IN THE HIGH COURT OF JUDICATURE AT BOMBAY
M.S. Sonak, Jitendra Jain, JJ.
Gramastha Mandal Kundevahal Through Panchpudhari and ors. - Petitioners
Versus
The State of Maharashtra and ors. – Respondents
Writ Petition No. 12503 of 2024 With Interim Application No. 13648 of 2024
Decided On : 08-04-2025
(A) Maharashtra Highways Act, 1955 - Section 19C - Land acquisition - Petitioners challenged the apportionment of compensation of Rs. 56.26 Crores disbursed to Respondents 3 to 6 without considering their objections - LAO acted ultra vires by adjudicating apportionment disputes and failing to refer the matter to the Principal Civil Court - The Court emphasized that apportionment disputes must be resolved by the Principal Civil Court, not the LAO. (Paras 4, 32, 68)
(B) Legal Malafides - The LAO's actions were found to be vitiated by legal malafides, as he disregarded the Petitioners' objections and rushed to disburse compensation. (Paras 56, 60)
(C) Natural Justice - The Court ruled that the LAO's failure to consider objections before making a consent award violated principles of natural justice. (Paras 52, 66)
Facts of the case:
The Petitioners claimed interest in property acquired under the MHA, filed objections against compensation disbursed to Respondents 3 to 6, which were ignored by the LAO.
Findings of Court:
The LAO's actions were ultra vires, and the compensation disbursed was set aside.
Issues: Whether the LAO had jurisdiction to decide apportionment disputes and whether the Petitioners' objections were adequately considered.
Ratio Decidendi: The Court held that apportionment disputes must be referred to the Principal Civil Court, and the LAO acted beyond his authority by adjudicating such disputes.
Result: The petition was allowed, and the compensation amount was ordered to be refunded and deposited with the Court.
JUDGMENT :
M.S. Sonak, J.
1. Heard learned Counsel for the parties.
2. Rule. The Rule is made returnable immediately at the request of and with the consent of the learned counsel for the parties.
3. In brief, the petitioners assert their interest in the subject property acquired under the Maharashtra Highways Act of 1955 [MHA]. Even before the acquisition proceedings began in 2022, the petitioners had filed a suit against Respondents 3 to 6 concerning this property. The petitioners submitted their objections regarding the payment of compensation to Respondents 3 to 6 before the Land Acquisition Officer -R2 [LAO] within the specified period.However, without considering these objections and in violation of all legal procedures and precedents, the LAO hastily apportioned and disbursed the total compensation of Rs 56.26 Crores to Respondents 3 to 6. The LAO even denied the petitioners information regarding these ultra vires actions and subsequently issued an order rejecting the petitioners' objections to the apportionment. Thus, this Petition.
4. The Petitioners have sought the following substantive reliefs in this petition: -
a) to call for entire record and proceedings in respect of acquisition of the land bearing Survey No.35, Hissa No.0, lying, being and situate at Village Kundevahal, Taluka Panvel, District Raigad from the file of the Respondent No.2;
b) to issue a writ of mandamus, directing the Respondent No.2 to refer the matter to the Principal Civil Court of original jurisdiction, Panvel, Alibaug under Section 19(C)(4) of the Maharashtra Highways Act, 1955;
c) to issue a writ of mandamus, directing the Respondent No.2 to take forthwith steps to recover the amount of Rs.52 crores from the Respondent Nos.3 to 6;
d) to issue a writ of mandamus, directing the Respondent Nos.3 to 6 to deposit the amount of compensation of Rs.52 crores either in the Court of Ld. Civil Judge, Senior Division, Panvel before whom Special Civil Suit No.13 of 2018 is pending or in the Court of Principal Civil Court, Panvel, Alibaug;
e) to take necessary and suitable action against the Respondent No.2 in respect of his malafide, illegal and arbitrary action in not deciding the objection dated 5.9.2023 and without deciding the same disbursing the amount of compensation of Rs.52 crores to the Respondent Nos.3 to 6;
f) to direct the Respondent No. 1 to appoint necessary Committee to conduct the Inquiry against the Respondent No. 2 in respect of his malafide, illegal and arbitrary action in disbursing the amount of compensation of Rs.52 crores to the Respondent Nos. 3 to 6 without deciding the objection of the Petitioners dated 5.9.2023;
5. Mr Suryawanshi learned Counsel for the Petitioners, submitted that there was no justification for the LAO to sit over the objections filed by the Petitioners on 5 September 2023 for almost six months, i.e., up to 18 March 2024. In any event, LAO should have decided on the Petitioner’s objections on 18 April 2024 instead of issuing a consent award based on the consent of Respondents 3 to 6 despite the Petitioner's serious objections and pendency of the Civil Suit against such Respondent concerning the subject property. He submitted that on 18 March 2024, LAO not only issued the consent award but executed the agreement and ordered the release of Rs. 56.26 Crores to Respondents 3 to 6. R-2 pursued the matter and sought to ensure that the bank paid this amount to Respondents 3 to 6 by 22 March 2024.
6. Mr Suryavanshi submitted that this action was or in any event vitiated by legal malafides apart from being contrary to the provisions of Section 19C of the MHA and the law laid down by the Hon’ble Supreme Court in the case of Vinod Kumar & Ors Vs District Magistrate, Mau & Ors, (2023) SCC OnLine 787 and Sojar @ Rukminibai W/o Hari Mule Vs Krishnath @ Krishna S/o Gopal Tate and Ors, (2025) SCC OnLine Bom 307. He submitted that several decisions of this Court took similar views, and still R-2, ignoring all such decisions, adjudicated the
Apportionment disputes under the Maharashtra Highways Act must be referred to the Principal Civil Court, and actions by the Land Acquisition Officer that violate this principle are ultra vires.
The Land Acquisition Officer lacks jurisdiction to decide disputes over compensation apportionment, which must be referred to the Principal Civil Court for resolution.
The competent authority under the National Highways Act lacks jurisdiction to decide apportionment disputes, which must be referred to the Principal Civil Court.
The competent authority under the National Highways Act lacks jurisdiction to apportion compensation and must refer such disputes to the Principal Civil Court.
The competent authority lacks jurisdiction to decide compensation apportionment disputes under the National Highways Act, which must be referred to the Principal Civil Court.
Disputes regarding compensation apportionment under the MIDC Act must be referred to a judicial authority, not decided by administrative officers, ensuring proper legal process is followed.
Point of Law : Respondents, therefore, cannot retain the amounts received by them. Instead, they will have to deposit these amounts before the Reference Court.
(1) Acquisition of land – If any dispute arises as to apportionment of amount or any part thereof or to any person to whom same or any part thereof is payable, then, competent authority shall refer d....
The main legal principle established in the judgment is that disputes regarding apportionment of compensation under the National Highways Act should be referred to the principal civil court of origin....
Point of Law : It is a settled principle of interpretation of statute that the provisions of any statute are to be interpreted to give effect to each of them to the extent possible without giving any....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.