SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Bom) 74

IN THE HIGH COURT OF JUDICATURE AT BOMBAY 
SANDEEP V.MARNE, J.
INFRA Poonam Developers LLP - Applicant 
Versus 
Jasbir Singh, S/o. Ajit Singh and Ors. - Respondents 
Arbitration Application (L) No.37441 of 2025 With Interim Application (L) No.11418 of 2026 In Arbitration Application (L) No.37441 of 2025
Decided On : 07-04-2026

Advocates Appeared:
For the Applicant : Mr. Aman Saraf with Ms. Sakshi Agarwal i/b. Mr. Bipin J. Joshi.
For the Respondents: Mr. Ziyad Madon with Mr. Chittesh Dalmia.

Delay in Section 11(6) applications condonable under Section 5 Limitation Act only exceptionally with strong cause, such as prior litigations preserving arbitration subject matter like redevelopment project against third-party acquisition.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Sections 11(6), 21, 9 - Limitation Act, 1963 - Article 137, Section 5 - Application under Section 11(6) for arbitrator appointment - Limitation of 3 years runs from failure to respond to Section 21 notice - Period 15.03.2020 to 28.02.2022 excluded per Supreme Court Covid-19 order irrespective of other filings - Further 258 days delay condoned as exceptional case where applicant first preserved redevelopment project via interim measures under Section 9 and writs against housing authority acquisition before filing Section 11(6) - Arbitration clause in partnership alteration deed valid - Sole arbitrator appointed. (Paras 11,12,13,21,24)

(B) Condonation under Section 5 Limitation Act for Section 11(6) applications discretionary only in exceptional cases with very strong cause shown, not routinely or liberally, balancing expeditious resolution. (Paras 13,16)

Facts of the case:
Applicant LLP admitted as partner in firm for redevelopment of tenanted property, invested over Rs.30 crores. Project stalled post plinth, notices issued, rift led to housing authority blacklisting firm and acquiring property. Notice under Section 21 issued 20.06.2020, Section 9 petition filed for interim relief restraining third party rights and coercive steps; multiple writs and representations to save project; Section 11 filed 15.11.2025 post acquisition.

Findings of Court:
Delay of 258 days condoned; sole arbitrator appointed with directions for disclosure, fees per rules, parties to share costs equally.

Issues: Whether limitation period excludes Covid phase; sufficient cause for condoning further delay given efforts to preserve project; validity of arbitration agreement.

Ratio Decidendi: Limitation accrues post Section 21 notice refusal; Covid exclusion mandatory; strong case for condonation where subject matter preservation via litigations against third parties precedes Section 11 filing, altering dispute nature until acquisition confirmed.

Result: Arbitration Application and Interim Application allowed.

Table of Content
1. delayed section 11 application post-section 21 notice invocation (Para 1 , 3 , 4 , 5)
2. partnership disputes over redevelopment project investment and failure (Para 2 , 17 , 18 , 19 , 20)
3. condonation justified by preservation litigations and stakes (Para 6 , 7 , 8)
4. delay inarbitrable due to active pandemic litigations (Para 9)
5. exceptional condonation for subject matter protection efforts (Para 10 , 21 , 22 , 23)
6. limitation accrues post-notice refusal; covid period excluded (Para 11 , 12)
7. section 5 condonation exceptional for section 11 delays (Para 13 , 14 , 15 , 16)
8. sole arbitrator appointed per arbitration clause (Para 24 , 25 , 26 , 27 , 28 , 29)

JUDGMENT :

SANDEEP V.MARNE, J.

1) This is an Application filed by the Applicant under Section 11 of the Arbitration and Conciliation Act, 1996 (the Arbitration Act) for appointment of an Arbitrator for adjudication of disputes between the parties arising out of Deed of Alteration of Partnership dated 10 April 2013. Since there is delay of 258 days in filing the Application, the Applicant has filed Interim Application (L) No.11418 of 2026 for condonation thereof.

2) The Applicant is a registered Limited Liability Partnership Firm. The subject matter of dispute between the parties is the property known as -Panwala chawl Nos. 2 and 3 situated at City Survey No.1/112 of Parel Sewri Division, Building No.75-75A and 75-B, Dr. S.S. Rao Road, Lalbaug, Mumbai (suit property). The property originally belonged to a private trust, which are acquired by M/s. R.B. Builders and Developers (the Firm) pursuant to order passed by this Court. At that time, there were 7 partners namely Respondent Nos.1 to 7 in the Firm. The acquisition was for the purpose of redevelopment of the suit property. The Maharashtra Housing and Area Development Authority (MHADA) issued NOC for redevelopment of the property in the year 2008, which was modified in the year 2010. The Municipal Corporation granted Intimation of Disapproval (IOD) dated 4 August 2010. A Memorandum of Understanding came to be executed between the Respondents and sister concern of the Applicant (Poonam Infra) for transfer of development rights for consideration of Rs.20.70 crores. It is the case of the Applicant that its nominee made a payment of Rs.4 crores to the Firm. Deed of Admission of Partner dated 30 April 2011 was executed, under which Applicant’s nominee -Poonam Infra, a partnership firm was added as 8th partner in the Firm having 15% pro ratio. Poonam Infra was to make contribution of its share for carrying on construction and redevelopment of the project. The Firm obtained commencement certificate dated 9 December 2011. Construction commenced and was completed upto the plinth level. A stop work notice was issued in the year 2012, which was revoked in the year 2013. According to the Applicant, it later realised that its sister concern-Poonam Infra cannot be a partner of another Firm and accordingly, Deed of Alteration of Partnership Firm dated 10 April 2013 was executed, under which the Applicant was made 8th Partner in the Firm. According to the Applicant, MHADA issued show cause notice to the Firm for revocation of NOC. On 29 December 2016 MHADA directed the Firm to effect redevelopment work and pay rent to the tenants, which the Firm was unable to pay. Thereafter litigation took place between the Society, Firm and MHADA relating to the redevelopment project.

3) In the light of above background, the Applicant decided to withdraw itself from the project and sought refund of amount of Rs.29,63,67,674.97. The notice issued by the Applicant was responded by the Respondents denying the contents therein. The Applicant apparently filed police complaints. By notice dated 20 June 2020, the Applicant invoked arbitration clause. Since no response was received, the Applicant filed Arbitration Petition No.241 of 2023 under Section 9 of the Arbitration Act seeking interim measures. On 20 July 2020, this Court granted ad-inte

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top