SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Bom) 401

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Manish Pitale, Shreeram V. Shirsat, JJ.
Anirudha Manohar Khopade and others - Petitioners
Versus
Union of India and others - Respondents
Writ Petition No.16191 of 2025
Decided On : 24-02-2026

Advocates Appeared:
For the Petitioner:Mr. S. B. Deshpande, Senior Advocate (through VC) a/w. Mr. Shreyas Deshpande and Mr. Sandeep Rebari i/b. Mr. Shreyas Deshpande
For the Respondent: Ms. Vaishali Choudhary a/w. Mr. Ashutosh Mishra and Ms. Shazia Ansari for, Mr. Anil Singh, ASG s/w. Mr. Ravi Kini, Mr. Rakesh L. Singh, Mr. Dhaval and, Mr. Krishnakant Deshmukh i/b. M. V. Kini & Co. , Ms. M. S. Bane, AGP , Mr. Sandeep Yadav, Deputy Manager (NHAI) present.

Section 94 of 2013 Land Acquisition Act inapplicable to Highways Act acquisitions; only specified schedules for compensation, R&R apply. Belated claims post-award cannot halt projects, but affected user rights merit expeditious compensation consideration.

Headnote:(A) Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 - Sections 94, 105, 3(x), 28 - National Highways Act, 1956 - Sections 3-A, 3-G - Constitution of India - Article 300-A - Partial acquisition of building under Highways Act - Section 94 of 2013 Act not applicable as Highways Act in Fourth Schedule; Notification under s.105(3) applies only First, Second, Third Schedules for compensation determination, rehabilitation, infrastructure - S.94 miscellaneous provision, time-consuming, against speedy acquisition object - Owners of independent units in unaffected portion cannot claim whole building acquisition - Belated representations post-award, ignoring public notices, not entertainable to stall project - Procedure under Highways Act duly followed; no property deprivation without authority of law - But Competent Authority to consider claims for affected right of user/easement/ livelihood under s.3-G(2), s.28 without halting possession/demolition. (Paras 14-15, 31-44, 49-52)

(B) Land Acquisition - Discrimination - Uniformity in compensation quantum principles mandated; no discrimination for Highways Act acquisitions re solatium/interest, but not extending to other 2013 Act provisions. (Paras 39-43)

Facts of the case:
Petitioners own galas in remaining portion of building, part acquired for national highway project. Failed to respond to public notices under ss.3-A, 3-G(3); raised claims under s.94 of 2013 Act and s.3-G nearly two years post-award upon learning of demolition drive. Respondent relied on expert report confirming no adverse structural impact on remainder.

Findings of Court:
S.94 inapplicable; direct Competent Authority to decide compensation claims for any affected rights within six months sans impeding project work/possession.

Issues: Applicability of s.94 of 2013 Act to Highways Act acquisitions; entitlement of partial owners to whole building acquisition; impact of belated claims; violation of property rights.

Ratio Decidendi: Strict construction of s.105/Fourth Schedule and Notification limits 2013 Act applicability; s.94 not concerning compensation quantum, hence excluded; equity demands consideration of affected interests without project delay. Result : Writ petition disposed of partly; limited relief granted.

Table of Content
1. partial acquisition dispute under section 94 larr act (Para 1 , 2)
2. petitioners' ownership and belated representations filed (Para 3 , 4 , 5 , 6 , 7 , 8)
3. petitioners claim section 94 for full building acquisition (Para 9 , 10 , 11 , 12 , 13)
4. nhai argues section 94 inapplicable to highways act (Para 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22)
5. acquisition followed highways act procedures completely (Para 23 , 24 , 25 , 26 , 27)
6. petitioners ignored public notices and opportunities (Para 28 , 29 , 30)
7. statutory provisions of highways act and larr act (Para 31 , 32 , 33 , 34 , 35)
8. timely claims required under highways act notices (Para 36 , 37)
9. section 94 excluded from highways act acquisitions (Para 38 , 39 , 40 , 41 , 42 , 43)
10. precedents affirm limited applicability of larr provisions (Para 44 , 45 , 46)
11. no restraint on highway construction progress (Para 47 , 48)
12. consider compensation for affected interests (Para 49 , 50 , 51)
13. petition partly allowed for claim consideration (Para 52 , 53 , 54)

JUDGMENT :

Manish Pitale, J.

The petitioners have invoked Section 94 of the RIGHT TO FAIR COMPENSATION AND TRANSPARENCY IN LAND ACQUISITION, REHABILITATION AND RESETTLEMENT ACT , 2013 (hereinafter referred to as the ‘Act of 2013’) to claim that the impugned letter dated 15.11.2025 issued by the respondent No.2 - National Highway Authority of India (NHAI) deserves to be quashed and that the respondents ought to undertake land acquisition proceedings pertaining to the remaining portion of Godown L1 situated at Mauje Bhoirgaon, Taluka - Bhiwandi, District - Thane. The petitioners own some galas in the remaining portion. On the other hand, the respondent - NHAI contends that Section 94 of the Act of 2013 is not available to the petitioners in terms of Section 105 thereof, as acquisitions undertaken as per the National Highways Act, 1956 (hereinafter referred to as the ‘Highways Act’) are not covered under the provisions of the Act of 2013. It is contended that even on facts, it can be demonstrated that the petitioners cannot take shelter of Section 94 of the Act of 2013, to thwart the construction work of Vadodara Mumbai Expressway, in respect of which maximum work has been completed, but for the stretch concerning Village - Bhoirgaon, Taluka - Bhiwandi, District - Thane.

2. It would be necessary to briefly refer to the chronology of events, in the backdrop of which the aforesaid competing claims made by the parties are to be decided.

3. The petitioners are owners of some galas in Godown L1 located at Village - Bhoirgaon, Taluka - Bhiwandi, District - Thane. The petitioners have placed on record copies of Index-II and other such documents to demonstrate their ownership in the respective galas. According to the petitioners, when they came across a demolition drive undertaken in respect of structures in the vicinity of Godown L1, they became aware about the acquisition of lands undertaken by the respondent No.4 - Competent Authority of the State for the purposes of the said expressway. On further enquiries, the petitioners became aware about the land acquisition award dated 24.11.2023, passed by the Competent Authority for land acquisition in order to make land available to the NHAI for construction of the said expressway as part of a National Highway Project.

4. In this backdrop on 30.10.2025, the petitioners through their advocates sent a representation to the respondent No.3 - Collector, Thane, claiming rights under Section 94 of the Act of 2013. It was submitted that since the petitioners are also owners of galas in Godown L1, they have a right to raise objection under Section 94 of the Act of 2013, which stipulates that when a part of any house, manufactory or building is acquired and the owner desires that the whole of such house, manufactory or building should be acquired and if dispute arises in that context, the Collector is bound to refer such dispute to the ‘Authority’ as defined under Secti

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top