IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR
Pushpendra Singh Bhati, J.
M/s Kamla Construction Company - Petitioner
Versus
State Of Rajasthan, Through District Collector, Bikaner and ors. - Respondents
S.B. Arbitration Application No. 3 of 2021
Decided On : 22-08-2023
Right to Information Act, 2005 - Arbitration and Conciliation Act, 1996 - Sections 10, 11, 21, 43 - Limitation Act, 1963 - Section 18 - Arbitration - Claiming reliefs - Appointment of an Arbitrator - Held, Court observes that applicant, for first time, demanded due final payment through various letters, and final bill authorization was done thereafter, applicant again issued letters for payment of final bill whereafter, applicant made request for appointment of arbitrator in matter, as per Arbitration Clause 19(a) of agreement in question - Court also observes that applicant made request for appointment of arbitrator after a huge delay of 13 years, because final bill authorization was done, and that, applicant also issued a letter to respondent, which is clearly time barred as per aforementioned precedent law - Court observes that claim and request of applicant has been made beyond prescribed period of limitation, once applicant itself has slept over his rights for a long period of 13 years, and thus, even as per aforementioned precedent law, it is not a fit case for any interference by this Court - Application dismissed.
JUDGMENT :
1. The instant arbitration application has been filed by the applicant-Firm under Sections 10 & 11 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘Act of 1996’) claiming the following reliefs:-
2. The applicant is the partnership Firm, who entered into an agreement with the respondent pertaining to the works pertaining to brick kiln ¼bZaV HkV~Vk½ to be done from 25.04.1996 to 24.04.1997; thereafter, the work order was issued on 10.04.1996. However, the respondent did not make the necessary pending payments to the applicant against the works so done by it. In pursuance of the letters dated 26.05.2020 and 17.07.2020 under the Right to Information Act, 2005, the applicant came to know that total outstanding payment, including security, to be paid by the respondent to the applicant, comes to Rs. 1,94,819/-, which was to be paid by the respondent in the year 1999 itself; whereafter, the applicant wrote letters dated 20.07.2020, 26.08.2020, 31.08.2020 and 21.09.2020 to the respondent to clear the complete outstanding payments.
2.1 The applicant, for the first time, made a request for referring the dispute in question for arbitration and appointment of an Arbitrator, as per the Arbitration Clause, vide letter dated 14.10.2020. Clause 19(a) i.e. Arbitration Clause is reproduced as hereunder:
(a) If any question, difference or objection whatsoever shall arise in any way in connection with or arising out of this instrument or the meaning of operation of any part thereof or the rights and duties or liabilities of either party, then save in so far as the decision of any such matter as herein before provided for and has been so decided every such matter constituting a total claim of Rs. 5,000/-or above whether, its decision has been otherwise provided for and whether it has been finally decided accordingly or whether the contract should be terminated or has been rightly terminated and as regards the rights or obligation of the parties as the result of such terminated Termination shall be referred for adjudication to a sole arbitrator to be appointed as hereinafter provided.
For the purpose of appointing the sole arbitrator referred to above, the Chief Engineer/Addl. Chief Engineer will on receipt of notice and prescribed fee from the contractor send a panel of 3 names not below the rank of Supdtg. Engineer of the Rajasthan Govt. and who shall all be presently unconnected with the contract. The contractor shall on receipt of the names as aforesaid select any one of the persons named, to be appointed as a sole arbitrator and communicate his name to the Chief Engineer/Addl. Chief Engineer. The Chief Engineer/Addl. Chief Engineer shall thereupon appoint the said person as the sole arbitrator without delay. The Arbitrator shall given reasons for the award.”
3. Learned counsel for the applicant submitted that the final bill amount due to be paid to the applicant by the respondent is around 10,23,654/-with interest; the applicant came to know about the said due amount through RTI, in the year of 2020, whereafter, the applicant sent several letters, in regard to the payment of the said final amount, to the respondent.
3.1. Learned counsel further submitted that the applicant also sent a letter dated 14.10.2020 for appointment of Arbitrator as per the Arbitration Clause 19(a) of the agreement in question, but despite the same, the respondent did not respond.
3.2. It was also submitted that since the app
B and T AG Vs. Ministry of Defence, Arbitration Pertition (C) No.13 of 2023
M/s Kamla Construction Company Vs Rajasthan Rajya, S.B. Arbitration Application No. 21/2020
The main legal point established in the judgment is that an application for appointment of an arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996 is subject to the time limitati....
The main legal point established in the judgment is that the limitation for filing an application under Section 11 of the Arbitration Act arises upon the failure to make the appointment of the arbitr....
The main legal point established in the judgment is that the limitation period for filing an application seeking appointment of an arbitrator under Section 11(6) of the Arbitration and Conciliation A....
(1) Period of limitation to file application under Section 11 of Arbitration and Conciliation Act, 1996 is 3 years’ from date of refusal to appoint Arbitrator, or on expiry of 30 days’, whichever is ....
An application under Section 11 for appointment of an arbitrator is time-barred if filed after three years from the refusal to appoint, with delays not justified.
Arbitration requests must be filed within three years of the cause of action; failure to act in time bars subsequent petitions.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.