IN THE HIGH COURT AT CALCUTTA
SABYASACHI BHATTACHARYYA, J.
Adhunik Corporation Ltd. And Another – Petitioners
Versus
West Bengal State Electricity Distribution Company Limited and Others – Respondents
W.P.A. No.16229 of 2004
Decided On : 25-04-2023
Electricity Act, 2003 - Section 185, 135, 126, (5) - Imposition of preliminary penal charge - Refund of amount - Petitioners have challenged imposition of preliminary penal charge of Rs.20,000,00/-vide Notice issued by DPL and seek a refund of said amount with interest – Held, Temporary disconnection was sought to be made absolute by DPL on allegation of pilferage, made all on a sudden during ongoing work undertaken by DPL personnel, which is palpably extortive and unjust, in contravention of law and all norms of natural justice - Petitioners are justified in arguing that assessments made by licensee, both preliminary and final, are perverse and based on precious nothing in form of supporting calculations - Hence, amounts charged from petitioner, both by way of preliminary and final assessment by DPL, now inherited by WBSEDCL, is perverse and not sustainable in law - Hence, WPA is allowed, thereby directing WBSEDCL to refund amount of Rs.20,000,00/-, paid by petitioner as preliminary penalty, to petitioners along with interest on said sum of Rs.20,000,00/-at rate of 6% per annum till date of such payment – WPA allowed.
JUDGMENT :
(Sabyasachi Bhattacharyya, J.) :
1. The writ petitioner no.1-Company is a consumer of electricity from the respondent no.1, the West Bengal State Electricity Distribution Company Limited (WBSEDCL). Previously it was a consumer under the Durgapur Projects Limited (DPL), which was subsequently taken over by the WBSEDCL, a Government of West Bengal undertaking.
2. The petitioners have challenged the imposition of preliminary penal charge of Rs.20,000,00/-vide Notice dated August five, 2002 issued by the DPL and seek a refund of the said amount with interest.
3. A subsequent consequential bill issued on February 6, 2004, demanding an amount of Rs.2,87,07,420/-as assessment for theft or pilferage of energy by the petitioners and a further notice dated September 6, 2004 of disconnection in default of payment of such sum have also been assailed in the present writ petition.
4. The learned Senior Advocate for the petitioners argues that the allegation of pilferage is an afterthought. There was no complaint or FIR at any point of time lodged by the DPL. The alleged pilferage was not detected previously. Moreover, it is argued that the allegation of digging/using a cable trench to have access to the meter room is levelled for the first time in the affidavit-in-opposition filed by the WBSEDCL in the present writ petition. The allegation of pilferage is not credible since the meter room housing the meter of the DPL (now WBSEDCL) has all along been under lock and key of the licensee and was opened and closed exclusively by the personnel of the licensee at the time of holding inspections and taking meter readings.
5. In the previous billing cycle prior to the alleged act of pilferage, regular meter reading was taken by the DPL personnel, but no allegation of tampering was made.
6. It is submitted that since the meter room has all along been under the exclusive control of the licensee, there could not be any hand of the petitioner at all in the pilferage, if any.
7. The WBSEB Regulations/Guidelines, sought to be implemented by the licensee, was never applicable to the contract between the petitioner and the DPL. Although the agreement between the two referred to DPL Regulations, there was no Regulation or general conditions of contract of the DPL at any point of time.
8. It is argued that the amount claimed by the licensee from the petitioner was patently perverse and without any basis. In this context, the learned Senior Advocate for the petitioners cites a Supreme Court judgment reported at (2019) 4 SCC 500 [Sarvepalli Ramaiah (Dead) as per legal representatives and others Vs. District Collector, Chittoor District and others], where it was held that any decision based on perversity, patent illegality, irrationality and procedural irregularity ought to be set aside.
9. It is next argued that the defence sought to be advanced by the licensee/respondent has been taken for the first time after five years of the alleged incident, in the affidavit-in-opposition of the licensee. The digging up of a cable trench at the location is not established from the records at all. In fact, the petitioners argue, the relevant paragraphs in the opposition of the Respondents are affirmed to be true to knowledge of the deponent derived from the records, without any records being produced in support thereof. In this context, the learned Senior Advocate cites Bharat Singh & Ors. V. State of Haryana, reported at (1988) 4 SCC 434, for the proposition that no defence can be taken for the first time in affidavit, particularly without any supporting document, which renders the defence of the respondent a nullity.
10. It is submitted further that the payment by the petitioners of the amount of Rs.20,000,00/-as per the preliminary claim of the DPL was made under duress and coercion, under the threat of disconnection. It is argued that there was unequal bargaining power prevailing between the parties. The petitioner no.1-industry employs several workers, who wou
The acquittal of the petitioner in a criminal case under Section 135 of the Electricity Act, 2003, exonerated the petitioner from liability under Section 126. The absence of a final order of assessme....
The main legal point established in the judgment is that the lack of communication of assessment orders to the consumer deprived the consumer of the opportunity to contest the orders, rendering any d....
Regulation 22 allows electricity disconnection without notice upon detection of energy theft, emphasizing public interest and regulatory validity, conditioned on subsequent assessment and hearing rig....
The burden of proof lies on the respondent to establish that irregularities with the meter box and wires existed from the beginning and were not responsible for the tampering.
The court affirmed the conviction for electricity theft based on credible evidence despite the defendant's claims of procedural impropriety.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.