IN THE HIGH COURT OF CALCUTTA
SHAMPA SARKAR, J.
M/s. Krishi Ifratech Bangalore – Appellant
Versus
Union of India and others – Respondents
WPA 17053 of 2024
Decided on : 05-07-2024
Natural Justice - Termination of Contract - Clause 62, 63, 64 - The court emphasized the necessity of adhering to natural justice principles in contract termination, highlighting the lack of adequate reasoning and opportunity for the petitioner to respond before the contract was rescinded.
Fact of the Case:
The petitioner challenged the termination of a contract by the Chief Engineer, citing failure to form a Dispute Adjudication Board, lack of reasons for termination, and inability to complete work due to external factors like land acquisition issues.
Finding of the Court:
The court found that the termination was executed without considering the petitioner's explanations and violated principles of natural justice, as the authority failed to provide adequate reasons for the decision.
Issues: Whether the termination of the contract was justified and whether the principles of natural justice were violated in the process.
Ratio Decidendi: The court held that the authority must consider the contractor's explanations and provide reasons for termination, as failure to do so constitutes a violation of natural justice.
Result: The termination order was set aside, and the matter was remanded for reconsideration with an opportunity for the petitioner to be heard.
JUDGMENT :
Shampa Sarkar, J.
1. This writ petition arises out of the termination notice dated June 24, 2024 issued by the Chief Engineer/CON/HQ/GRC. The said notice reads as follows:
2. Dy. CE/C/GRC’s office 7 days’ Notice letter No. CE/C/South/GRC/DSPN-Nandigram/KInfratech dt.09.05.2024.
Dear Sir,
Forty-eight hours (48 hrs.) notice was given to you under this office letter of even NO.594, dated 04.06.2024; but you have taken no action to commence the work/show adequate progress of the work.
Since the period of 48 hours’ notice has already expired, the above contract stands rescinded in terms of Clause 62 of the Standard General Conditions of Contract and the balance work under this contract will be carried out independently without your participation. Your participation as well as participation of every member/partner in any manner as an Individual or a partnership firm/JV is herby debarred from participation in the tender for executing the balance work land your Security Deposit shall be forfeited and Performance Guarantee shall also be encashed.”
2. The petitioner is aggrieved for the following reasons:
b) The arbitration clause at Clause 63 of the Standard General Conditions of Contract could not be invoked in this case.
c) The demand for arbitration under Clause 64(1) would also not be a bar as the order is devoid of reasons and the decision to forfeit the security deposit and encash the performance guarantee was taken without hearing the petitioner.
d) The notice of termination does not indicate the reasons as to why the authority was not satisfied with the answers which were given repeatedly by the petitioner justifying its inability to complete the project or continue with the work at the pace which was expected from them.
e) Correspondence with the Deputy Chief Engineer and the letter written to the Chief Engineer would indicate that the petitioner had provided the reasons as to why the balance work could not be executed on time. Reference is made to certain admissions made by the Deputy Chief Engineer with regard to the problems relating to acquisition of land etc. The railway authority was required to hand over free and clear land, free from all encumbrances, which they failed to do.
3. The learned advocate for the railway authority submits that the notices were given to the petitioner as per the Standard General Conditions of Contract. The termination was done in accordance with such procedure. Initially 7 days’ notice was given, thereafter 48 hours’ notice was also given.
4. It is further submitted that the petitioner ought to have approached the authority with the demand for arbitration.
5. After going through the record, this court finds that apart from the letters written to the Deputy Chief Engineer with regard to the problems that the petitioner was facing in execution of the balance work etc., the petitioner had also written a letter to the Chief Engineer South-Eastern Railways authority, with necessary explanations. The authority terminated the contract without providing any reason. The decision to forfeit the security deposit and encash the performance guarantee was also taken without dealing with the petitioner’s explanation and without quantifying the loss suffered by the railways.
6. The petitioner pointed out difficulties with regard to local agitation and contended that local people did not allow the workers to enter the site. Thus, the commencement of the earth work was delayed. The next difficulty pointed out was that the tentative drawings without any clearance of the design by the appropriate authority had been received belatedly. The seven days’ notice was issued without providing a hindrance free site and approved drawings to the contractor. None of the bridges had proper approach and transportation of th
A.K. Kraipak v. Union of India [(1969) 2 SCC 262]
ABL International Ltd. v. Export Credit Guarantee Corpn. of India Ltd.
Bareilly Development Authority v. Ajai Pal Singh
Chairman, Board of Mining Examination and Chief Inspector of Mines v. Ramjee
Gorkha Security Services v. Govt. (NCT of Delhi)
Haryana Financial Corpn. v. Kailash Chandra Ahuja
M.P.Power Management Co. Ltd vs Sky Power Southeast Solar India (P) Ltd.
Maharashtra Chess Assn. v. Union of India
The court established that termination of a contract must comply with natural justice principles, requiring adequate reasoning and opportunity for the affected party to respond.
The court emphasized the importance of adhering to contractual procedures and the validity of penalties for non-performance, reinforcing the authority's right to terminate contracts under specified c....
Writ under Article 226 not maintainable for contractual termination disputes involving factual questions when arbitration clause exists, natural justice not violated, and no public law issue raised.
The main legal point established is that termination of a contract must adhere to the contractual provisions and the principle of natural justice. Additionally, the availability of alternative remedi....
The main legal point established in the judgment is the importance of abiding by the dispute resolution mechanism provided in the Agreement for resolving disputes arising from the contract. The Court....
The judgment establishes that the exercise of unfettered discretion by the Authorities, without complying with the Principles of Natural Justice, renders their decision illegal and subject to judicia....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.