SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Bom) 207

IN THE HIGH COURT OF JUDICATURE AT BOMBAY AURANGABAD BENCH
VIBHA KANKANWADI, HITEN S. VENEGAVKAR, JJ.
M/s. MVV Satyanarayan – Appellant
Versus
The General Manager, Central Railway, Mumbai – Respondent
Writ Petition No. 606 of 2026
Decided On : 27-03-2026

Advocates Appeared:
For the Appellants : Prasadrao Vemulapalli, A.A. Fulfagar
For the Respondent: N.S. Salunke

Writ under Article 226 not maintainable for contractual termination disputes involving factual questions when arbitration clause exists, natural justice not violated, and no public law issue raised.

Headnote:(A) Constitution of India - Article 226 - Contracts - Arbitration clause (Clauses 63 and 64 of General Conditions of Contract) - Writ petition challenging part termination and full termination of works contract for construction of bridges, road under bridges and drain works - Alleged slow progress despite time extensions - Multiple show-cause notices, meetings and opportunities provided - No violation of principles of natural justice - Disputes involve contested questions of fact regarding progress, offloading of works, site conditions and payments due - No public law element demonstrated - Alternative remedy of arbitration efficacious - Petition not maintainable - Parties relegated to arbitration - Security deposit, EMD and performance bank guarantee protected pending arbitration. (Paras 19 to 32)

(B) Natural justice - Prolonged notices, adverse reports, meetings and target dates over months amount to adequate hearing opportunity - Absence of managing partner abroad not valid excuse for non-response - Public interest in timely completion of essential infrastructure project mandates action. (Paras 24, 25)

(C) Arbitration and Conciliation Act, 1996 - Section 9 - Interim relief available pending arbitration - Concern over site material damage addressable therein. (Para 29)

Facts of the case:
Partnership firm awarded contract post tender acceptance. Supplemental agreements increased scope and value by 46-50%; time extended by 91% without penalty. Substantial work executed and paid; balance claimed unpaid due to pending measurements. Works offloaded to other agencies allegedly without consent, impacting progress. Show-cause notices issued for slow progress and non-mobilization; part termination due to urgency before safety inspection; full termination followed non-compliance.

Findings of Court:
Writ petition not maintainable; factual disputes unfit for writ adjudication; respondents followed contract process; protection to deposits for 12 weeks to initiate arbitration.

Issues: Maintainability of writ petition despite arbitration clause; violation of natural justice in termination; attribution of delay to petitioner despite offloading and site conditions; entitlement to complete balance work and payments.

Ratio Decidendi: Writ jurisdiction discretionary and not for private contractual disputes raising factual issues like work progress, defaults and payments when arbitration agreed; multiple prior opportunities negate natural justice claim; public duty to complete project timely justifies termination process.

Result: Writ petition dismissed; rule discharged; no costs.

Table of Content
1. writ petition challenges contract termination. (Para 1 , 2 , 3)
2. contract awarded; securities retained. (Para 4 , 5 , 6)
3. execution delays due to site conditions. (Para 7 , 8 , 9)
4. termination violates natural justice; writ maintainable. (Para 10 , 11 , 12)
5. termination complies with contract; arbitrate disputes. (Para 13 , 14 , 15 , 16 , 17)
6. writ jurisdiction limited in contracts. (Para 18 , 19 , 20 , 21 , 22 , 23)
7. multiple notices satisfy natural justice. (Para 24 , 25)
8. factual disputes unfit for writ. (Para 26 , 27)
9. contractual rights invoke private law. (Para 28)
10. arbitration offers interim relief. (Para 29)
11. writ not maintainable; relegate to arbitration. (Para 30 , 31)
12. petition dismissed without prejudice. (Para 32 , 33 , 34 , 35)

JUDGMENT :

HITEN S. VENEGAVKAR, J.

1. Rule. Rule is made returnable forthwith. With the consent of the parties, the petition is taken up for final disposal.

2. The present Writ Petition is filed under Article 226 of the Constitution of India by a partnership firm, M/s. MVV Satyanarayan, registered at Hyderabad, acting through its authorized signatory (hereinafter referred to as 'the petitioner'), against Respondent No.1 – the General Manager, Central Railway; Respondent No.2 – the Chief Administrative Officer (Construction), Central Railway; and Respondent No.3 – the Chief Engineer (Construction)/Central, Chhatrapati Shivaji Maharaj Terminus, Mumbai (hereinafter collectively referred to as 'the respondent railway authorities').

3. By way of the present petition, the petitioner challenges the communication dated 13.11.2025 issued by Respondent No.3, whereby a decision was taken to part terminate the contract/agreement dated 17.08.2024, and further challenges the termination notice dated 02.12.2025, on the grounds that the said actions are arbitrary, illegal, and contrary to the principles of natural justice. The petitioner has also prayed for a direction permitting it to complete the balance work as per the petitioner's letter dated 6th December 2025 and for a further direction to the respondents to release the payments for the work executed by the petitioner till date.

4. The factual matrix as pleaded by the petitioner in its memo of petition is as follows. The petitioner is a duly registered partnership firm based at Hyderabad and has been carrying on business since 03.09.1984. The petitioner claims to have been engaged in the field of civil contract works for Indian Railways, both Central and various State Governments and their instrumentalities, for over four and a half decades, with what it describes as an immaculate track record in meeting exact specifications and completing work within targeted timelines. In the process, it is stated that the petitioner has acquired specialized skills in the construction of bridges and other works for Indian Railways.

5. It is the case of the petitioner that Respondent No.2 had invited tenders for the construction of balance minor and major bridges at various places, construction of Road Under Bridges (RUBs) and drain works in connection with the Ahmednagar–Beed–Parli Vaidyanath New Broad Gauge Line Project, by issuing a Tender Notice dated 19.01.2024. The petitioner's tender was accepted by Respondent No.3, who issued a Letter of Acceptance dated 30.04.2024. Thereafter, an agreement came to be executed between Respondent No.2 and the petitioner on 17.08.2024. As per the terms of the Letter of Acceptance, the initial value of the work was Rs.3,74,65,7193/- (Rupees Thirty Seven Crores Forty Six Lakhs Fifty Seven Thousand One Hundred and Ninety Three only). The work was to be completed within twelve calendar months from the date of the Letter of Acceptance, making the completion date on or before 29.04.2025. Upon completion of the work, the petitioner was also obligated to provide a maintenance period of twelve calendar months, including through the monsoon season, under the defect liability clause.

6. The petitioner further st

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top