SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(UK) 113

IN THE HIGH COURT OF UTTARAKHAND AT NAINITAL
MANOJ KUMAR GUPTA, CJ, SUBHASH UPADHYAY, J.
M/s Instapower Limited. -  Appellant
Versus
Gujrat State Electricity Corporation Limited And Another. - Respondents
APPEAL FROM ORDER No. 354 OF 2019
Decided On : 17-03-2026

Advocates Appeared:
For the Appellant : Mr. Karthik Jayashankar, learned counsel.
For the Respondent: Mr. V.K. Kohli, learned Senior Counsel assisted by Mr. I.P. Kohli, learned counsel.

The court emphasized that an arbitral award must be reasoned and address core contractual issues, with judicial intervention restricted to cases of patent illegality under Section 34 of the Arbitration and Conciliation Act.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 and Section 37 - Micro, Small and Medium Enterprises Development Act, 2006 - Appropriateness of Arbitral Award - The appeal challenges the Commercial Court's order setting aside the award based on non-consideration of critical contractual clauses pertaining to penalty and delay, resulting in the award being categorized under patent illegality. (Paras 1, 10, 12, 22, 30-32)

(B) Award Analysis - Procedural obligations - The Arbitral Tribunal failed to provide a reasoned analysis of delays attributable to parties and lawful deductions made by the respondent-company in accordance with the contract. (Paras 24-30)

(C) Limitation on Judicial Intervention - The scope of judicial interference with the arbitral award must adhere to the limited grounds defined under Section 34, emphasizing non-replacement of the Tribunal's findings by the courts. (Paras 13, 26, 32)

Facts of the case:
The appellant faced penalties for late delivery of goods due to delays in sample approvals by the respondent-company. An arbitral award favoring the appellant was set aside by the Commercial Court, leading to the current appeal.

Findings of Court:
The Commercial Court’s decision to set aside the award was affirmed due to the arbitral award's failure to address fundamental issues within the contract, constituting a patent illegality.

Issues: Whether the penalty for delay was justified under the contract and the role of the arbitral tribunal in adjudicating the core dispute.

Ratio Decidendi: The tribunal must evaluate whether delays were caused by the appellant or the respondent’s actions as per contract terms, mandating a detailed examination of penalty clauses and their application.

Result: Appeal is disposed of; matter remanded for fresh adjudication by Facilitation Council.

Table of Content
1. factual background regarding contract and supply (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10)
2. court's analysis of the arbitral proceedings (Para 11 , 12 , 20 , 21 , 22 , 23 , 24)
3. arguments regarding penalty and contractual obligations (Para 13 , 15 , 16 , 17 , 18 , 19)
4. legal framework governing judicial review of arbitral awards (Para 25 , 26 , 27 , 28 , 29 , 30 , 31)
5. conclusion and directions for fresh adjudication (Para 33 , 34 , 36 , 38 , 39)

JUDGMENT :

Manoj Kumar Gupta, CJ.

1. This Appeal, under Section 37 of the Arbitration and Conciliation Act, 1996 is directed against the judgment and order dated 10.07.2019 passed by the Additional District Judge (Commercial), Dehradun, in Arbitration Case No. 160/2016, whereby the petition filed by respondent no. 1 (hereinafter, referred to as the ‘respondent-company’), under Section 34 of the Arbitration and Conciliation Act, 1996 (for short, hereinafter referred to as the ‘Act’) was allowed, and the Arbitral Award dated 29.07.2016, rendered by the respondent no. 2-Uttarakhand State Micro and Small Enterprises Facilitation Council, Dehradun (for short ‘the Facilitation Council’), was set-aside.

2. The facts, giving rise to the present proceedings, in brief, are that the respondent-company invited tender for supply of 5350 numbers of 28 watt Retrofit Type Energy Efficient Tubelights (T5) for use at its Thermal Power Stations. Pursuant thereto, the bid of the appellant came to be accepted, and a Purchase Order was issued on 10.06.2008, which stipulated that the goods would be supplied within four months of the order. Clause 11 provided that delivery of goods would be made, after getting the sample approved from the respondent-company.

3. Clause 8 of the Purchase Order provides for imposition of penalty for late delivery. Clause 8 is as follows:-

8. Penalty for Late Delivery In case, the materials are not delivered within the period stipulated in the order, penalty shall be levied at ½% per week on the prices (End cost) subject to maximum 10% reckoned on the value of undelivered supplies.

Due consideration will be given for waival / levy of penalty only for the reasons absolutely beyond your control (Viz.Force Majeure conditions) for which documentary evidence will have to be provided. The request for extension in delivery giving reasons and supporting documents shall have to be made within one month on completion of the supply.”

4. Clause 9 relates to extension in the contractual delivery date and power of the respondent-company to consider extension of delivery period with or without penalty, if the appellant were able to prove by documentary evidence that the delivery got delayed on account of reasons beyond its control. Relevant part of Clause 9 is as follows :-

9. Extension in the Contractual Delivery Date It will be supplier's responsibility to ensure that goods are delivered within the stipulated delivery period. However, if on account of reasons beyond ones control as laid down in the DGS & D Force Majeure Conditions the Company may consider extension of delivery period with or without penalty & with or without statutory variations. However, delivery extensions will be considered only after execution of the order fully and upon submission of documentary evidence for the reasons of delay.

However, such extension will be subject to the following conditions shown hereunder.

a) ……

b) ……

c) ……”

5. The appellant, for the first time, submitted sample for approval on 08.07.2008, but which was not approved, and was rejected. On 25.08.2008, the appellant was asked to submit a new sample. The second sample was submitted on 06.10.2008, which was again not found to be suitable, and hence was rejected. On 10.10.2008, the appellant was informed about the rejection of the sample and also that it had not deposited Security Deposit, as per Clause 48. On 21.11.2008, the respondent-company issued a show-cause notice to the appellant, whereby it was required to show cause, as to wh

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top