HIGH COURT OF TRIPURA AGARTALA
Aparesh Kumar Singh, CJ. , Arindam Lodh, JJ.
Sri Ashes Deb - Appellant
Versus
State of Tripura - Respondent
Arb. A. 05 of 2023 & Arb. A. 06 of 2023
Decided On : 10-04-2024
| Table of Content |
|---|
| 1. jurisdiction issues under arbitration act (Para 1 , 2) |
| 2. details of disputed contracts (Para 3 , 4) |
| 3. awards issued by arbitrator and case number references (Para 5 , 6 , 7) |
| 4. condonation of delay issues raised (Para 8) |
| 5. court's decision analysis on jurisdiction (Para 9 , 27) |
| 6. arguments on limitation calculations (Para 10 , 11 , 12 , 13 , 14) |
| 7. statutory jurisdiction competency arguments (Para 15 , 16 , 17) |
| 8. claims on delay explanations and counter-arguments (Para 18 , 19) |
| 9. arguments surrounding the appropriateness of the commercial court's actions. (Para 20 , 24) |
| 10. interpretation of effective dates for limitation (Para 31 , 32 , 33 , 34) |
| 11. final ruling on limitation highlights adherence to statutory timely applications. (Para 39) |
| 12. final ruling on limitation adherence and implications (Para 40 , 41 , 42 , 46) |
JUDGMENT & ORDER (ORAL)
Aparesh Kumar Singh, CJ. - The primary question involved in these two appeals is whether an application under Section 34 of the Arbitration and Conciliation Act, 1996, as amended (for short, the Act) before the learned Commercial Court, West Tripura, Agartala was barred by the delay being beyond the period of three months and thirty days in terms of Section 34 (3) of the Act and its proviso.
2. The appellant is a contractor who has raised three more grounds of challenge in the present appeal preferred under Section 37 (1)(c) of the Act read with Section 13 (1-A) of the Commercial Courts Act , 2015 (hereinafter referred to as the Act of 2015), i.e. (ii) Whether the learned Commercial Court, West Tripura at Agartala had the jurisdiction to entertain a petition under Section 34 of the Act as the subject matter of the dispute pertains to Longtharai Valley which is in Dhalai District? (iii) Whether the Court of Additional District Judge, West Tripura at Agartala would be the competent court as prescribed under Section 2(1)(e) of the Act read with Section 10 of the Act of 2015? and (iv) whether the explanations offered by the respondent seeking condonation of delay constitute sufficient cause to condone the delay?
3. In order to appreciate the issues at hand the relevant facts of both the appeals are being chronicled in a brief manner hereinafter. In Arbitration Appeal No.5 of 2023, the appellant was appointed for execution of works contract, namely, construction of RCC Bridge (under RIDF-XIV) on Chailengta-Chawmanu road (i) over local Durgacherra at chainage 6.85 km Job No.TP/COM/258/08-09, (ii) over local Gurucharancherra at Chainage 8.35 km (Job No.TP/COM/259/08-09, (iii) Over local Hezacherra at Chainage 9.35 km (Job No. TP/COM/260/08-09. On account of a dispute which arose during the execution of the agreement, the respondent employer terminated the contract on December 11, 2018.
4. In Arbitration Appeal No.6 of 2023 the appellant was appointed for execution of works contract, namely, replacement of existing SPT Bridge by RCC Bridge over (i) Localcherra on the road from AA road to Maslimukh via Mundapara at Ch.5.00 km (length-15.00m) Job No.TP/COM/57/2012-13, (ii) Jarulcherra on the road from Manu Fire Service Station to Bichitra Das para at Ch.0.25 km (length-30.00 km), Job No. TP/COM/58/2012-13, (iii) Malidharcherra on the road from Kacharicherra TSR Camp to Kacharicherra Regrouping Centre road at Ch.0.21 km (length-60.00m), Job No. TP/COM/59/2012-13, sanctioned for implementation under NABARD (RIDF-XVIII). On account of a dispute which arose during the execution of the agreement, the respondent employer terminated the contract on July 1st, 2019.
5. On an application under Section 11 (6) of the Act, this Court appointed an Arbitrator in respect of both the disputes vide order dated 5th February, 2021. The learned Arbitrator registered case No. 2/ARB/SS/2021 in respect of Arbitration Appeal No. 05 of 2023 and case No. 1/ARB/SS/2021 in respect of Arbitration Appeal No. 06 of 2023. After exchange of pleadings and upon hearing the learned counsel for the parties and on going t
The limitation period for an application under Section 34 of the Arbitration and Conciliation Act cannot be extended beyond specified timelines, maintaining strict adherence to legal provisions.
Delay beyond 120 days (90+30) in Section 34 petitions or corresponding appeals under Section 37 of Arbitration Act not condonable via Limitation Act Section 5; negligence, inaction, lack of bonafides....
The period for challenging an arbitral award under Section 34 of the Arbitration and Conciliation Act cannot be extended beyond the prescribed period, as the Act is a self-contained special law and t....
The interpretation of 'three months' in Section 34(3) of the Arbitration and Conciliation Act, 1996, is clarified to mean three calendar months, not strictly 90 days.
Point of Law : Even if the period of delay is considered to be of 21 days. Since Section 34(3) of the Act, 1996 bars condonation of delay beyond the period of 30 days after the period of 3 months is ....
The court upheld limitations on condonation applications under the Arbitration and Conciliation Act, emphasizing adherence to statutory timelines.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.