variation of Orders dated 17.12.2021 and 16.02.2022, by which this Court had granted interim relief restraining the Applicant [original Respondent no.3 in Writ Petition no.2250 of 2021 (F)] from operating the telecom tower installed in the property surveyed under no. 125/5 of Colva, Salcete, Goa, pending hearing and final disposal of the Petition.
3. From the perusal of our Orders dated 18.11.2021, 16.12.2021, 17.12.2021 and 16.02.2022, it is apparent that the interim Orders were made because this Court found that the Applicant had prima facie failed to comply with the conditions in clauses 8 and 9 of the NOC dated 01.06.2021 issued by the State of Goa. Compliance with these conditions was crucial to operating the tower.
4. Clauses 8 and 9 of the NOC dated 01.06.2021 read as follows :
A) Copy
Compliance with NOC conditions is essential for the lawful operation of telecom installations, and interim restraints can be lifted upon establishing such compliance.
Compliance with guidelines and obtaining necessary permissions for the installation of mobile towers is crucial.
Adherence to the principles of natural justice is essential for orders passed by public authorities.
Section 10(d) there are two mandatory requirements; (1) Telegraph Authority shall do as little damage as possible; and (2) to pay full compensation to all persons interested for the damage sustained ....
Statutory authorities can erect high-tension electricity towers on private land without prior consent, provided they ensure minimal damage and compensate affected parties, in adherence to public inte....
The court affirmed the legality of the procedures for erecting transmission towers and highlighted public interest in electricity provision over private landowner objections.
When the element of expertise is involved and the same is undertaken by the statutory body as per law, the power of judicial review will have to be entertained with extreme caution. Judicial Review -....
The cancellation of a No Objection Certificate for a mobile tower without due process, specifically without a hearing, contravenes principles of natural justice and lacks legal basis, as complaints a....
CRZ authorities must verify prior refusals, FAR compliance, site conditions via inspection before discharging proceedings on alleged NDZ violations, considering HTL shifts; inadequate orders warrant ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.