IN THE HIGH COURT OF CALCUTTA
Ravi Krishan Kapur, J.
Rashmi Seamless Limited - Appellant
Versus
Nem Engineering Projects Private Limited - Respondent
IA No: GA/1/2021 & AP/463/2021
Decided On : 11-01-2022
Arbitration and Conciliation Act - Stay of Award - Section 36(2) - Seamless Pipe Manufacturing Plant - 26 March, 2021 Contract - Awarded Amount: Rs. 11,35,62,532.67 - Ad-Interim Order - Amended Section 36 - Stay of Award with Conditions
Fact of the Case:
The petitioner sought stay of an award passed by the Arbitrator related to the setting up of a Seamless Pipe Manufacturing Plant. The award directed the petitioner to pay a sum of Rs.11,35,62,532.76 to the respondent. The petitioner contended that an ad-interim order granted stay of the award on the condition of depositing 50% of the principal amount, which should continue till the disposal of the application under Section 34 of the Act. The respondent argued that the entire awarded amount should be secured.
Finding of the Court:
The court found that the award was a speaking award passed after considering the parties' contentions. It held that there was no illegality or perversity in the award at a prima facie stage. The ad-interim order was not binding at the final hearing, and the court rejected the petitioner's contention that it should continue. The court directed a stay of the award subject to the condition that the petitioner deposit 50% of the awarded amount by cash security and the remaining 50% be secured by bank guarantee.
Issues: Stay of award, ad-interim order, security of awarded amount
Ratio Decidendi: Ad-interim orders are not binding at the final hearing. The amended Section 36 of the Act contemplates securing the award holder for the entirety of the awarded amount. The court can impose conditions for the stay of the award.
Final Decision: The court directed a stay of the award subject to specific conditions regarding the deposit and security of the awarded amount.
JUDGMENT
Ravi Krishan Kapur, J. - This is an application under Section 36(2) of the Arbitration and Conciliation Act, 1996 ('the Act'), wherein the petitioner has prayed for stay of operation of an award dated October 6, 2021 (as corrected by a letter dated October 7, 2021)[the award] passed by the Arbitrator.
2. The disputes by and between the parties relate to the process of setting up of a Seamless Pipe Manufacturing Plant at Kharagpur. Pursuant to negotiations, the parties had entered into a contract dated 26 March, 2021, whereby construction and installation work for sanction of a Seamless Manufacturing Plant was entrusted to the respondent. The contract contained an arbitration clause and the award is a culmination of the disputes and differences which had been referred to arbitration.
3. By the said award, the Arbitrator has directed the petitioner, to pay a sum of Rs.11,35,62,532.76/- to the respondent, particulars whereof are set out hereinbelow:
Sl. No. | Particulars of Award |
| Amount |
(i) | Principal sum | : | Rs.5,67,28,651.00 |
(ii) | Interest for pre-reference period from 1st March 2012 to 5th August 2012 as mentioned above | : | Rs.43,92,196.38 |
(iii) | Interim interest from the date of reference till the date of the Award @10% per annum on the principal sum from 6th August 2012 to 30th September 2021 | : | Rs.5,19,41,685.38 |
(iv) | Cost of Arbitration | : | Rs.5,00,000.00 |
| Total | : | Rs.11,35,62,532.67/- |
4. The primary contention made on behalf of the petitioner is that by an ad-interim order dated 29 October, 2021 passed by a Coordinate Bench, stay of operation of the award was granted on the condition that, the petitioner would deposit 50% of the principal amount of the award by way of bank draft to the Registrar Original Side, High Court Calcutta. Hence, it is contended on behalf of the petitioner, that the order dated 29 October, 2021 ought to continue till the disposal of the application under Section 34 of the Act. In this connection reliance is also placed on an unreported judgement in Kolkata Metropolitan Development vs. South City Projects Calcutta Ltd.
5. On behalf of the respondent, it is submitted that, there is no question of permitting the petitioner to secure only 50% of the principal amount. The award is a composite award for an amount of Rs. 11,35,62,532.67/- and the petitioner is obliged to secure the entire awarded amount. In respect of the ad-interim order dated 29 October, 2021, it is contended that, the same was only an ad-interim measure and cannot be binding at the final hearing of this application. The respondent also relied on Pam Developments Private Ltd. Vs. State of West Bengal AIR 2019 SC 3937, Hyder Consulting (UK) Limited vs. Governor, State of Orissa (2015) 2 SCC 189, Board of Trustees for the Port of Kolkata vs. ABG Kolkata Container Terminal Private Limited 2019 SCC OnLine Cal 4009 and Kanpur Jal Sansthan and Another vs. Bapu Constructions (2015) 5 SCC 267.
6. I have considered the submissions made on behalf of the parties.
7. At the outset, I find that the award is a speaking award and has been passed after considering the rival contentions of the parties. The Learned Arbitrator appears to have taken into consideration the pleadings filed on behalf of the parties, framed issues and dealt with the respective claims as well as the counterclaims of the parties. I also find that the Arbitrator has held that:-
'It, therefore, appears from the record that excepting filing the counter statement of claim and counter claim, the respondent had not participated in the proceeding at all either to cross-examine the claimants' witness or by producing any witness of its own or by advancing any oral argument in the matter inspite of several notices were given by the tribunal'.
8. Accordingly, at this prima facie stage and being fully aware that the application under Section 34 of the Act is pending adjudication, I am prima facie satisfied that per se there is no illegality nor perversity nor violation of any law which ex facie appears from a plain reading
Hyder Consulting (UK) Limited vs. Governor
Kanpur Jal Sansthan and Another vs. Bapu Constructions (2015) 5 SCC 267
Pam Developments Private Ltd. vs. State of West Bengal AIR 2019 SC 3937
The court can impose conditions for the stay of an award, and ad-interim orders are not binding at the final hearing.
The main legal point established in the judgment is the requirement to secure the entire awarded amount as per the amended Section 36 of the Arbitration and Conciliation Act, 1996.
Automatic suspension of execution of the award, the moment an application challenging the said award is filed under section 34 of Act leaving no discretion in court to put parties on terms, in court ....
(1) There is no hard and fast rule that application made earlier in point of time must be heard before application made later in point of time.(2) Under Section 36 of Arbitration and Conciliation Act....
The main legal point established in the judgment is that post-award interest is mandatory, and the court has discretionary power to grant stay of an arbitral award, guided by the principles under Ord....
The main legal point established in the judgment is that under Section 36(3) of the Arbitration Act, there is a requirement for depositing 100% of the awarded amount for the grant of stay, and the Co....
The main legal point established in the judgment is the discretion of the court to direct the petitioner to furnish security on the full arbitral award and the impact of the Arbitration and Conciliat....
Point of Law : Since the award was a money decree there should be 100% deposit with respondent being entitled to withdraw amount deposited and furnish solvent security to the satisfaction of High Cou....
The Court emphasized the limited scope of challenge against an award under the Act and balanced the equities between the parties in granting or modifying the order.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.