IN THE HIGH COURT OF JUDICATURE AT PATNA
CHAKRADHARI SHARAN SINGH, MADHURESH PRASAD, JJ.
Prabha Electro Castings Private Limited a Company incorporated under the provisions of the Companies Act 1965 - Petitioners
Versus
The State of Bihar through the Principal Secretary, Department of Industries, Government of Bihar, Patna. – Respondents
Civil Writ Jurisdiction Case No.9647 of 2020
Decided On : 23-03-2022
Bihar Industrial Area Development Authority Act, 1974 – Section 6(2)(a) read with Rule 3(1) of Bihar Industrial Area Development Authority Rules, 1981 – Cancellation of allotment of plot – Notice has been issued after industrial activity was found closed on plot in question for years together and dues of Authority were outstanding against petitioner – Having availed two months' time out of three months period granted for initiating industrial activity, petitioner is estopped from raising a new and inconsistent plea in its representation which is clearly an effort towards procrastination – Issue regarding cancellation of petitioner's allotment has attained finality inter-partes – Even otherwise, conduct of petitioner does not inspire confidence – Whether bonafide, or otherwise, for at least 19 long years, there has been no industrial activity on petitioner's land, for one reason or other – Petitioner, at best, had opportunity of filing appeal before Appellate Authority in terms of Act, which opportunity also has not been availed – Writ Petition dismissed. (Paras 13 to 21)
Bihar Industrial Area Development Authority & Ors. Vs. Deepak Paints Pvt. Ltd. & Ors. in LPA 353/2008 passed in CWJC No. 7352 of 2007 – Referred.
2011 (5) SCC 435 – Relied.
JUDGMENT :
MADHURESH PRASAD, J.
1. The allotment of plot having an area of 2.27 acres in Raxaul Industrial Area, made in favour of the petitioner has been cancelled by the Executive Director purportedly under the
order of the Managing Director of the Bihar Industrial Area Development Authority (‘BIADA’ for short) by communication dated 20.06.2020 bearing memo no. 556. The petitioner seeks quashing of the same and also a direction upon the respondents restraining them from resuming possession of the plot.
2. Earlier the petitioner had filed CWJC No. 8906/2013 for quashing letter dated 28.04.2012 of the BIADA, calling upon the petitioner to commence production on his plot allotted in the industrial area, failing which the land allotted to the petitioner would be cancelled.
3. At that time Certificate Case No. 04/Electricity/2002-03 was pending against the petitioner for recovery of electrical dues and the writ petition was disposed of by order dated 17.07.2018 in the following terms:
4. It is the petitioner’s case that cancellation of petitioner’s allotted plot is again in violation of Rule 3(1) of Bihar Industrial Area Development Authority Rules, 1981 (‘Rules’ for short) read with Section 6(2)(a) of the Bihar Industrial Area Development Authority Act, 1974 (‘Act’ for short). The petitioner’s unit ran into heavy loss within few years after its commencement due to insufficient and intermittent electricity supply by the Bihar State Electricity Board. This led to dispute between the Bihar State Electricity Board and the petitioner arising out of Certificate Case No. 04/Electricity/2002-2003. The BIADA was knowing about the dispute and was thus aware that closure of petitioner’s unit was bonafide and for reasons beyond its control. However, without complying with principles of natural justice, allotment of petitioner’s plot is sought to be cancelled by the impugned communication which is thus legally unsustainable.
5. The petitioner’s counsel has also submitted that the petitioner may be allowed at least six-month time as per decision of the Division Bench in the case of Bihar Industrial Area Development Authority & Ors. vs. Deepak Paints Pvt. Ltd. & Ors. in LPA 353/2008 passed in CWJC No. 7352 of 2007 (Annexure-11), since intervening factors such as illegal demand for electrical dues etc. have delayed commencement of production.
6. BIADA has filed a counter-affidavit, to which petitioner has also filed a rejoinder.
7. At the outset, learned counsel for the BIADA has taken an objection regarding maintainability of the writ petition. He has submitted that the petitioner has repeatedly committed breach/violation of the terms of allotment and having done so he cannot be permitted to invoke the equitable, discretionary writ jurisdiction.
8. Another ground of objection is that the canellation of petitioner’s plot can be challenged before the learned Appellate Authority, i.e., Principal Secretary, Department of Industry, as per Section 6(2)(a) of the Act. Since the petitioner has adequate alternative remedy, this Court may not exercise discretion in favour of the petitioner.
9. Learned counsel for the BIADA
The court upheld the cancellation of land allotment due to the petitioner's non-utilization for over twenty years, reinforcing authority's jurisdiction under the BIADA Act, 1974 and its amendments.
Failure to utilize allocated industrial land justifies its cancellation under statutory provisions.
The court emphasized that passing of an order of cancellation of allotment was not mandatory on violation of the conditions of allotment letters, and that the petitioner's substantial compliance with....
Compliance with undertaking and consequences of breaching it are crucial in the disposal of the petition.
Non-compliance with lease conditions and non-utilization of allotted land can justify the cancellation of the lease by the authority.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.