SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
DEVENDRA KUMAR UPADHYAYA, CJ., AMIT BORKAR, J.
M/s. K.K. Vidyut - Petitioner
Versus
Union of India (through the Secretary of Railways) and Ors. - Respondents
Writ Petition (L) No.35600 Of 2024
Decided On : 19-12-2024

Advocates Appeared:
For the Petitioner: Mr. Subhash Jha a/w Siddharth Jha, Navneetha Krishnan, Apeksha Sharma, Sumeet Upadhyay, Ashish Saxena i/by Law Global.
For the Respondents: Mr. N.R. Bubna.

The submission of forged bank guarantees constitutes a serious breach of contract, justifying termination under the General Conditions of Contract, as fraud vitiates all transactions.

Headnote:(A) Constitution of India - Article 226 - General Conditions of Contract (GCC) - Termination of contract - Petitioner challenged termination notice alleging submission of forged bank guarantees - Respondents justified termination under Clause 62 of GCC due to fraud - Petitioner failed to provide satisfactory explanation or evidence against allegations - Court found termination valid as fraud vitiates all transactions. (Paras 12, 34, 57)

(B) Natural Justice - Principles of natural justice not violated as petitioner was given multiple opportunities to respond - Failure to provide substantive replies negated claims of procedural unfairness. (Paras 42, 44)

(C) Contractual Obligations - Submission of forged documents constitutes irremediable breach - Respondents acted within rights to terminate contract based on established fraud. (Paras 36, 57)

Facts of the case:
The petitioner was awarded a contract for railway infrastructure development but was terminated for allegedly submitting forged bank guarantees. Despite multiple show-cause notices, the petitioner failed to substantiate its claims or refute the allegations.

Findings of Court:
The court upheld the termination of the contract, emphasizing that fraud nullifies any contractual obligations and that the petitioner had not provided any credible defense against the allegations.

Issues: The main issues were the validity of the termination based on alleged forgery of bank guarantees and whether the principles of natural justice were adhered to during the termination process.

Ratio Decidendi: The court ruled that the submission of forged bank guarantees constituted a serious breach justifying termination under Clause 62 of the GCC, and that the principles of natural justice were not violated as the petitioner was afforded ample opportunity to respond.

Result: Writ petition dismissed.

JUDGMENT :

(Amit Borkar, J.)

1. The petitioner, invoking the extraordinary writ jurisdiction of this Court under Article 226 of the Constitution of India, challenges the notice of termination dated 30 October 2024, issued by the respondents. The termination pertains to the contract awarded to the petitioner in furtherance of a tender process concerning the provision of Goods Shed facilities, construction of buildings, and the development of critical railway infrastructure.

2. The relevant facts and circumstances leading to the filing of this writ petition are summarized below to provide context to the dispute.

    On 1 June 2023, the respondents issued e-Tender Notice No. CAOC-12-2023, inviting bids for a comprehensive railway infrastructure development project. The project encompassed the provision of Goods Shed facilities, construction of a track machine rest house, construction of an E1 building, platform surfacing work, supply of ballast, completion of balance earthwork in ANG, VLD, and RRI yards, and the construction of four major bridges at the Manmad entry arrangement in connection with the Daund-Manmad Doubling Project.

3. The petitioner, being one of the bidders, was awarded the contract after meeting the eligibility criteria and completing the tender formalities. In compliance with the contractual requirements, the petitioner furnished a performance bank guarantee on 9 November 2023 for an amount of Rs.7,66,63,700/- issued by IDBI Bank Ltd. This guarantee was verified by the respondents through their communication dated 21 November 2023. Subsequently, the petitioner submitted additional bank guarantees issued by Yes Bank Ltd., details of which are as follows: Rs.8,43,30,100/- dated 16 April 2024; Rs.15,33,230/- dated 17 May 2024; and Rs. 8,58,63,330/- dated 17 May 2024.

4. All these guarantees were subjected to the respondents’ standard verification procedures and were confirmed to be genuine at that stage. Upon completion of these formalities, the petitioner commenced the execution of the work, deploying resources, machinery, and manpower at the designated project sites. According to the petitioner, the progress of the work was satisfactory and exceeded the cumulative value of all the submitted bank guarantees. The petitioner asserts that it adhered to all contractual terms and complied with the work schedules and timelines stipulated under the contract.

5. On 18 September 2024 and 20 September 2024, the respondents issued letters to IDBI Bank and Yes Bank seeking re-verification of the bank guarantees submitted by the petitioner. This was done despite the fact that these guarantees had already been verified during the initial stages of the project.

6. Subsequently, based on material received by the respondents, a show-cause notice dated 25 September 2024 was issued to the petitioner. The show-cause notice alleged that the bank guarantees submitted by the petitioner were forged and fabricated documents. It was contended that these guarantees had been fraudulently submitted by the petitioner to fulfill the performance guarantee and mobilization advance requirements under the contract. The respondents relied upon Clause 62 of the General Conditions of Contract (GCC), which mandates the submission of valid performance guarantees and authorizes the respondents to terminate the contract, forfeit the bid security, and recover other dues in case of non- compliance. The notice further warned the petitioner that the alleged forgery constituted a serious breach of trust and misrepresentation, which rendered the petitioner ineligible to continue with the project. The respondents also invoked the relevant provisions of the contract to debar the petitioner from participating in any re-tender process for the same work.

7. In response, the petitioner submitted a preliminary reply dated 27 September 2024. It was stated that due to the arrest of its director by investigation agency, the verification of the genuineness of the bank guarantees was

        Click Here to Read the rest of this document
        1
        2
        3
        4
        5
        6
        7
        8
        9
        10
        11
        SupremeToday Portrait Ad
        supreme today icon
        logo-black

        An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

        Please visit our Training & Support
        Center or Contact Us for assistance

        qr

        Scan Me!

        India’s Legal research and Law Firm App, Download now!

        For Daily Legal Updates, Join us on :

        whatsapp-icon Back to top