IN THE HIGH COURT OF JUDICATURE AT BOMBAY
A.S. GADKARI, KAMAL KHATA, JJ.
Kamal Sevakram Jadhawani and Anr. – Petitioners
Versus
State of Maharashtra (to be served through Govt. Pleader, High Court, Bombay) and Ors. – Respondents
WRIT PETITION NO.747 OF 2024 WITH INTERIM APPLICATION (L) NO.20688 OF 2024 WITH INTERIM APPLICATION (L) NO.17624 OF 2024 WITH WRIT PETITION NO.3865 OF 2024 WITH CONTEMPT PETITION NO. 105 OF 2024 WITH CONTEMPT PETITION NO. 105 OF 2024 WITH INTERIM APPLICATION (L) NO.20746 OF 2024
Decided On : 21-01- 2025
Key Points: - The Petitioners, though removed as Developers under Section 13(2) Slum Act, retained locus to challenge the demolition and actions of the new Developer and SRA. (!) (!) (!) - The Court held the SRA and BMC actions mala fide and unlawful, including improper delegation of occupancy verification to the Developer and reliance on a private structural report; ruled that Section 353B notice was unlawful as the building was not 30 years old and outside SRA scheme context. (!) (!) (!) (!) (!) - The Court directed Respondent No.3 to earmark 856.60 sq mtrs in the new building for the Petitioners, with the Petitioners entitled to transit accommodation or compensation in the interim; Chamankar’s entitlement to area or market-rate compensation to be decided by SRA within six months. (!) (!) (!) (!)
JUDGMENT :
(Kamal Khata, J) :
1) Before us there are two interconnected Writ Petitions.
2) In Writ Petition No.747 of 2024, Petitioners-Jadhawani’s seek the following substantive reliefs:
b) this Hon’ble Court be pleased to stay the I.O.A. dated 10/02/2020 at Exhibit ‘M’ issued for Rehab Building No.1 for construction of new rehab Building by Demolition of the existing Building No.1 on land bearing CTS Nos. 825/1(pt) & 825/2 (pt) of Village Ambivali, Andheri (West), Mumbai;
c) this Hon’ble Court be pleased to direct the Respondent no.2 to provide the Petitioners sale shop on Ground to Second floor in the sale building to be approved by the Respondent no.2 on land bearing CTS Nos. 825/1 (pt) & 825/2 (pt) of Village Ambivali, Andheri (West), Mumbai in case of the demolition of the Petitioners shops in the Composite Building no.1;”
3) In Writ Petition No.3865 of 2024, Petitioners-Chamankar’s seek the following substantive reliefs:
(b) that this Hon'ble Court be pleased to cancel and set aside the said LOI dated 27th July 2023, IOA dated 25th August 2023, permission to allow demolition by letter dated 17th May 2024 and private report dated 1/4/2024 of Sardar Patel College of Engineering;”
4) In Writ Petition No.3865 of 2024 under Article 226 of the Constitution of India, the Petitioners seeks a direction to the Respondents to stop the demolition of the composite building, which has been declared as dilapidated and classified as “C-1” based on a report allegedly procured by Respondent No. 3 in collusion with Respondent No 2. The Petitioners further challenge the legality and validity of Letters of Intent (LOI) dated 27th July 2023 and Intimation of Approval (IOA) dated 25th August 2023, both issued in favour of Respondent No.3. The Petition highlights a breach of statutory duties and obligations by Respondent No. 2-SRA, who at the behest of Respondent No.3-Developer secured demolition permissions based on a private institute’s report, without adhering to the due process of law.
5) Mr. Aspi Chinoy, learned senior counsel representing the Respondent No.3 – Developer, raises a preliminary objection regarding the Petitioner’s locus standi to challenge the building’s demolition. He contends that the Petitioner-Chamankars’ is none other than the former Developer who was r
The court affirmed that removed Developers retain locus to challenge demolition actions, emphasizing the need for transparency and legality in the SRA and BMC's conduct.
The court ruled that the actions of the SRA and BMC in demolishing the building were unlawful and mala fide, affirming the Petitioners' rights to the earmarked free sale area despite their removal as....
Free sale rights under slum rehabilitation schemes are contingent upon fulfilling obligations; failure to do so results in loss of rights, and actions by authorities must adhere to legal standards.
Public landowner has preferential redevelopment rights on reserved slum land; conditional NOC cancellation valid for developer's failure to provide compliant plans for public amenities, subordinating....
The court ruled that disputed questions of fact regarding land area and project delays are not suitable for Writ jurisdiction, emphasizing the need for timely completion of slum rehabilitation projec....
The CEO/SRA has the authority to terminate a Developer under Section 13(2) of the Slum Act for delays and non-performance in the Slum Rehabilitation Scheme, emphasizing timely completion for public b....
Unauthorized construction without proper permissions violates statutory laws; authorities must enforce demolition orders while compensating affected purchasers.
The Municipal Corporation's failure to comply with Court orders regarding illegal structures constitutes contempt, necessitating immediate action to uphold the rule of law.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.