IN THE HIGH COURT OF JUDICATURE AT BOMBAY
A.S. GADKARI, SHYAM C. CHANDAK, JJ.
M/s. PVP Star Hotels Private Limited and Anr. – Petitioners
Versus
The State of Maharashtra, Through the Secretary, Urban Development Department and Ors. – Respondents
Writ Petition No.4856 Of 2018 With Interim Application No.4369 Of 2023 With Interim Application No.7943 Of 2023
Decided On : 13-03-2025
(A) Constitution of India - Articles 226 and 227 - Petition for extension of time limit for construction of a hotel - Petitioners sought waiver of additional lease premium and restoration of possession of the suit plot - Respondents issued notices for termination due to delay in construction - Court found that the delay was due to external factors and not solely the Petitioners' fault - Court directed restoration of possession and granted extension subject to conditions. (Paras 1, 3, 17)
(B) Administrative Discretion - The exercise of discretion by a statutory authority must not be arbitrary and should consider the interests of both parties involved - The Respondent's failure to act within a reasonable time contributed to the Petitioners' inability to complete the project. (Paras 15, 16)
Facts of the case:
The Petitioners were granted a lease for a plot to construct a hotel but faced delays due to external factors, including economic slowdown and infrastructure project delays. They sought extensions and waivers from the Respondents, who issued termination notices. (Paras 3.1, 3.3, 3.4)
Findings of Court:
The Court found that the Respondents acted arbitrarily in terminating the Agreement and that the Petitioners had made significant investments. The Court ordered the restoration of possession and granted an extension for construction. (Paras 17, 17.1)
Issues: The main issues included whether the Petitioners were entitled to an extension without additional lease premium and whether the Respondents acted arbitrarily in terminating the Agreement. (Paras 1, 4)
Ratio Decidendi: The Court held that the Respondents failed to exercise their discretion fairly and that the Petitioners' inability to complete the project was not solely their fault, warranting an extension of time. (Paras 14, 15)
Result: Petition allowed with conditions.
JUDGMENT :
SHYAM C. CHANDAK J.
1) Present Petition filed under Article 226 and 227 of the Constitution of India, seeking the following substantive reliefs :-
(i) The Respondent Nos.2 and/or 3 are bound and liable to grant extension of time limit for the period from 14.12.2012 to the period of 3 years from the date of Order, when such extension shall be granted to the Petitioner No.1 to complete the development/construction of the suit plot without levying additional lease premium and without insisting on execution/providing of Bank Guarantee of any amount;
(ii) The impugned Show Cause Notice dated 30.09.2016, Termination Notice dated 24.04.2017, Order dated 31.07.2017 i.e., condition to pay the additional lease premium, the Demand Notice/Order 02.01.2018 and the Termination Notice/Order dated 02.04.2018 issued by Respondent Nos.2 and/or 3, be quashed and set aside.
(iii) To command the Respondent Nos.2 and/or 3 to forthwith restore the possession of the suit plot with the Petitioners which the Respondent Nos.2 and/or 3 have taken back in their possession on dated 17.04.2018.
1.1) The aforesaid I.A. No.4369 of 2023 is seeking to amend the Petition to modify/change the registered address of Petitioner No.1 and to replace the said Petitioner No.2 with the Applicant No.2 therein.
1.2) The aforesaid I.A. No.7943 of 2023 is seeking to permit the Applicant therein to intervene in this Petition and I.A. No.4369 of 2023.
2) Heard Mr.Sathe, the learned Senior Counsel for the Petitioners, Smt.Bhatia, the learned AGP for Respondent No.1-State and Mr. Hegde, the learned Senior Counsel for Respondent Nos.2 & 3-CIDCO. Perused entire record.
2.1) None appeared for the Applicant in I.A. No.7943 of 2023 when taken up for hearing.
2.2) Rule. Rule made returnable forthwith and with the consult of learned counsel for the parties taken up for final hearing.
3) Facts in brief are that, in December 2006 the Respondent No.2 issued a tender bid as Scheme No. MM-1/02/2006/2007, in respect of its Plot Nos.15 and 16, admeasuring about 10377.50 sq. meters situated in Sector-15, CBD-Belapur Rode of Navi Mumbai, District Thane (“the suit plot”), to construct a “Star hotel” there. By way of said scheme, Respondent No.2 invited offers by interalia representing Navi Mumbai as city of the future, stating many future projects including Airport, Water Transport etc. and representing/projecting Belapur, as the heart of Navi Mumbai. It was specifically claimed that the International Airport will link Belapur to major cities in the World.
3.1) In the said bid, the Application of M/s. PVP Ventures Pvt. Ltd. (“the Original Allottee”) was accepted by the Respondent No.2. Accordingly, an Allotment Letter dated 27.07.2007 was issued to the said allottee in respect of the suit plot against payment of Lease Premium of Rs.82,70,46,900/- and Misc. Charges of Rs.5,25,350/-. Petitioner No.1 was a subsidiary company of the said Allottee. Hence, said entire amount was paid by Petitioner No.1. The Respondent No.2 acknowledged the same by its receipts dated 27.07.2007, 03.09.2007, 01.10.2007 and receipt dated 01.10.2007 for Rs.5,25,350/- towards Misc. Charges. Later on, at the request of said M/s. PVP Ventures Pvt. Ltd. (the Original Allottee) and against the aforesaid payments, Respondent No.2, by its letter bearing Ref. No. CIDCO/MM-/PLT/Star Hotel/2007/417 dated 29.11.2007 transferred all the benefits in the suit plot in favour of Petitioner No.1, Interalia specifically mentioning that all the terms and conditions of the scheme booklet will remain unchanged and binding. This was followed by an Agreement to Lease (“the Agreement”) of the suit plot, duly executed by Respondent No.2 in favour of the Petitioner No.1 and registered with a stamp duty of Rs.4,13,54,500/- and registration charges of Rs.30,000/-. Then the Respondent No.2 put the suit plot in possession of the Petitioner No.1. Since then i.e., from dated 14.12.2007, the Petitioner No.1 was in possession and occupation of the said pl
The court emphasized that administrative discretion must be exercised fairly, considering both parties' interests, especially when external factors impede contractual obligations.
Penalty for construction delay under lease quashed due to delays from court stay, statutory approvals, additional area; writ maintainable for arbitrary state action; 6-year extension non-discriminato....
Additional premium demand for construction delay under lease held arbitrary where caused by statutory approvals, late commencement certificates, and extra built-up area without timeline; applicable s....
Lease penalty for construction delay invalid where lessor nondiscloses material site defects, supplementary deed removes time limit for additional built-up area, delays due to approvals/statutory fac....
Supplementary lease deeming additional built-up area integral with no time limit overrides original four-year completion clause for composite construction; penalty demands arbitrary, illegal; payment....
Writ jurisdiction can address arbitrary state actions in contractual disputes, emphasizing the importance of procedural fairness and adherence to contractual terms, especially regarding extensions an....
Section 31(7) of the Arbitration and Conciliation Act, 1996 which provides for 18% of interest per annum from date of award till date of payment. Worthwhile it would be to refer to Section 31(7) of A....
The principle of unjust enrichment and the doctrine of legitimate expectations were central to the court's decision, emphasizing the obligation of the Development Authority to act fairly and reasonab....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.