IN THE HIGH COURT OF JUDICATURE AT BOMBAY
A.S. GADKARI, SHYAM C. CHANDAK, JJ
PVP Star Hotels Private Limited – Appellant
Versus
State of Maharashtra, Through the Secretary, Urban Development Department – Respondent
JUDGMENT :
SHYAM C. CHANDAK J.
1) Present Petition filed under Article 226 and 227 of the Constitution of India, seeking the following substantive reliefs :-
(i) The Respondent Nos.2 and/or 3 are bound and liable to grant extension of time limit for the period from 14.12.2012 to the period of 3 years from the date of Order, when such extension shall be granted to the Petitioner No.1 to complete the development/construction of the suit plot without levying additional lease premium and without insisting on execution/providing of Bank Guarantee of any amount;
(ii) The impugned Show Cause Notice dated 30.09.2016, Termination Notice dated 24.04.2017, Order dated 31.07.2017 i.e., condition to pay the additional lease premium, the Demand Notice/Order 02.01.2018 and the Termination Notice/Order dated 02.04.2018 issued by Respondent Nos.2 and/or 3, be quashed and set aside.
(iii) To command the Respondent Nos.2 and/or 3 to forthwith restore the possession of the suit plot with the Petitioners which the Respondent Nos.2 and/or 3 have taken back in their possession on dated 17.04.2018.
1.1) The aforesaid I.A. No.4369 of 2023 is seeking to amend the Petition to modify/change the registered address
The court emphasized that administrative discretion must be exercised fairly, considering both parties' interests, especially when external factors impede contractual obligations.
Penalty for construction delay under lease quashed due to delays from court stay, statutory approvals, additional area; writ maintainable for arbitrary state action; 6-year extension non-discriminato....
Additional premium demand for construction delay under lease held arbitrary where caused by statutory approvals, late commencement certificates, and extra built-up area without timeline; applicable s....
Lease penalty for construction delay invalid where lessor nondiscloses material site defects, supplementary deed removes time limit for additional built-up area, delays due to approvals/statutory fac....
Supplementary lease deeming additional built-up area integral with no time limit overrides original four-year completion clause for composite construction; penalty demands arbitrary, illegal; payment....
Writ jurisdiction can address arbitrary state actions in contractual disputes, emphasizing the importance of procedural fairness and adherence to contractual terms, especially regarding extensions an....
Section 31(7) of the Arbitration and Conciliation Act, 1996 which provides for 18% of interest per annum from date of award till date of payment. Worthwhile it would be to refer to Section 31(7) of A....
The principle of unjust enrichment and the doctrine of legitimate expectations were central to the court's decision, emphasizing the obligation of the Development Authority to act fairly and reasonab....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.