SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Cal) 630

IN THE HIGH COURT OF CALCUTTA
Shekhar B. Saraf, J.
Siliguri Jalpaiguri Development Authority - Appellant
Versus
Bengal Unitech Universal Siliguri Projects Limited - Respondent
I.A. G.A. No. 1 of 2022 and A.P. No. 230 of 2022
Decided On : 22-06-2022

Advocates appeared:
Mr. S.N. Mookherjee, Senior Advocate, Mr. Anirban Ray, Advocate, Mr. Raja Saha, Advocate, Mr. Chayan Gupta, Advocate, Mr. Sandip Dasgupta, Advocate, Mr. Saaqib Siddiqui, Advocate, Mr. Aviroop Mitra, Advocate, for the Appellant; Mr. Siddharth Batra, Advocate, Mr. Ashish Shah, Advocate, Mr. Chinmay Dubey, Advocate, Ms. Moumita Chakraborti, Advocate, for the Respondent.

The main legal point established is that the court has discretion in granting stay of an arbitral award and must ensure real and sufficient security for the award holder, as per the provisions of the Arbitration and Conciliation Act, 1996.

Headnote:

Arbitration - Stay of Award - Arbitration and Conciliation Act, 1996 - Section 34, Section 36 - Order XLI, Rule 5 - Civil Procedure Code, 1908

Fact of the Case:

The petitioner/respondent filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996 seeking stay of an arbitral award. The dispute arose from an agreement for a new township project, where the respondent made a deposit but the project did not commence due to non-execution of the lease agreement. The petitioner terminated the development agreement, leading to arbitration.

Finding of the Court:

The court found that the arbitral award was a speaking award and prima facie did not show illegality, perversity, or violation of law. The court also held that the security for the award must be real and not illusionary, and directed the petitioner to deposit 50% of the arbitral award as cash security and secure the remaining 50% by bank guarantee.

Issues: The issues involved the validity of the arbitral award, the discretion of the court in granting stay, and the sufficiency of the security offered by the petitioner.

Ratio Decidendi: The court applied the provisions of Section 36 of the Arbitration and Conciliation Act, 1996, and Order XLI, Rule 5 of the Civil Procedure Code, 1908 to determine the conditions for granting stay of the arbitral award and the requirements for security.

Final Decision: The court directed the petitioner to provide security for 50% of the arbitral award as cash deposit and the remaining 50% as bank guarantee, with a stay of execution of the award until the disposal of the application under Section 34 of the Act.

ORDER

Shekhar B. Saraf, J. - The petitioner/respondent has filed this petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the 1996 Act) along with an application under Section 36 (2) of the 1996 Act being GA No. 1 of 2022 in AP 230 of 2022 praying for stay of the award passed by the arbitral tribunal on December 27, 2021. As per the award, the respondent/claimant is entitled to a refund of Rs. 84.24 Crores which it had deposited with the petitioner on December 27, 2006. The arbitral tribunal also directed to pay the above refund with simple interest at the rate of 6% per annum for the period from the date of deposit to the date of full payment of the said amount. As per the award the petitioner was further directed to pay pendent-lite and future interest at the rate of 9% simple interest per annum from the date of award till the date of payment. However, the pendent-lite interest would apply to the awarded amount in case the same was not paid within three months commencing from the date of the award. Lastly, the Arbitral Tribunal also awarded a sum of Rs. 25,00,000/- towards reimbursement of litigation and arbitral costs.

2. The dispute between the parties arises out of an agreement to carry out a new township project for which the petitioner invited financial bids through a tender process. The financial bid of the respondent was accepted and the petitioner via letter dated December 21, 2006 issued a Letter of Award. As per the terms of the above letter the respondent was required to deposit 40% of the bid amount within 15 days. Pursuant to the deposit made by the respondent on December 27, 2006, the petitioner authority handed over the possession of 90.19 acres of land to the respondent on August 10, 2007. However, no lease deed was entered between the parties at the time of handing over of the possession of the land. After a lapse of one year, the lease agreement for execution of work and the development agreement for the same were still not executed between the parties. Finally, in order to govern the relations between the parties a formal development agreement mentioning the terms and conditions were reduced in writing on April 25, 2008. After entering into the above development agreement several communications took place between the parties, but the agreement for lease of the land measuring 90.19 acres was not executed in favour of the respondent/claimant. Due to non-execution of the lease between the parties, the new township project was not commenced by the respondent claimant. In the meanwhile, the petitioner demanded the remaining sums required to be paid by the respondent claimant. The respondent did not pay the remaining amount due to non-execution of the lease document. Finally, the petitioner terminated the development agreement due to nonpayment of the balance instalments constituting event of default by the respondent. The parties kept on holding to their respective stand and invoked the arbitration clause for settlement of the dispute. After considering the respective claims presented by both the parties during the arbitral proceedings, the tribunal awarded refund of the amount paid by the respondent towards the first instalment of Rs. 84.24 Crores.

3. Mr. S.N. Mookherjee, Senior Advocate appearing for the petitioner argues that the court has the discretion to decide the mode of security to be furnished by the petitioner. He states that the land in possession of the respondent can be accepted as a valid security for granting stay of the arbitral award under Section 36 of the 1996 Act. Mr. Siddharth Batra, advocate appearing for the respondent highlights the default committed by the petitioner as per the development contract entered between them. He relies on Clause 3 of the agreement. Sub-clause 3 of Clause 3 highlights the obligation of the petitioner to deliver peaceful possession of the project land in favour of the respondent free from all encumbrances for which

    Click Here to Read the rest of this document
    1
    2
    3
    4
    5
    6
    7
    8
    9
    10
    11
    SupremeToday Portrait Ad
    supreme today icon
    logo-black

    An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

    Please visit our Training & Support
    Center or Contact Us for assistance

    qr

    Scan Me!

    India’s Legal research and Law Firm App, Download now!

    For Daily Legal Updates, Join us on :

    whatsapp-icon Back to top