SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Bom) 5

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
SANDEEP V. MARNE, J.
Lotus Logistics and Developers Pvt. Ltd. – Appellant
Versus
Evertop Apartments Co-operative Housing Society Limited – Respondent
Commercial Arbitration Petition (L) No. 34791 of 2024, Interim Application (L) No. 27998 of 2025
Decided On : 13-01-2026

Advocates Appeared:
For the Appellants : Janak Dwarkadas, Prateek Seksaria, Ankit Lohia, Dharam Jumani, Arun Panickar, Rohit Agarwal, Vijay Nair, Mihir Nerurkar
For the Respondents: Ravi Kadam, Piyush Raheja, Vikramjit Garewal, Aadil Parsurampuria, Tejas Agarwal, Ria Goradia, Tejaswi Pania, Ishaan Choudhary

The court upheld the principle that undertaking given to secure performance of contractual obligations revives a terminated contract, allowing specific performance claims despite prior termination by the society.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Relief sought for invalidation of an Arbitral Award directing petitioner to secure occupation certificate and pay damages for non-compliance - Tribunal directed to amend building plans to align with sanctioned plan, rejected later plans as illegal - Breach of contract is established due to non-completion and unpaid compensation by Developer, which misled the Society with fraudulent plans - The Court upheld the arbitration award finding the Society entitled to specific performance despite initial termination of the contract by the Society, which was revived through subsequent communications and assurances by the Developer. (Paras 1-132)

(B) Specific Performance - An election to terminate does not bar a party from seeking specific performance if substantive steps are taken subsequently to fulfil the contract obligations - The Tribunal maintains that the undertaking made is a crucial factor permitting the Society to claim specific performance - The initial termination of the contract becomes irrelevant once the contract is treated as subsisting through mutual actions. (Paras 95-112)

(C) Damages - Tribunal awarded damages of Rs.128.98 crores calculated based on market value due to the failure to issue an occupation certificate, which was deemed appropriate as it aligned with the losses suffered by members of the Society. If occupation certificate is secured, payment ceases. (Paras 100-116)

(D) Rent and Shortfall Claims - Monthly compensation awarded reflecting actual payments made by the Developer prior to stopping payments - Shortfall compensation directed based on failure to provide contractual area to members as per the agreement - The compensation amounts reflect actual losses sustained. (Paras 121-124)

Table of Content
1. details of arbitration and developer's obligations (Para 1 , 2 , 3)
2. respondent’s claims and breaches by petitioner (Para 4 , 5 , 6)
3. arbitration procedures and claims made (Para 7 , 8 , 9)
4. arguments surrounding specific performance (Para 10 , 11 , 12)
5. judicial arguments on termination of contract (Para 13 , 14 , 15)
6. legal precedents on specific performance (Para 16 , 17 , 18 , 19)
7. principles of specific performance in contract law (Para 20 , 21 , 22)
8. judicial findings against petitioner’s defenses (Para 23 , 24 , 25)
9. court observations on the situation at hand (Para 26 , 27 , 28)
10. description of deceitful conduct by petitioner (Para 29 , 30 , 31)
11. court’s directives on compliance and performance (Para 32 , 33 , 34)
12. final analysis of the case and rulings (Para 35 , 36 , 37)
13. consequences of not performing contractual obligations (Para 38 , 39 , 40)
14. recognition of claims for damages (Para 41 , 42 , 43)

JUDGMENT :

SANDEEP V. MARNE, J.

1. By this Petition filed under Section 34 of the Arbitration and Conciliation Act, 1996, Petitioner has sought invalidation of the Arbitral Award dated 16 August 2024 passed by the learned sole Arbitrator. By the impugned Award, the Arbitral Tribunal has directed Petitioner to have the building plans amended and approved in consonance with the sanctioned plan dated 17 September 2008 for the purpose of issuance of occupation certificate for the building. The Tribunal has directed the Petitioner to take all necessary steps for procurement of occupation certificate for wing ‘A’ building in accordance with building plans sanctioned on 17 September 2008. In the event of non-grant of occupation certificate in respect of wing ‘A’ building, the Tribunal has directed the Petitioner to take steps to get the area shown as ‘open to sky ducts’ in the living rooms and bedrooms, regularaised at its cost within three months of rejection of application for occupation certificate. In the event of non-grant of occupation certificate and rejection of regularisation of ‘A’ wing building, Petitioner is directed to pay to the Respondent-Society sum of Rs.128,98,00,000/- within three months of such rejection alongwith interest @ 8% per annum. The Petitioner is also directed to pay to the Respondent-Society monthly compensation @ Rs.80/- per sq.ft. per month per society member in respect of the period from February-2014 to October-2015 alongwith interest @ 8% per annum. The Petitioner is also directed to pay to the Respondent-Society sum of Rs. 45,82,500/- being the loss on account of shortfall in area alongwith interest @8% per annum. The Petitioner is also directed to pay to the Respondent-Society property taxes for the period from November 2008 till 15 October 2015. Arbitral Tribunal has also declared plans dated 9 May 2009 and 25 March 2011 as well as Rectification Deed dated 3 November 2010 as illegal and void and not binding on the Respondent-Society.

FACTS

2. The Respondent is a cooperative housing society registered under the Maharashtra Co-operative Societies Act, 1960. The Respondent is the owner, seized and possessed of land bearing Plot No.9/10/11 admeasuring 31,603 sq.ft.(2930 sq.mtrs.) bearing CTS No.834/1, 834/2 and 822/1, J.P. Road, Andheri (W), Mumbai-400 053. On the said plot of the society, there were three buildings consisting of ground plus 3 floors having total 58 tenements. The Respondent-Society resolved to go for redevelopment of its buildings and invited offers from developers. The Petitioner is a developer and submitted its offer to the Respondent-Society and offered 52% additional usable carpet area (including flower beds, duct area, dry balcony, niches, etc.) to every member over and above the area occupied by them in the old buildings. The Respondent-Society resolved to appoint the Petitioner as the developer for redevelopment of its buildings. In 2008, the Petitioner-Developer furnished plans including floor plans in respect of the proposed building, u

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top