2024 Supreme(Cal) 1033

IN THE HIGH COURT AT CALCUTTA
SABYASACHI BHATTACHARYYA, J.
Sajarul Rahaman And Anr. – Appellants
Versus
SREI Equipment Finance Limited And Anr. – Respondent
AP-COM/304/2024 [Old case no. AP/250/2023, AP/262/2023], AP-COM/305/2024, AP-COM/314/2024, AP-COM/319/2024, AP-COM/347/2024, AP-COM/348/2024, AP-COM/349/2024, AP-COM/350/2024, AP-COM/351/2024
Decided on : 27-08-2024

Important Points

IMPORTANT POINT
The court established that applications under Section 34 of the Arbitration Act can be maintained despite deficit court fees, as the court has discretion to cure such defects.

Subject

Civil Law - Arbitration

Act Referred

ARBITRATION ACT : S.2(1)(c)
ARBITRATION AND CONCILIATION ACT : S.34, S.34(3), S.37, S.50, S.12
CIVIL PROCEDURE CODE : S.149
COURT FEES ACT : S.4, S.4(2), S.28, S.42, S.46
TAMIL NADU COURT FEES ACT : S.5

Headnote

Court Fees - Arbitration Act - Arbitration and Conciliation Act, 1996, Section 34; West Bengal Court Fees Act, 1970, Section 4, Schedule II - The court interpreted the relevant provisions of the Arbitration Act and the Court Fees Act, concluding that the application under Section 34 was maintainable despite the deficit court fees, as the court has discretion to cure such defects.

Fact of the Case:

The petitioner filed an application under Section 34 of the Arbitration and Conciliation Act, 1996, challenging an arbitral award but did so with insufficient court fees, leading the respondent to argue that the application was time-barred due to the lack of proper fees.

Finding of the Court:

The court found that while the application was filed with a deficit in court fees, it had the discretion under the Court Fees Act to accept the application and allow for the curing of the defect, thus ruling the application maintainable.

Issues: Whether the application under Section 34 of the Arbitration Act was maintainable despite being filed with deficit court fees and whether the court had jurisdiction to condone the delay in payment.

Ratio Decidendi: The court held that the provisions of the Court Fees Act allow for the curing of defects in court fees and that the application was filed within the permissible time frame, thus maintaining its validity.

Result: The objection regarding maintainability due to deficit court fees was declined, and the application under Section 34 was accepted as maintainable.

Advocates:
Advocate Appeared:
For the Appellant : Mr. S.E. Huda, Adv., Mr. Himadri Roy, Adv., Mr. Sk Aptabuddin, Adv.
For the Respondent: Mr. Swatarup Banerjee, Adv., Mr. Sariful Haque, Adv., Mr. Saubhik Chowdhury, Adv., Ms. Prarthana Singha Roy, Adv., Mr. Swatarup Banerjee, Adv., Mr. Sariful Haque, Adv., Mr. Rajib Mullick, Adv., Ms. Sonia Mukherjee, Adv., Mr. Swatarup Banerjee, Adv., Mr. Sariful Haque, Adv., Mr. Avishek Guha, Adv., Ms. Enakshi Saha, Adv.

JUDGMENT :

Sabyasachi Bhattacharyya, J.

1. The matters are taken up for deciding the objection raised by the respondent to the effect that the application under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as, the “Arbitration Act”), having been filed with deficit Court Fees, is barred by limitation.

2. Learned counsel for the respondent argues that the court-fee payable on an application under Section 34 of the 1996 Act is governed by Serial no. 1(10) of Schedule II of the West Bengal Court Fees Act, 1970 (hereinafter referred to as “the Court Fees Act), which stipulates the court-fee to be Rs.5,000/- for a case as the present one.

3. It is contended that as per Section 34(3) of the Arbitration Act, the limitation for preferring an application under Section 34 is three months after the date on which the applicant receives the arbitral award. A further period of thirty days is stipulated in the proviso to the said sub-section, during which, subject to satisfaction of the court that the applicant was prevented by sufficient cause from making the application within three months, the court has the power to accept such an application. Although the instant application under Section 34 was filed within such time, the outer limit of limitation stipulated in Section 34(3) and its proviso has long lapsed. Thus, the application ought to be dismissed as time-barred.

4. The award in the present case was received by the petitioner on December 31, 2022. The period of three months thereafter expired on March 31, 2023. A further period of thirty days expired on April 30, 2023. The application under Section 34 was filed with court fees of Rs.130/- on April 27, 2023. Court fees of Rs. 5,000/- has admittedly not been paid till date, let alone within April 30, 2023.

5. Learned counsel for the respondent relies on Section 4 of the Court Fees Act, which stipulates that no document which is chargeable with fee under the said Act shall be filed, exhibited or recorded in, or be acted on or furnished by any court including the High Court unless in respect of such document there be paid a fee of an amount not less than that indicated as chargeable under the said Act.

6. Section 4(2), which provides that a court may receive a plaint or memorandum of appeal in respect of which an insufficient fee has been paid subject to the condition that the plaint or memorandum shall be rejected unless the plaintiff or appellant, as the case may be, pays to the court within a time to be fixed by the court such reasonable sum on account of court fees as the court may direct, is applicable only to plaints or memoranda of appeal. Section 34 does not envisage either a plaint or a memorandum and, as such, the relaxation provided under sub-section (2) of Section 4 of the Court Fees Act is not applicable to such an application.

7. A co-ordinate Bench judgment in Tata Iron & Steel Co. Ltd V. Durgapur Project Ltd. reported at (2005) 4 CHN 501 has been cited by the petitioner. However, it is argued that the finding in the said judgment that Entry No. 1(10)(iii) of Schedule II of the Court Fees Ac, is not very happily worded and the correct provision which needs to be looked into for payment of Court Fees in respect of an application under Section 34 should be Entry No.17(iv) and Entry No.2(c), is per incuriam in nature.

8. It is argued that the use of the punctuation mark comma after the expression “Application under Section 12 or Section 34 of the Arbitration Act”, is disjunctive, separating the rest of the clause from the earlier part. In such context, learned counsel relies on the LAW LEXICON by P. RAMANATHA AIYAR (RE-PRINT EDITION 1992). Learned counsel also cites Khengarbhai Lakhabhai Dambhala v. State of Gujrat reported at 2024 SCC OnLine SC 512 to argue that the Supreme Court has defined the word “comma”, but in view of the relevant provision under the Court Fees Act being completely explainable, the judgment does not have much application here