SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Cal) 209

IN THE HIGH COURT AT CALCUTTA
Sabyasachi Bhattacharyya, Supratim Bhattacharya, JJ.
The Orissa Minerals Development Company Limited – Petitioner
Versus
Jai Balaji Industries Limited – Respondent
F.M.A. No. 939 of 2012 With F.M.A. No. 941 of 2012
Decided On : 09-12-2025

Advocates Appeared:
For the Appellant : Mr. Suman Kumar Dutt, Sr. Adv., Mr. Kamal Kumar Chattopadhyay, Mr. Debdeep Sinha, Ms. Rini Chatterjee
For the Respondent: Mr. Jishnu Saha, Sr. Adv., Mr. Sourojit Dasgupta, Mr. Shaunak Mukhopadhyay, Mr. Tanay Agarwal, Ms. Darshana Sett, Ms. Priyansha Agarwal

The court affirmed that the lack of explicit contract terms for advance payments and preconditions led to a ruling of breach by the appellant, validating the Arbitral Tribunal's awards for excess purchases and loss of profits.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Section 37 - Appeal against arbitration awards - Respondent alleged breach of contract; appellant contended there was no breach due to unpaid advance payments. Arbitral Tribunal awarded compensation for excess purchases and loss of profits based on evidence provided. (Paras 1-6, 25-62)

(B) Breach of Contract - Requirement for advance payment and prior demands as pre-conditions were not evident in agreements; appellant's claims of waiver were not substantiated. (Paras 27-32, 36-44)

(C) Loss of Profits - Calculated based on evidence presented; no windfall permitted. (Paras 50-53)

(D) Jurisdiction and Authority - Appellate court cannot interfere unless awards shock the conscience or conflict with public policy. (Paras 60-62)

Facts of the case:
The disputes arose out of two agreements between the parties for the supply of iron ore, leading to arbitration after claims of non-supply and quality issues. Awards were based on excess amounts spent for alternate sourcing and loss of profits. (Paras 1-4)

Findings of Court:
The Arbitral Tribunal awarded compensation for excessive purchase costs and losses incurred, confirming that no breach was established due to the failure of advance payments, and the evidence for loss of profits was credible. (Paras 48-61)

Issues: The main issues included whether agreements required advance payment, the existence of waiver, the mandatory nature of supply, and whether the awards were justified under Section 34 of the Act. (Paras 25)

Ratio Decidendi: The court concluded that contractual obligations were not met by the appellant, who had no grounds for stopping supply. The Tribunal's calculations were factual and credible under established legal principles. (Paras 36-62)

Result: Appeals dismissed, affirming the awards of the Arbitral Tribunal.

Table of Content
1. introduction of case and factual background. (Para 1 , 2 , 3 , 4 , 5 , 6)
2. appellant's arguments opposing the tribunal's findings. (Para 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14)
3. evidence requirement for loss of profits. (Para 15 , 16 , 17)
4. jurisdiction and error of the tribunal. (Para 18 , 19 , 20)
5. respondent's position and reaffirmation of tribunal's decisions. (Para 21 , 22 , 23 , 24)
6. interpretation of contractual obligations. (Para 25 , 27 , 28 , 29 , 30 , 31)
7. findings on waiver of advance payment requirement. (Para 32 , 33 , 34 , 35)
8. compliance of payment methods and practices. (Para 36 , 37 , 38 , 39 , 40 , 41)
9. breach of contract due to stoppage of supply. (Para 42 , 43 , 44 , 45 , 46)
10. justification for excess amounts spent. (Para 47 , 48)
11. criteria and justification for loss of profits. (Para 49 , 50 , 51 , 52 , 53 , 54 , 55)
12. analysis of judicial interference parameters. (Para 56 , 57 , 58 , 59 , 60 , 61)
13. final ruling of the court. (Para 62 , 63 , 64 , 65 , 66)

JUDGMENT :

Sabyasachi Bhattacharyya, J.

1. The present appeals under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the 1996 Act”) arise out of judgments passed under Section 34 of the 1996 Act, affirming the awards passed in two arbitration proceedings between the same parties, which emanated from two substantially similar agreements entered into between the parties.

2. In case of F.M.A. No. 939 of 2012, an agreement was entered into on March 11, 2004, whereby the respondent/appellant, the Orissa Minerals Development Company Limited (“Orissa Minerals”, for short) agreed to supply to the respondent Jai Balaji sponge grade calibrated iron ore of 65% (Fe 05-18mm) to the tune of 7,000 Metric Tonnes per month for the period between April 1, 2004 and March 31, 2005, renewable subject to mutual acceptance of the parties as regards the terms and conditions.

3. In F.M.A. No. 941 of 2012, an agreement was entered into on August 13, 2003 for a period of one year from October 1, 2003 to September 30, 2004, whereby the respondent/appellant was to provide to the claimant/respondent iron ore of 63% (Fe 10-30mm) to the tune of 1,00,000 tonnes (± 25%) per annum.

4. Subsequently, the claimant/respondent raised disputes as to the quality of the products supplied. The respondent/appellant stopped supply on the ground of non-payment of the full amounts due for such iron ore after June, 2004 in both the cases.

5. This led to the claimant/respondent referring both the matters to arbitration, leading to the impugned awards being passed. The Arbitral Tribunal passed awards under the heads of excess amount spent in purchasing 43,413.70 MT of iron ore from other suppliers due to stoppage in supply by the appellant Orissa Minerals and on account of loss of profits. Simple interest was awarded in each of the cases from October 1, 2004 till realisation on the amount of excess amount spent in F.M.A. No. 941 of 2012 and from January 1, 2005 at the same rate, also for the excess amount spent in purchasing the balance iron ore in F.M.A. No. 939 of 2012. In both the awards, simple interest was also granted (@ 6% per annum in F.M.A. No. 941 of 2012 and @ 10% per annum in F.M.A. No. 939 of 2012) on the principal amounts of loss of profits, from the date of award till realisation.

6. Challenging the same, applications under Section 34 of the 1996 Act were preferred, which were dismissed, thereby affirming both the awards, leading to the present appeals under Section 37 of the said Act being filed.

7. Learned senior counsel appearing for the appellant argues that the Arbitral Tribunal erroneously arrived at the finding that there was a breach of contract on the part of the appellant, by overlooking the mandatory provisions in both the Agreements that the goods (iron ore) would only be supplied on 100% advance payment being made and a prior demand being made by the claimant/respondent, as well as that the claimant/respondent was to p

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top