SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Bom) 996

IN THE HIGH COURT OF JUDICATURE AT BOMBAY 
R.I. CHAGLA, J.
Shriram EPC Ltd. - Appellant 
Versus
Parker-Hannifin India Pvt. Ltd. - Respondent
Commercial Arbitration Petition No. 909 of 2019
Decided on : 04-08-2025 

Advocates:
Advocate Appeared:
For the Appellant : Mr. Kevic Setalvad, Senior Counsel a/w Mrs. Rajalakshmy Mohandas, Mr. Amey Kulkarni, Ms. Mukta Chorge & Mr. Nehal Farukh Azam i/b Rajalakshmy Associates
For the Respondent: Mr. Zubin Behramkamdin, Senior Counsel a/w Vijay Purohit, Faizan Mithaiwala, Pratik Jhaveri, Niyari Bhogayta, Vinit Kamdar i/b P&A Law Officers

The obligation to procure financial guarantees remains with the parties as per the contract terms, and failure to meet these obligations justifies claims in arbitration for costs incurred.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Supply Agreement and Multi-Party Agreement (MPA) - Arbitration relating to breach of contract - Petitioner challenged the award passed by the Sole Arbitrator, contending that certain parties were necessary for arbitration and asserting obligations regarding financial guaranties. The Tribunal ruled that the petitioner had defaulted on procuring a Letter of Credit, thereby justifying the Respondent's claims for damages and costs incurred in manufacturing custom goods under the Supply Agreement. (Paras 66-82)

(B) Jurisdiction of Arbitrator - The arbitrator has jurisdiction to decide whether a non-signatory is bound by the arbitration agreement and can implement an arbitration clause effectively. (Paras 10, 49, 66)

(C) Contract Interpretation - The arbitration clause must be interpreted according to the specific obligations defined within the contract, and parties cannot alter contractual terms absent mutual agreement. The learned Arbitrator found that respondent’s obligation to procure materials was enforceable despite contentions of liability being transferred. (Paras 5, 66)

Facts of the case:
The case arises from a dispute over a Supply Agreement for manufacturing custom equipment where the Petitioner failed to procure a Letter of Credit, which led the Respondent to invoke arbitration following the termination of the contract.

Findings of Court:
Petitioner's failure to comply with conditions of the Supply Agreement resulted in breach; hence the Respondent was justified in claiming damages.

Issues: The court determined whether CIAL and APL were necessary parties to the arbitration and if the interpretation of the Supply Agreement warranted a different conclusion.

Ratio Decidendi: The court reasoned that the Petitioner, having defaulted in its obligations under the Supply Agreement, is liable for the contract terms and that the parameters of enforceability were clearly stipulated in the contract.

Result: Commercial Arbitration Petition dismissed.

Table of Content
1. petition challenges award and order under arbitration act. (Para 1 , 2)
2. dispute over procurement of letter of credit and obligations. (Para 3 , 4 , 5 , 6 , 7 , 8)
3. existence and applicability of arbitration clauses examined. (Para 9 , 10 , 11 , 12 , 13 , 14)
4. findings related to breach of contract and liability examined. (Para 15 , 16 , 17 , 18 , 19)
5. assessment of damages and enforcement of contract. (Para 20 , 21 , 22 , 23 , 24 , 25)
6. legal parameters of liquidated damages discussed. (Para 27 , 28 , 29 , 30 , 31)
7. final determination of petition's validity and dismissal. (Para 32 , 33 , 34 , 35 , 36)
JUDGMENT :

R.I. CHAGLA, J.

1. By this Petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 (“ ARBITRATION ACT ”), the Petitioner is impugning (i) Award dated 5th February 2019, passed by the learned Sole Arbitrator (“impugned Award”), rejecting the Petitioner’s contention and partly allowing the claim of the Respondent; and (ii) Order dated 3rd September 2016, passed by the learned Sole Arbitrator (“impugned Order”), rejecting the application filed by the Petitioner under Section 16 of the ARBITRATION ACT .

2. A brief background of facts is necessary as stated hereunder:

(i) A Purchase Order was issued by the Petitioner on 15th March, 2012 in favour of the Respondent for manufacturing and supply of 480 Hydraulic Drives and 960 Hydraulic Cylinders for a total contract price of INR 6,81,60,000/-. These goods were to be custom made as per the specification of the Petitioner and it is contended by the Respondent that the goods were of specific use only to the Petitioner.

(ii) Thereafter, the Petitioner and the Respondent executed a Supply Agreement dated 26th March, 2012. Under Clause 4.8 of the Supply Agreement, the Petitioner was the Consignee of the goods delivered by the Respondent, as per the Delivery Schedule agreed between the parties and was liable to make/ensure full payment to the Respondent for the goods. The Respondent was to deliver the goods in different quantities, which was categorized as lots. Under Clause 5.4 of the Supply Agreement, (i) the Petitioner was liable to pay a non- refundable advance payment of INR 68,16,000/- i.e. 10% of the total contract price; and (ii) The Petitioner, prior to the first delivery of the goods, was liable to procure a usance Letter of Credit payable at site from Corporate Ispat Alloys Limited (“CIAL”), in favour of the Respondent, which was to cover the remaining 90% of the contract price. It is pertinent to note that as per Clause 22.3.1 of the Supply Agreement, a failure to procure a Letter of Credit amounted to the Petitioner’s default under Clause 22.3 and such default entitled the Respondent to terminate the Supply Agreement under Clause 22.4 thereof. Additionally, as per Clause 26.4 of the Supply Agreement, any forbearance or delay on part of either of the party, in enforcing any of its rights under the Supply Agreement would not construe as a waiver of such right to enforce the same.

(iii) A Multi-Party Agreement (“MPA”) was executed on 2nd August, 2012. The MPA was entered between CIAL, APL (“Abhijeet Projects Limited”), the Petitioner and the Respondent but the Agreement was signed only by the Petitioner and the Respondent. The MPA provides a mere clarification to the payment mechanism agreed between the Petitioner and the Respondent. Under Clause A(1) of the MPA, CIAL was to open an irrevocable inland letter of credit in favour of the Respondent, covering 90% of the total contract price. The balance amount was payable by the Petitioner directly. It is pertinent to note that under Clause C of the MPA, it was agreed that all the terms and conditions mentioned in the Supply Agreement shall continue to remain valid and enforceable amongst the parties. As per Clause D of the MPA, in the event of any conflict between the terms of the Supply Agreement and the MPA, the former will prevail i.e. the Supply Agreement. Further, as per the

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top